Skip to content

S4 · Pushpanjali Residency Phase III

Thane (M Corp.) · RERA P51700008949

IDBLD_07187030 floorsExtended 36 mo
30Sanctioned habitable floorsregistration certificate
31 Dec 2025Revised completionpromised 30 Dec 2022
139 of 142Units bookedMahaRERA project page

Floors

30 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51700008949 · registered 19 Aug 2017
Promised completion
30 Dec 2022
Revised completion
31 Dec 2025
Sanctioned habitable floors
30
ProjectId
13,940
ProjectName
PUSHPANJALI RESIDENCY PHASE III
TotalUnitCount
145
ProjectBuildingId
1,63,532
BuildingNameNumber
S4
FsiWithSanctionSqmts
St.+ 30th Floors
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
145
ProjectRegistartionNo
P51700008949
ProjectBuildingWingsId
1,66,989
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
S4
NoOfBuildingWingFloorProposed
31
NoOfBuildingWingFloorHabitable
30
NoOfBuildingWingFloorSanctioned
31

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1 BHK TYPE 137.5 m² (404 sq.ft)6059
1 BHK TYPE 236.8 m² (396 sq.ft)98
1 BHK TYPE 338.5 m² (414 sq.ft)99
2 BHK TYPE 148.8 m² (525 sq.ft)1919
2 BHK TYPE 250.5 m² (544 sq.ft)2020
2 BHK TYPE 356.5 m² (608 sq.ft)2524
Total142139
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology