Elegant City Bliss
Certificate SignedShirol, Thane 421602 |Promoter: Neele Buildcon LLP
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 5
- Unit types
- 1BHK, 2BHK, Shop, 1RK344 units in all
- Address
- 1390/A/1, 1390/A/2, 1390/A/3, NH-3, MUMBAI NASHIK HIGHWAY, ShahapurPIN 421602
- Designated bank account
- 51
- Developed in phases
- Yes
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 1 Dec 2020
- Promised
- 30 Jun 2028
- Revised
- 30 Oct 2028
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51700027320 | 1 Dec 2020 | 30 Jun 2028 | 30 Oct 2028 | Neele Buildcon LLP | Project page |
5 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
57 of 344 units booked (17%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Bliss-1 | 1BHK | 31.9 sq m · 343 sq ft | 2 | 2 |
| Bliss-1 | 1BHK | 32.44 sq m · 349 sq ft | 3 | 3 |
| Bliss-1 | 1BHK | 37.49 sq m · 404 sq ft | 1 | 1 |
| Bliss-1 | 1BHK | 37.94 sq m · 408 sq ft | 22 | 5 |
| Bliss-1 | 1BHK | 52.88 sq m · 569 sq ft | 1 | 0 |
| Bliss-1 | 2BHK | 44.82 sq m · 482 sq ft | 2 | 2 |
| Bliss-1 | 2BHK | 44.9 sq m · 483 sq ft | 1 | 1 |
| Bliss-1 | 2BHK | 46.77 sq m · 503 sq ft | 1 | 0 |
Show all 51 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Bliss-1 | 2BHK | 52.3 sq m · 563 sq ft | 1 | 1 |
| Bliss-1 | 2BHK | 52.48 sq m · 565 sq ft | 11 | 6 |
| Bliss-1 | 2BHK | 53 sq m · 570 sq ft | 1 | 1 |
| Bliss-1 | 2BHK | 53.02 sq m · 571 sq ft | 1 | 1 |
| Bliss-1 | 2BHK | 53.18 sq m · 572 sq ft | 10 | 3 |
| Bliss-1 | Shop | 16.79 sq m · 181 sq ft | 1 | 1 |
| Bliss-1 | Shop | 18.15 sq m · 195 sq ft | 1 | 1 |
| Bliss-1 | Shop | 18.25 sq m · 196 sq ft | 1 | 1 |
| Bliss-1 | Shop | 18.99 sq m · 204 sq ft | 1 | 1 |
| Bliss-1 | Shop | 25.35 sq m · 273 sq ft | 2 | 2 |
| Bliss-1 | Shop | 27.44 sq m · 295 sq ft | 1 | 0 |
| Bliss-1 | Shop | 31.87 sq m · 343 sq ft | 1 | 0 |
| Bliss-1 | Shop | 31.88 sq m · 343 sq ft | 1 | 0 |
| Bliss-2 | 1BHK | 31.9 sq m · 343 sq ft | 14 | 0 |
| Bliss-2 | 1RK | 32.44 sq m · 349 sq ft | 14 | 0 |
| Bliss-2 | 2BHK | 39.68 sq m · 427 sq ft | 1 | 0 |
| Bliss-2 | 2BHK | 42.76 sq m · 460 sq ft | 1 | 0 |
| Bliss-2 | 2BHK | 42.79 sq m · 461 sq ft | 1 | 0 |
| Bliss-2 | 2BHK | 44.82 sq m · 482 sq ft | 7 | 0 |
| Bliss-2 | 2BHK | 44.9 sq m · 483 sq ft | 7 | 0 |
| Bliss-2 | 2BHK | 46.7 sq m · 503 sq ft | 7 | 0 |
| Bliss-2 | 2BHK | 46.77 sq m · 503 sq ft | 7 | 0 |
| Bliss-2 | Shop | 16.7 sq m · 180 sq ft | 1 | 0 |
| Bliss-2 | Shop | 18.15 sq m · 195 sq ft | 1 | 0 |
| Bliss-2 | Shop | 18.15 sq m · 195 sq ft | 1 | 0 |
| Bliss-2 | Shop | 18.9 sq m · 203 sq ft | 1 | 0 |
| Bliss-2 | Shop | 25.26 sq m · 272 sq ft | 1 | 0 |
| Bliss-2 | Shop | 25.27 sq m · 272 sq ft | 1 | 0 |
| Bliss-2 | Shop | 27.41 sq m · 295 sq ft | 1 | 0 |
| Bliss-2 | Shop | 31.87 sq m · 343 sq ft | 1 | 0 |
| Bliss-2 | Shop | 31.88 sq m · 343 sq ft | 1 | 0 |
| Bliss-3 | 1BHK | 28.64 sq m · 308 sq ft | 11 | 6 |
| Bliss-3 | 1BHK | 28.65 sq m · 308 sq ft | 31 | 6 |
| Bliss-3 | 1BHK | 37.01 sq m · 398 sq ft | 15 | 1 |
| Bliss-3 | 1BHK | 39.37 sq m · 424 sq ft | 13 | 0 |
| Bliss-4 | 1BHK | 28.64 sq m · 308 sq ft | 7 | 1 |
| Bliss-4 | 1BHK | 28.65 sq m · 308 sq ft | 35 | 2 |
| Bliss-4 | 1BHK | 37.01 sq m · 398 sq ft | 14 | 1 |
| Bliss-4 | 1BHK | 39.37 sq m · 424 sq ft | 14 | 0 |
| Bliss-5 | 1BHK | 28.64 sq m · 308 sq ft | 8 | 4 |
| Bliss-5 | 1BHK | 28.65 sq m · 308 sq ft | 34 | 1 |
| Bliss-5 | 1BHK | 37.01 sq m · 398 sq ft | 14 | 1 |
| Bliss-5 | 1BHK | 39.37 sq m · 424 sq ft | 14 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 119 filings listed on MahaRERA's project page
Show all 120 documentsShow fewer documents
Migrated
- 1 Other1390 FIRE NOC -min.pdf · uploaded 25 Nov 2020Source
- 1 Copy of the legal title reportTITLE CERTIFICATE_Compressed.pdf · uploaded 27 Nov 2020Source
- 1 Details of encumbrancesEncumbrances Neele.pdf · uploaded 27 Nov 2020Source
- 1 Copy of Layout Approval (in case of layout)Layout plan.pdf · uploaded 27 Nov 2020Source
- 1 Building Plan Approval / NA Order for plotted developmentbuilding plan-1.pdf · uploaded 27 Nov 2020Source
- 2 Building Plan Approval / NA Order for plotted developmentbuilding plan-2.pdf · uploaded 27 Nov 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)NEELE BUILDCON LLP FORM -3 REGISTRATION_Compressed.pdf · uploaded 27 Nov 2020Source
- 1 Proforma of Allotment letterAgreement and Allotement Neele.pdf · uploaded 27 Nov 2020Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT CC.pdf · uploaded 1 Sep 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Rera 31_03_2021_Compressed.pdf · uploaded 1 Sep 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Rera 30_06_2021_Compressed.pdf · uploaded 1 Sep 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineers certificate 31-03-2021.pdf · uploaded 1 Sep 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate 30-06-2021.pdf · uploaded 1 Sep 2021Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form-3 CA Bliss as on 31-03-2021_Compressed.pdf · uploaded 1 Sep 2021Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form-3 CA Bliss as on 30-06-2021_Compressed.pdf · uploaded 1 Sep 2021Source
- 1 Disclosure of sold/ booked inventorySold and booked inventory 30-06-2021_Compressed.pdf · uploaded 3 Sep 2021Source
- 2 Proforma of Allotment letterAGREEMENT FOR SALE Rera upload draft.pdf · uploaded 26 Oct 2021Source
- 3 Proforma of Allotment letterALLOTMENT LETTER New Rera Coustmors.pdf · uploaded 26 Oct 2021Source
- 4 Proforma of Allotment letterAGREEMENT FOR SALE Rera upload draft.pdf · uploaded 26 Oct 2021Source
- 5 Proforma of Allotment letterALLOTMENT LETTER New Rera Coustmors.pdf · uploaded 26 Oct 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form-5.pdf · uploaded 31 Dec 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_30-09-2021.pdf · uploaded 3 Oct 2022Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1_Compressed.pdf · uploaded 3 Oct 2022Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1_Compressed.pdf · uploaded 3 Oct 2022Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2_Buildcon_30-09-2021_Compressed.pdf · uploaded 3 Oct 2022Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Compressed.pdf · uploaded 3 Oct 2022Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Compressed.pdf · uploaded 3 Oct 2022Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Neele_30092021_Compressed.pdf · uploaded 3 Oct 2022Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Neele_31122021_Compressed.pdf · uploaded 3 Oct 2022Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Neele_31032022_Compressed.pdf · uploaded 3 Oct 2022Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Neele_30062022.pdf · uploaded 2 Feb 2023Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Neele_30062022_Compressed.pdf · uploaded 2 Feb 2023Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Neele_30092022.pdf · uploaded 3 Feb 2023Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_Neele_30092022-compressed.pdf · uploaded 3 Feb 2023Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Neele_30062022_compressed.pdf · uploaded 10 Feb 2023Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Neele_30092022_compressed.pdf · uploaded 10 Feb 2023Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1_Neele_31122022.pdf · uploaded 14 Feb 2023Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2_Neele_31122022_Uploaded.pdf · uploaded 14 Feb 2023Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3_Neele_31122022_Uploaded.pdf · uploaded 14 Feb 2023Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_2023-03-31 (1).pdf · uploaded 7 Feb 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_2023-06-30.pdf · uploaded 7 Feb 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Neele Builcom 31032023.pdf · uploaded 15 Feb 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Neele Buildcom 30062023.pdf · uploaded 15 Feb 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Neele Buildcom 30092023.pdf · uploaded 15 Feb 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_2023-09-30.pdf · uploaded 7 Mar 2024Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_2023-12-31 (1).pdf · uploaded 7 Mar 2024Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Meele Buildcon LLP 30_06_2023_compressed.pdf · uploaded 7 Mar 2024Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Neele Buildcon LLP 30_09_2023_compressed.pdf · uploaded 7 Mar 2024Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Neele Buildcon LLP 31_12_2023.pdf · uploaded 7 Mar 2024Source
- 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Neele Buildcon LLP 31_03_2023_compressed.pdf · uploaded 7 Mar 2024Source
- 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Neele Buildcon LLP 31_12_2023.pdf · uploaded 13 Mar 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form 2A - FY -2020-21.pdf · uploaded 13 Mar 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A -FY 2021-22.pdf · uploaded 13 Mar 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A - FY 2022-23.pdf · uploaded 13 Mar 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Neele Builcom 31032023_compressed.pdf · uploaded 28 Mar 2024Source
- 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Neele Builcom 30062023_compressed.pdf · uploaded 28 Mar 2024Source
- 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Neele Builcom 30092023Compressed.pdf · uploaded 28 Mar 2024Source
- 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Neele Builcom 31122023 Compressed.pdf · uploaded 28 Mar 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_31-03-2024.pdf · uploaded 6 May 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_30-06-2024.pdf · uploaded 6 May 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_30-09-2024.pdf · uploaded 6 May 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_31-12-2024.pdf · uploaded 6 May 2025Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1_Buildcon_31-03-2025.pdf · uploaded 6 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 -31032024.pdf · uploaded 7 May 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - 30062024.pdf · uploaded 7 May 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - 30092024.pdf · uploaded 7 May 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - 31122024.pdf · uploaded 7 May 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - 31032025.pdf · uploaded 7 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 31032024 Final.pdf · uploaded 12 May 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30062024 Final.pdf · uploaded 12 May 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30092024 Final.pdf · uploaded 12 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3 - neele - 31122024_compressed.pdf · uploaded 16 May 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3 - neele - 31032025_compressed.pdf · uploaded 16 May 2025Source
