Om Residency A Wing · Om Residency

Thane (M Corp.) · RERA P51700008682

IDBLD_0117759 floorsCompleted
9Sanctioned habitable floorsregistration certificate
29 Dec 2020Revised completionpromised 30 Jun 2019

Floors

9 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51700008682 · registered 19 Aug 2017
Promised completion
30 Jun 2019
Revised completion
29 Dec 2020
Sanctioned habitable floors
9

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK30.1 m² (324 sq.ft)6not published
1BHK31.1 m² (335 sq.ft)14not published
1BHK33.9 m² (365 sq.ft)6not published
1BHK34.7 m² (374 sq.ft)6not published
1BHK40.3 m² (434 sq.ft)6not published
2BHK47.6 m² (513 sq.ft)6not published
SHOP170.2 m² (756 sq.ft)1not published
SHOP1018.7 m² (201 sq.ft)1not published
SHOP1120.9 m² (225 sq.ft)1not published
SHOP1214.9 m² (160 sq.ft)1not published
Show all 19 unit typesShow fewer unit types
TypeCarpet areaUnitsBooked
SHOP1314.4 m² (155 sq.ft)1not published
SHOP2163 m² (1,754 sq.ft)1not published
SHOP323.8 m² (256 sq.ft)1not published
SHOP424.4 m² (263 sq.ft)1not published
SHOP5168.6 m² (1,814 sq.ft)1not published
SHOP618.7 m² (201 sq.ft)1not published
SHOP719.6 m² (211 sq.ft)1not published
SHOP819 m² (205 sq.ft)1not published
SHOP914.3 m² (154 sq.ft)1not published
Total57

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered0002
Open Space0001

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor60%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises80%
  • Sanitary Fittings within the flats / premises50%
Show all 11 activitiesShow fewer activities
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks95%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.95%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.75%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology