Sector 5 - Wing J and K
Certificate SignedThane (M Corp.), Thane 400607 |Promoter: Agile Real Estate Pvt. Ltd.
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 2
- Unit types
- Types of 2 BHK, Types of 1 BHK, Types of 3 BHK385 units in all
- Address
- New S No. 79/5 Part 79/8 Part 79/9 Part 80/1 Part of Village Balkum, Kolshet Road, Village Balkum, ThanePIN 400607
- Designated bank account
- 85
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 29 Mar 2019
- Promised
- 30 Dec 2027
- Revised
- 30 Apr 2028
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700020264 | 29 Mar 2019 | 30 Dec 2027 | 30 Apr 2028 | Agile Real Estate Pvt. Ltd. | Project page |
2 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
4 of 385 units booked (1%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing J | Types of 2 BHK | 10,787.16 sq m · 1,16,112 sq ft | 236 | 1 |
| Wing K | Types of 1 BHK | 1,345.5 sq m · 14,483 sq ft | 31 | 1 |
| Wing K | Types of 2 BHK | 2,843.84 sq m · 30,611 sq ft | 62 | 1 |
| Wing K | Types of 3 BHK | 4,464.32 sq m · 48,053 sq ft | 56 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 160 filings listed on MahaRERA's project page
Legal
Show all 161 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 27 Mar 2019Source
- 2 Details of encumbrancesWing J and K.pdf · uploaded 27 Mar 2019Source
- 1 Copy of Layout Approval (in case of layout)Layout-1.pdf · uploaded 27 Mar 2019Source
- 1 Building Plan Approval (IOD)IOD.pdf · uploaded 27 Mar 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 27 Mar 2019Source
- 1 Declaration in FORM BWing J and K.pdf · uploaded 27 Mar 2019Source
- 1 Certificates of CA (Form 3)Wing J and K.pdf · uploaded 27 Mar 2019Source
- 1 Proforma of Allotment letterWing J and K.pdf · uploaded 27 Mar 2019Source
- 1 OtherWing JK.pdf · uploaded 27 Mar 2019Source
- 3 Copy of the legal title reportAddendum-2019.pdf · uploaded 6 Apr 2019Source
- 3 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 6 Apr 2019Source
- 1 Form 2ASector 5 Wing J and K(1).pdf · uploaded 29 Jun 2019Source
- 2 Form 2ASector 5 Wing J and K.pdf · uploaded 6 Aug 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5)Sector 5 JK.pdf · uploaded 30 Sep 2019Source
- 3 Form 2ASector 5 Wing J and K.pdf · uploaded 16 Oct 2019Source
- 2 Proforma of Allotment letterProject Sector5 Wing JK.pdf · uploaded 4 Nov 2019Source
- 4 Form 2ASector 5 Wing J and K.pdf · uploaded 16 Jan 2020Source
- 5 Form 2ASector 5 Wing J and K-March 2020.pdf · uploaded 14 Sep 2020Source
- 6 Form 2ASector 5 Wing J and K-June 2020.pdf · uploaded 14 Sep 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Expansia J - K.pdf · uploaded 9 Oct 2020Source
- 7 Form 2ASector 5 Wing J and K-Sept2020.pdf · uploaded 29 Oct 2020Source
- 8 Form 2ASector 5 Wing J and K-Dec 2020 signed.pdf · uploaded 10 Feb 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sector 5 Wing J and K-Mar2021.pdf · uploaded 7 May 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Wing JK.pdf · uploaded 20 Jul 2021Source
- 1 Declaration about Commencement Certificatesector 5 - Jk.pdf · uploaded 4 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Tower J K Sector 5.pdf · uploaded 5 Oct 2021Source
- 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sector 5 Wing J and K.pdf · uploaded 7 Oct 2021Source
- 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sector 5 JK.pdf · uploaded 21 Apr 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Expansia Tower JK.pdf · uploaded 1 Oct 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)1 Annual Audit Report of Statutory CA (Form 5) (7).pdf · uploaded 20 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing J K.pdf · uploaded 23 Feb 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing J K.pdf · uploaded 23 Feb 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Sector 5 JK.pdf · uploaded 23 Jun 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Sector 5 JK.pdf · uploaded 23 Jun 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing JK.pdf · uploaded 25 Jul 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing JK.pdf · uploaded 25 Jul 2023Source
- 2 Certificates of CA (Form 3)Sector 5 Wing JK.pdf · uploaded 25 Jul 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Expansia JK.pdf · uploaded 30 Sep 2023Source
- 3 Certificates of CA (Form 3)Sector 5 Wing J and K.pdf · uploaded 20 Oct 2023Source
- 4 Certificates of CA (Form 3)Sector 5 Wing J and K.pdf · uploaded 19 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5-Wing JK.pdf · uploaded 20 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5-Wing JK.pdf · uploaded 20 Apr 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5-Wing JK.pdf · uploaded 20 Apr 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 - Wing J K Sign.pdf · uploaded 20 Apr 2024Source
- 5 Certificates of CA (Form 3)Sector 5 Wing J K.pdf · uploaded 20 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Sector 5 Wing JK.pdf · uploaded 14 Jun 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5-Wing JK.pdf · uploaded 20 Jul 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)wing J and K.pdf · uploaded 20 Jul 2024Source
- 6 Certificates of CA (Form 3)Expansia JK.pdf · uploaded 20 Jul 2024Source
- 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 JK.pdf · uploaded 20 Oct 2024Source
- 16 Certificates of CA (Form 3)Sector 5 Wing JK_241018_122209.pdf · uploaded 20 Oct 2024Source
- 18 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 JK.pdf · uploaded 20 Oct 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Sector 5 JK.pdf · uploaded 21 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 JK.pdf · uploaded 20 Jan 2025Source
- 1 Certificates of CA (Form 3)Sector 5 wing J and K.pdf · uploaded 20 Jan 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Wing JK.pdf · uploaded 20 Jan 2025Source
- 10 Certificates of CA (Form 3)CA certificate - Expansia-J-K RERA QE 31-12-2021.pdf · uploaded 17 Feb 2025Source
- 9 Certificates of CA (Form 3)CA Certificate - Sep21 Tower JK.pdf · uploaded 17 Feb 2025Source
- 7 Certificates of CA (Form 3)CA Certificate - Sector 5 -Tower -J,K- Rera Qtr -Feb21.pdf · uploaded 17 Feb 2025Source
- 6 Certificates of CA (Form 3)CA Certificate - Expansia -Tower J- K - 30-11-2020.pdf · uploaded 17 Feb 2025Source
- 5 Certificates of CA (Form 3)Expansia JK.pdf · uploaded 17 Feb 2025Source
- 4 Certificates of CA (Form 3)CA Certificate Sector 5 J, K_Dec 19.pdf · uploaded 17 Feb 2025Source
- 3 Certificates of CA (Form 3)CA Certificate Sector 5-J,K.pdf · uploaded 17 Feb 2025Source
- 2 Certificates of CA (Form 3)CA Certificate_Sector 5-J,K_June 2019.pdf · uploaded 17 Feb 2025Source
- 8 Certificates of CA (Form 3)CA Certificate Expansia Tower JK - 31May21.pdf · uploaded 17 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Wing JK June19.pdf · uploaded 21 Feb 2025Source
- 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5-Wing JK.pdf · uploaded 21 Feb 2025Source
- 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 JK.pdf · uploaded 21 Feb 2025Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing J K.pdf · uploaded 21 Feb 2025Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing JK.pdf · uploaded 21 Feb 2025Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5- Wing JK.pdf · uploaded 21 Feb 2025Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing JK.pdf · uploaded 21 Feb 2025Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing JK dec21.pdf · uploaded 21 Feb 2025Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector-5-Wing JK sept 21.pdf · uploaded 21 Feb 2025Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing JK may21.pdf · uploaded 21 Feb 2025Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)SEctor 5 JK feb21.pdf · uploaded 21 Feb 2025Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sec 5 JK nov2020.pdf · uploaded 21 Feb 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)sector 5 - wing JK feb2020.pdf · uploaded 21 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 -wing JK dec19.pdf · uploaded 21 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 JK sept19.pdf · uploaded 21 Feb 2025Source
- 15 Certificates of CA (Form 3)Sector 5 Wing JK.pdf · uploaded 21 Feb 2025Source
- 14 Certificates of CA (Form 3)Sector 5 J K Dec22.pdf · uploaded 21 Feb 2025Source
- 13 Certificates of CA (Form 3)Tower JK.pdf · uploaded 21 Feb 2025Source
- 12 Certificates of CA (Form 3)Sector 5 Wing J-K.pdf · uploaded 21 Feb 2025Source
- 11 Certificates of CA (Form 3)Sector 5 Wing J-K March22.pdf · uploaded 21 Feb 2025Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing JK.pdf · uploaded 21 Feb 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)JK nov2020.pdf · uploaded 21 Feb 2025Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5- Wing JK.pdf · uploaded 21 Feb 2025Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing JK.pdf · uploaded 21 Feb 2025Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing J K.pdf · uploaded 21 Feb 2025Source
- 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 JK.pdf · uploaded 21 Feb 2025Source
- 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing J and K.pdf · uploaded 21 Feb 2025Source
- 17 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing J and K.pdf · uploaded 21 Feb 2025Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)JK dec2021.pdf · uploaded 21 Feb 2025Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)JK Sept2021.pdf · uploaded 21 Feb 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)JK jun2021.pdf · uploaded 21 Feb 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)JK feb2021.pdf · uploaded 21 Feb 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)JK jul2020.pdf · uploaded 21 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)JK dec19.pdf · uploaded 21 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)JK sept19.pdf · uploaded 21 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)JK jun19.pdf · uploaded 21 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Sector 5 Wing JK.pdf · uploaded 20 Apr 2025Source
- 1 Certificates of CA (Form 3)EXPANSIA jk.pdf · uploaded 20 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Sector 5 Wing JK EC.pdf · uploaded 20 Apr 2025Source
- Form 2A (FY 2024-2025)Sector 5 JK.pdf · uploaded 12 Aug 2025Source
- Form 5 (FY 2024-2025)Sector 5- Wing JK.pdf · uploaded 24 Sep 2025Source
- Form 1Sector 5 Wing JK AC.pdf · uploaded 31 Oct 2025Source
- Form 2Sector 5 Wing JK EC.pdf · uploaded 31 Oct 2025Source
- Form 3Sector 5-JK.pdf · uploaded 31 Oct 2025Source
- Disclosure of Sold and Booked InventorySector 5- Wing J and K.pdf · uploaded 31 Oct 2025Source
- Form 2A (FY 2025-2026)Form 2A Sector 5 Wing JK.pdf · uploaded 22 Jun 2026Source
- Form 5 (FY 2025-2026)Sector 5 JK Tower.pdf · uploaded 16 Sep 2026Source
Technical
Technical (Architect)
- DocumentSector 5-Wing JK.pdf · uploaded 30 Sep 2024Source
- DocumentSector 5 JK.pdf · uploaded 20 Oct 2024Source
- DocumentSector 5 JK.pdf · uploaded 20 Jan 2025Source
- DocumentWing JK June19.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 JK sept19.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 -wing JK dec19.pdf · uploaded 21 Feb 2025Source
- Documentsector 5 - wing JK feb2020.pdf · uploaded 21 Feb 2025Source
- DocumentSec 5 JK nov2020.pdf · uploaded 21 Feb 2025Source
- DocumentSEctor 5 JK feb21.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing JK may21.pdf · uploaded 21 Feb 2025Source
- DocumentSector-5-Wing JK sept 21.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing JK dec21.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing JK.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5- Wing JK.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing JK.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing J K.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 JK.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5-Wing JK.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing JK.pdf · uploaded 20 Apr 2025Source
Technical (Engineer)
- Documentwing J and K.pdf · uploaded 3 Oct 2024Source
- DocumentSector 5 JK.pdf · uploaded 20 Oct 2024Source
- DocumentWing JK.pdf · uploaded 20 Jan 2025Source
- DocumentJK jun19.pdf · uploaded 21 Feb 2025Source
- DocumentJK sept19.pdf · uploaded 21 Feb 2025Source
- DocumentJK dec19.pdf · uploaded 21 Feb 2025Source
- DocumentJK jul2020.pdf · uploaded 21 Feb 2025Source
- DocumentJK nov2020.pdf · uploaded 21 Feb 2025Source
- DocumentJK feb2021.pdf · uploaded 21 Feb 2025Source
- DocumentJK jun2021.pdf · uploaded 21 Feb 2025Source
- DocumentJK Sept2021.pdf · uploaded 21 Feb 2025Source
- DocumentJK dec2021.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing JK.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5- Wing JK.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing JK.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing J K.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 JK.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing J and K.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing J and K.pdf · uploaded 21 Feb 2025Source
- DocumentSector 5 Wing JK EC.pdf · uploaded 20 Apr 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Thane (M Corp.), Thane taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- New S No 79-5 Pt 79-8 Pt 80-1 Pt of Village Balkum
- South
- New S No 79-8 Pt 79-9 Pt 80-1 Pt of Village Balkum
- East
- New S No 79-8 Pt 79-9 Pt 80-1 Pt of Village Balkum
- West
- New S No 79-5 Pt 79-8 Pt 80-1 Pt of Village Balkum
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Engineer | Zankar Borse | — |
Source: MahaRERA project page. Contact details are not shown.