The Hyde Park

Active

Mira Bhayandar (M Corp.), Thane 401107 |Promoter: Aristone Builders

6 Aug 2024Registered with MahaRERA
31 Dec 2029Promised completion
2Buildings
2MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Active
Buildings
2
Land area for this project
13,600 sq m (1,46,389 sq ft)
Permissible built-up area
49,291 sq m (5,30,567 sq ft)
Sanctioned built-up area
8,142 sq m (87,645 sq ft)
Planning authority
Mira-Bhayandar Municipal Corporation
Address
Old SNo 422, New Sno 103, Hno 2, Old Sno 424, New SNo 104, Hno 3 and 4, Old Sno 425, New SNo 100, Hno 6, 9, 10 and 11, KANAKIA ROAD, MIRAROADPIN 401107
Designated bank account
Icici Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.28884, 72.86864
The Hyde Park is at latitude 19.28884, longitude 72.86864.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2029

Registered
6 Aug 2024
Promised
31 Dec 2029

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000773286 Aug 202431 Dec 2029—Aristone BuildersProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building No 19—
Building No 39—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Building No 1Closed/Covered01001
Building No 1Open Space021500215
Building No 3Closed/Covered00001
Building No 3Open Space000099

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building No 1

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor20%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Building No 3

  • Excavation0%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor0%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyFrom MBMC0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)As per Consultant Dwg0%
  • Storm Water DrainsAs per Consultant Dwg0%
  • Landscaping & Tree PlantingAs per norms0%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterSTP provision0%
  • Solid Waste Management And DisposalAs per Consultant Dwg0%
  • Water conservation /Rain water harvestingAs per Consultant Dwg0%
  • Energy managemcntAs per Consultant Dwg0%
  • Fire protection and fire safety requirementsAs per Approved Plan0%
  • Electrical meter room, sub-station, receiving stationAs per Approved Plan0%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingWIP0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

72 documents held by Deedo, 48 filings listed on MahaRERA's project page

Other (71)

Show all 120 documentsShow fewer documents

Other (71)

