Completion promised for 20 May 2028
- Registered
- 30 Apr 2026
- Promised
- 20 May 2028
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PR1330002600308 | 30 Apr 2026 | 20 May 2028 | — | Rudra Constructions | Project page |
2 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Floors with CC | Units |
|---|---|---|---|
| Gururaj Co-operative A | 6 | 7 | 24 |
| Gururaj Co-operative B | 6 | 7 | 30 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Documents
1 document held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.