Skip to content
Deedo home
Menu

Building 4 - Omkara · Cosmos Meluha

Thane (M Corp.) · RERA P51700009729

IDBLD_0118319 floorsCompleted
9Sanctioned habitable floorsregistration certificate
30 Mar 2022Promised completion

Floors

9 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51700009729 · registered 22 Aug 2017
Promised completion
30 Mar 2022
Sanctioned habitable floors
9

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK41.8 m² (450 sq.ft)6not published
1BHK41.9 m² (451 sq.ft)6not published
1BHK45.9 m² (494 sq.ft)2not published
1BHK48.8 m² (526 sq.ft)2not published
Shop134 m² (1,442 sq.ft)1not published
Shop177 m² (1,905 sq.ft)2not published
Shop178.9 m² (1,926 sq.ft)1not published
Total20

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered0001
Open Space0000

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises0%
Show all 11 activitiesShow fewer activities
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology