Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Active
Buildings
4
Land area for this project
293 sq m (3,151 sq ft)
Permissible built-up area
5,783 sq m (62,251 sq ft)
Sanctioned built-up area
5,783 sq m (62,251 sq ft)
Recreational open space
1,185 sq m (12,759 sq ft)
Planning authority
MIRA BHAYANDER MUNICIPAL CORPORATION
Address
S. No-181 H. No- 7p(A), 7p(B), 9, 10 & S. No-182 H. No- 3, 4, 5, 6, 8, Pleasant Park Mira Bhayander Road, Mira Road EastPIN 401107
Designated bank account
Kotak Mahindra Bank Limited
Developed in phases
No
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.30311, 72.89377
Shree Shashwat Building No. 21 is at latitude 19.30311, longitude 72.89377.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 14 Jan 2027

Registered
5 Apr 2024
Promised
14 Jan 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P517000556315 Apr 202414 Jan 2027—G N DevelopersProject page

4 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Bldg No C23—
C-Wing——
G N Developers——
G-Wing——

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000051
Open Space00009

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Bldg No C

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises87%
  • Sanitary Fittings within the flats / premises0%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks90%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.50%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Common areas and amenities

  • Internal Roads & FootpathsTO BE DONE BEFORE OC0%
  • Water SupplyTO BE PROVIDED BY MBMC AFTER OC0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)TO BE DONE BEFORE OC10%
  • Storm Water DrainsTO BE DONE BEFORE OC0%
  • Landscaping & Tree PlantingTO BE DONE BEFORE OC0%
  • Street LightingNot applicable
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterSTP WILL BE DONE BEFORE OC10%
  • Solid Waste Management And DisposalAS PER CONSTRUCTION0%
  • Water conservation /Rain water harvestingTO BE DONE BEFORE OC0%
  • Energy managemcntTO BE DONE BEFORE OC0%
  • Fire protection and fire safety requirementsTO BE DONE BEFORE OC30%
  • Electrical meter room, sub-station, receiving stationNO RECEIVING STATION80%
  • Aggregate area of recreational Open SpaceRECREATIONAL OPEN SPACE COMMON FOR LAYOUT20%
  • Open ParkingTO BE DONE BEFORE OC80%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

54 documents held by Deedo, 56 filings listed on MahaRERA's project page

Encumbrances

Commencement certificates

Form b

Title

Others

Allotment letters

Registration certificate

Form 1s

Form 2s

Form 2as

Layout plan

Building plan

Document library

  • a Details of encumbrances concerned to FinanceEncumbrance.pdf · uploaded 9 Jan 2024View
  • b Details of encumbrances concerned to LegalEncumbrance.pdf · uploaded 9 Jan 2024View
  • Building Plan Approval / NA Order for plotted developmentC Wing.pdf · uploaded 9 Jan 2024View
  • Commencement Certificates / NA Order for plotted developmentCC Copy.pdf · uploaded 9 Jan 2024View
  • Declaration about Commencement CertificateDeclaration CC.pdf · uploaded 9 Jan 2024View
  • Declaration in FORM BFORM B.pdf · uploaded 9 Jan 2024View
  • Copy of the legal title reportTitle Rera.pdf · uploaded 19 Mar 2024View
  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 19 Mar 2024View
  • Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other.pdf · uploaded 19 Mar 2024View
  • Proforma of Agreement for saleRERA AGR SS22.pdf · uploaded 19 Mar 2024View
  • Proforma of Allotment letterALLOTMENT LETTER (2).pdf · uploaded 19 Mar 2024View
  • Deviation Report with respect to Allotment letterDeviation Allotment.pdf · uploaded 19 Mar 2024View
  • Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration Bank Account.pdf · uploaded 19 Mar 2024View
  • Deviation Report with respect to model copy of AgreementDeviation of AFS.pdf · uploaded 19 Mar 2024View
  • CERSAI detailsUndertaking.pdf · uploaded 19 Mar 2024View
  • Other – Legal712 Pherphar.pdf · uploaded 19 Mar 2024View
  • Other – TechnicalDeclaration Rera Registration.pdf · uploaded 19 Mar 2024View
  • Other – TechnicalAnnexure A.pdf · uploaded 19 Mar 2024View
  • Other – TechnicalDeclaration Plinth.pdf · uploaded 19 Mar 2024View
  • Other – TechnicalDeclaration GN Construction.pdf · uploaded 19 Mar 2024View
  • a Details of encumbrances concerned to FinanceDeclaration on Encumbrances.pdf · uploaded 4 Apr 2024View
  • b Details of encumbrances concerned to LegalDeclaration on Encumbrances.pdf · uploaded 4 Apr 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)GND Bldg 21 Architect Certificate.pdf · uploaded 6 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)GND Bldg 21 Engineer Certificate.pdf · uploaded 6 Jul 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)GND Bldg 21 quality Certificate.pdf · uploaded 6 Jul 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng GND.pdf · uploaded 8 Oct 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng GND.pdf · uploaded 8 Oct 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc GND.pdf · uploaded 8 Oct 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality GND.pdf · uploaded 8 Oct 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc GND.pdf · uploaded 8 Oct 2024View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality GND.pdf · uploaded 8 Oct 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc GND.pdf · uploaded 16 Jan 2025View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)Eng GND.pdf · uploaded 16 Jan 2025View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Quality GND.pdf · uploaded 16 Jan 2025View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc GND.pdf · uploaded 7 Apr 2025View
  • Form 1Arc GND.pdf · uploaded 25 Jul 2025View
  • Form 2Eng GND.pdf · uploaded 25 Jul 2025View
  • Disclosure of Sold and Booked InventoryGND disclosure of Sold.pdf · uploaded 25 Jul 2025View
  • Withdrawal Update Form 1ArcGND.pdf · uploaded 30 Jul 2025View
  • Withdrawal Update Form 2Form 2 GND 30062025.pdf · uploaded 30 Jul 2025View
  • Withdrawal Update Form 1GND.pdf · uploaded 15 Oct 2025View
  • Withdrawal Update Form 2GND Form 2.pdf · uploaded 15 Oct 2025View
  • Withdrawal Update Form 1GND Form 1 Dec 25.pdf · uploaded 12 Jan 2026View
  • Withdrawal Update Form 2GND Form 2 Dec 25.pdf · uploaded 12 Jan 2026View
  • Withdrawal Update Form 1GND Withdrawal Application Form1.pdf · uploaded 9 Apr 2026View
  • Withdrawal Update Form 2GND Withdrawal Application Form2.pdf · uploaded 9 Apr 2026View
  • Withdrawal Update Form 1GND Withdrawal Application Form1.pdf · uploaded 18 Jul 2026View
  • Withdrawal Update Form 2GND Withdrawal Application Form2.pdf · uploaded 18 Jul 2026View
  • Withdrawal Update Form 1GND Form 1.pdf · uploaded 18 Jul 2026View
  • Withdrawal Update Form 2GND Form 2.pdf · uploaded 18 Jul 2026View

Promoter documents

  • Declaration Form BFORM B.pdf · uploaded 9 Jan 2024View
  • Legal Title reportTitle Rera.pdf · uploaded 19 Mar 2024View

Technical documents

  • Building Plan ApprovalC Wing.pdfView
  • Layout ApprovalLayout.pdfView

Other legal documents

  • Other – Legal712 Pherphar.pdfView

Proforma allotment letter

  • Proforma allotment letterALLOTMENT LETTER (2).pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Mira-Bhayandar (M Corp.), Thane taluka

Survey, CTS, gat or plot numbers

10104455667P(B)7P(B)8899S. NO-181 H. NO- 7P(A)S. NO181 H. NO 7P(A)S. NO-182 H. NO- 3S. NO182 H. NO 3

As published on MahaRERA's project page

S. NO-181 H. NO- 7P(A),7P(B),9,10 & S. NO-182 H. NO- 3,4,5,6,8

Boundaries

North
Shree Shashwat bldg no 1-5
South
Jangid Home
East
Shree Shashwat bldg no 20
West
Shree Shashwat bldg no 22

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnish & Associates—
Chartered accountantM B R & Associates—
EngineerJiten Patel—

Source: MahaRERA project page. Contact details are not shown.