- Form 1FORM-1 Buildcon 30062025.pdf · uploaded 19 Jul 2025Source
- Form 2FORM-2 30062025 Engineer.pdf · uploaded 19 Jul 2025Source
- Form 3Form3 Neele 30062025_compressed.pdf · uploaded 19 Jul 2025Source
- Disclosure of Sold and Booked InventoryDisclosure Of Sold and Unsold Inventory 30062025.pdf · uploaded 19 Jul 2025Source
- Form 5 (FY 2021-2022)System Generated 21-22 Form 5 (1).pdf · uploaded 28 Jul 2025Source
- Form 5 (FY 2022-2023)System Generated 22-23 Form 5 (1).pdf · uploaded 28 Jul 2025Source
- Form 5 (FY 2023-2024)System Generated 23-24 Form 5 (1).pdf · uploaded 28 Jul 2025Source
- Form 2A (FY 2023-2024)Form 2A 31st March 2024.pdf · uploaded 30 Jul 2025Source
- Form 2A (FY 2024-2025)Form 2A 31st March 2025.pdf · uploaded 30 Jul 2025Source
- Form 5 (FY 2024-2025)Neele Form 5 Signed Copy.pdf · uploaded 30 Sep 2025Source
- Withdrawal Update Form 1Form 1 Neele Buildcon 30092025.pdf · uploaded 10 Nov 2025Source
- Withdrawal Update Form 2Form 2 Neele Buildcon 30092025.pdf · uploaded 10 Nov 2025Source
- Withdrawal Update Form 3Form 3 Neele Buildcon 30092025.pdf · uploaded 10 Nov 2025Source
- Withdrawal Update Form 1Form 1 of Neele 31122025.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 2Form 2 of Neele 31122025.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 3Form 3 of Neele 31122025.pdf · uploaded 20 Jan 2026Source
- Withdrawal Update Form 1Form 1 Neele 31032026_Uploaded.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 2Neele Buildcon Rera Form 2_Uploaded.pdf · uploaded 20 Apr 2026Source
- Withdrawal Update Form 3Neele Buildcon Rera Form 3_31032026_Uploaded.pdf · uploaded 20 Apr 2026Source
- Form 2A (FY 2025-2026)Form 2A of Neele 25-26.pdf · uploaded 24 Jun 2026Source
- Withdrawal Update Form 1Form 1 Neele 30062026_signed.pdf · uploaded 24 Jul 2026Source
- Withdrawal Update Form 2Form 2 Neele 30062026 signed.pdf · uploaded 24 Jul 2026Source
- Withdrawal Update Form 3Form 3 Neele 30062026 signed_compressed.pdf · uploaded 24 Jul 2026Source
- Form 5 (FY 2025-2026)Form 5 of Neele Buildcon FY 25-26-signed.pdf · uploaded 18 Sep 2026Source
Technical
Technical (Architect)
- DocumentFORM-1_Buildcon_31-03-2024.pdf · uploaded 6 May 2025Source
- DocumentFORM-1_Buildcon_30-06-2024.pdf · uploaded 6 May 2025Source
- DocumentFORM-1_Buildcon_30-09-2024.pdf · uploaded 6 May 2025Source
- DocumentFORM-1_Buildcon_31-12-2024.pdf · uploaded 6 May 2025Source
- DocumentFORM-1_Buildcon_31-03-2025.pdf · uploaded 6 May 2025Source
- DocumentForm 1 Neele 30062026_signed.pdf · uploaded 24 Jul 2026Source
Technical (Engineer)
- DocumentForm 2 -31032024.pdf · uploaded 7 May 2025Source
- DocumentForm 2 - 30062024.pdf · uploaded 7 May 2025Source
- DocumentForm 2 - 30092024.pdf · uploaded 7 May 2025Source
- DocumentForm 2 - 31122024.pdf · uploaded 7 May 2025Source
- DocumentForm 2 - 31032025.pdf · uploaded 7 May 2025Source
- DocumentForm 2 Neele 30062026 signed.pdf · uploaded 24 Jul 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Shirol, Shahapur taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Shirol Karanjpada Waaralipada Main Road
- South
- Gut No 1379
- East
- Gut No 1390 Pt and Road
- West
- Gut No 1382 and 1381
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Archvision Architects & Int.designers | — |
| Architect | P D Architect | — |
| Chartered accountant | S B Jain And Associates | — |
| Chartered accountant | Shashank R Jain And Associates | — |
| Engineer | Sajid Ansari | — |
| Engineer | Sscons | — |
Source: MahaRERA project page. Contact details are not shown.