Nakhawa Enclave
Certificate SignedThane (M Corp.), Thane 400602 |Promoter: Sai Shrushti Enterprises
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 2BHK, 5BHK & more, Office space, Shop31 units in all
- Address
- C.t.s. No.38 Tika No.21, Opp Naupada Police Station M.g. Road, NaupadaPIN 400602
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Oct 2023
The latest completion date on record passed 3 years ago.
- Registered
- 29 Aug 2022
- Promised
- 31 Oct 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700046673 | 29 Aug 2022 | 31 Oct 2023 | 31 Oct 2023 | Sai Shrushti Enterprises | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Nakhawa Enclave | 8 | 31 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
31 of 31 units booked (100%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 53.81 sq m · 579 sq ft | 4 | 4 |
| 2BHK | 63.15 sq m · 680 sq ft | 4 | 4 |
| 2BHK | 64.15 sq m · 691 sq ft | 4 | 4 |
| 5BHK & more | 182.43 sq m · 1,964 sq ft | 1 | 1 |
| Office space | 329.98 sq m · 3,552 sq ft | 13 | 13 |
| Shop | 112 sq m · 1,206 sq ft | 5 | 5 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 47 filings listed on MahaRERA's project page
Finance
Legal
- Declaration Form BForm B_Promoter.pdf · uploaded 9 Aug 2022Source
- Declaration Form BForm B_Co Promoter.pdf · uploaded 9 Aug 2022Source
- Legal Title reportLegal Title Report.pdf · uploaded 18 Aug 2022Source
- Legal Title reportSearch Report.pdf · uploaded 18 Aug 2022Source
- Other – LegalForm 4 architect certificate.pdf · uploaded 10 Mar 2025Source
Show all 48 documentsShow fewer documents
Migrated
- 1 PAN Card1 Sai Shrushti PAN CARD.pdf · uploaded 9 Aug 2022Source
- 1 a Details of encumbrances concerned to FinanceLetter of Encumbrance_FInance.pdf · uploaded 9 Aug 2022Source
- 1 b Details of encumbrances concerned to LegalLetter of Encumbrances_Legal.pdf · uploaded 9 Aug 2022Source
- 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 9 Aug 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentLayout Plan_Building.pdf · uploaded 9 Aug 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 9 Aug 2022Source
- 1 Declaration about Commencement CertificateForm D_Declaration to CC.pdf · uploaded 9 Aug 2022Source
- 1 Declaration in FORM BForm B_Promoter.pdf · uploaded 9 Aug 2022Source
- 2 Declaration in FORM BForm B_Co Promoter.pdf · uploaded 9 Aug 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect_Certificate.pdf · uploaded 9 Aug 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 9 Aug 2022Source
- 1 CERSAI detailsCersai Search Report.pdf · uploaded 9 Aug 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3_CA Certificate.pdf · uploaded 9 Aug 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account declaration.pdf · uploaded 9 Aug 2022Source
- 1 Other – TechnicalNakhawa Enclave_NAREDCO Certificate.pdf · uploaded 9 Aug 2022Source
- 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 18 Aug 2022Source
- 2 Copy of the legal title reportSearch Report.pdf · uploaded 18 Aug 2022Source
- 1 Deviation Report with respect to Allotment letterDeviation Sheet Allotment Letter_Declaration.pdf · uploaded 18 Aug 2022Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Sheet Sale Agreement_Declaration.pdf · uploaded 18 Aug 2022Source
- 1 Proforma of Allotment letterAgreement for Sale_Nakhawa Enclave_as per Rules.pdf · uploaded 20 Aug 2022Source
- 2 Proforma of Allotment letterProforma allotment letter.pdf · uploaded 20 Aug 2022Source
- 2 Building Plan Approval / NA Order for plotted developmentReversed Plan New Pdf.pdf · uploaded 25 Oct 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentCC 1.pdf · uploaded 25 Oct 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOCCUPATION CERTIFICATE.pdf · uploaded 25 Oct 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form_1_Nakhawa.pdf · uploaded 8 Mar 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Form_3_NAKHAWA.pdf · uploaded 8 Mar 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form_2_Nakhawa.pdf · uploaded 8 Mar 2025Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Nakhwa Society Certificate.pdf · uploaded 8 Mar 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold_Nakhawa.pdf · uploaded 8 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form_2A_Nakhawa.pdf · uploaded 8 Mar 2025Source
- 1 Other – LegalForm 4 architect certificate.pdf · uploaded 10 Mar 2025Source
- 1 Other – FinanceForm 4 architect certificate.pdf · uploaded 10 Mar 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Thane (M Corp.), Thane taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Tropical Elite
- South
- Nav Darshan Soc
- East
- Panama Blade Co
- West
- M G Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Godbole Mukadam & Associates | — |
| Chartered accountant | Hemant Shetty & Co | — |
| Chartered accountant | Shetty & Shetty | — |
| Engineer | Ajay Mahale | — |
Source: MahaRERA project page. Contact details are not shown.