Shiv Sai Balaji Buildcon
Revocation on recordThane, India
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 1RK, Shop91 units in all
- Address
- Cts No 223, Village Aajade Golivali, DombivaliPIN 421201
- Designated bank account
- 59
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 1 Dec 2023
The latest completion date on record passed 2 years and 10 months ago.
- Registered
- 25 Aug 2021
- Promised
- 1 Dec 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700030499 | 25 Aug 2021 | 1 Dec 2023 | 1 Dec 2023 | — | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Shiv Ganga Apartment | 46 | 91 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 of 91 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 31.71 sq m · 341 sq ft | 56 | 0 |
| 1RK | 20.53 sq m · 221 sq ft | 28 | 0 |
| Shop | 9.66 sq m · 104 sq ft | 7 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
0 documents held by Deedo, 16 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card.pdf · uploaded 10 Aug 2021Source
Legal
Migrated
- 1 PAN Cardpan card.pdf · uploaded 10 Aug 2021Source
- 1 Copy of the legal title reporttitle.pdf · uploaded 10 Aug 2021Source
- 1 Details of encumbrancesenc.pdf · uploaded 10 Aug 2021Source
- 1 Copy of Layout Approval (in case of layout)PLAN COPY.PDF · uploaded 10 Aug 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentPERMISSION.pdf · uploaded 10 Aug 2021Source
Show all 16 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentPERMISSION.pdf · uploaded 10 Aug 2021Source
- 1 Declaration about Commencement Certificated from.pdf · uploaded 10 Aug 2021Source
- 1 Declaration in FORM BAFFIDAVIT.pdf · uploaded 10 Aug 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA.pdf · uploaded 10 Aug 2021Source
- 1 Proforma of Allotment letterAGREEMENT FOR SALE.pdf · uploaded 10 Aug 2021Source
- 2 Proforma of Allotment letterallotment.pdf · uploaded 10 Aug 2021Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Registration revokedMatched by RERA number
Registration revoked / ab initio void: VINAYAK VATIKA BUILDERS AND DEVELOPERS
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Golden Dimention | — |
| Chartered accountant | Scg Associate | — |
| Engineer | Golden Dimention | — |
Source: MahaRERA project page. Contact details are not shown.