Registration certificate

Document library

  • Copy of the legal title reportLEGAL TITLE REPORT_compressed.pdf · uploaded 12 Jun 2024View
  • Deviation Report with respect to Allotment letterAllotment Deviation.pdf · uploaded 12 Jun 2024View
  • a Details of encumbrances concerned to FinanceFinance.pdf · uploaded 12 Jun 2024View
  • a Details of encumbrances concerned to FinanceLegal.pdf · uploaded 12 Jun 2024View
  • b Details of encumbrances concerned to LegalFinance.pdf · uploaded 12 Jun 2024View
  • b Details of encumbrances concerned to LegalLegal.pdf · uploaded 12 Jun 2024View
  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 12 Jun 2024View
  • Building Plan Approval / NA Order for plotted developmentARISTONE BUILDERS LAYOUT PLAN-pages-1.pdf · uploaded 12 Jun 2024View
  • Building Plan Approval / NA Order for plotted developmentARISTONE BUILDERS LAYOUT PLAN-pages-2.pdf · uploaded 12 Jun 2024View
  • Building Plan Approval / NA Order for plotted developmentARISTONE BUILDERS LAYOUT PLAN-pages-3.pdf · uploaded 12 Jun 2024View
  • Deviation Report with respect to model copy of AgreementAgreement Deviation.pdf · uploaded 12 Jun 2024View
  • Commencement Certificates / NA Order for plotted developmentAristone Builders CC.pdf · uploaded 12 Jun 2024View
  • Declaration about Commencement CertificateDECLARTION ABOUT CC.pdf · uploaded 12 Jun 2024View
  • Declaration in FORM BAFFIDAVIT CUM DECLARATION SANTOSH SAMAL SIR.pdf · uploaded 12 Jun 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE.pdf · uploaded 12 Jun 2024View
  • CERSAI detailsSELF DECLARATION REGARDING CERSAI (2).pdf · uploaded 12 Jun 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A BRIJESH SINGH.pdf · uploaded 12 Jun 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A SANTOSH SAMAL SIR.pdf · uploaded 12 Jun 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A SHANKAR JHA.pdf · uploaded 12 Jun 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION ABOUT SEPARATE BANK ACCOUNT.pdf · uploaded 12 Jun 2024View
  • Other – TechnicalANNEXURE A-Declaration Undertaking.pdf · uploaded 12 Jun 2024View
  • Proforma of Allotment letterANNEXURE A ALLOTMENT LETTER_11zon.pdf · uploaded 6 Jul 2024View
  • Proforma of Agreement for saleDRAFT-ARISTONE.pdf · uploaded 8 Jul 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Aristone Builders ARCHITECT'S CERTIFICATE (1).pdf · uploaded 21 Feb 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Aristone Builders Engineer Certificate.pdf · uploaded 21 Feb 2025View
  • Withdrawal Update Form 1FORMMMM 1.pdf · uploaded 23 Jul 2025View
  • Withdrawal Update Form 2FORMMMM 2.pdf · uploaded 23 Jul 2025View
  • Withdrawal Update Form 1FORM 1 (422) 300925.pdf · uploaded 12 Nov 2025View
  • Withdrawal Update Form 2Form2 Certificate_SEP 2025.pdf · uploaded 12 Nov 2025View
  • Form 5 (FY 2024-2025)ARISTONE BUILDERS FORM 5 2024-25.pdf · uploaded 14 Jan 2026View
  • Withdrawal Update Form 1FORM 1 (1).pdf · uploaded 17 Jan 2026View
  • Withdrawal Update Form 2Form2 Certificate_DEC 2025.pdf · uploaded 17 Jan 2026View
  • Withdrawal Update Form 1FORM 1 (1).pdf · uploaded 17 Jan 2026View
  • Withdrawal Update Form 2Form2 Certificate_DEC 2025.pdf · uploaded 17 Jan 2026View
  • Withdrawal Update Form 1Form 1 (422).pdf · uploaded 22 Apr 2026View
  • Withdrawal Update Form 2Form2 Certificate_MAR 2026 (1).pdf · uploaded 22 Apr 2026View
  • Form 2A (FY 2024-2025)FORM 2A THE HIDE PARK 2024-25.pdf · uploaded 20 Jul 2026View
  • Form 2A (FY 2025-2026)FORM 2A THE HIDE PARK 2025-26.pdf · uploaded 20 Jul 2026View
  • Form 5 (FY 2025-2026)FORM 5 ARISTONE BUILDERS.pdf · uploaded 20 Jul 2026View
  • Withdrawal Update Form 1FORM 1 _ARCHITECT CERTIFICATE.pdf · uploaded 21 Jul 2026View
  • Withdrawal Update Form 2Form2 Certificate_JUNE 2026.pdf · uploaded 21 Jul 2026View

Promoter documents

  • Legal Title reportLEGAL TITLE REPORT_compressed.pdf · uploaded 12 Jun 2024View
  • Declaration Form BAFFIDAVIT CUM DECLARATION SANTOSH SAMAL SIR.pdf · uploaded 12 Jun 2024View

Technical documents

  • Layout ApprovalLayout.pdfView
  • Building Plan ApprovalARISTONE BUILDERS LAYOUT PLAN-pages-1.pdfView
  • Building Plan ApprovalARISTONE BUILDERS LAYOUT PLAN-pages-2.pdfView
  • Building Plan ApprovalARISTONE BUILDERS LAYOUT PLAN-pages-3.pdfView

Proforma allotment letter

  • Proforma allotment letterANNEXURE A ALLOTMENT LETTER_11zon.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Mira-Bhayandar (M Corp.), Thane taluka

Survey, CTS, gat or plot numbers

101011114442242442599Hno 2Hno 2Hno 3Hno 3Hno 6Hno 6New SNo 100New SNo 100New Sno 103New Sno 103New SNo 104New SNo 104Old SNo 422Old SNo 422Old Sno 424Old Sno 424Old Sno 425Old Sno 425

As published on MahaRERA's project page

Old SNo 422, New Sno 103, Hno 2, Old Sno 424, New SNo 104, Hno 3 and 4, Old Sno 425, New SNo 100, Hno 6,9,10 and 11

Boundaries

North
Old Sno 476 New SNo99 and Old Sno428 New SNo98
South
18 Mt WIde D P ROad
East
18 Mt Wide D P Road
West
18 Mt Wide D P Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDinanath Deshpande—
Chartered accountantRamesh Dhondiram Lukad—
Chartered accountantR D Lukad—
EngineerJiten Patel—
EngineerNitesh B Jadhav—

Source: MahaRERA project page. Contact details are not shown.

Data through12 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology