Happy Home Residency

Lapsed

Mira Bhayandar (M Corp.), Thane 401107 |Promoter: Happy Home Residency

Residential / Group HousingRERAP51700009830
22 Aug 2017Registered with MahaRERA
31 Dec 2017Promised completion
31 Dec 2018Revised completionPushed back 1 year
2Buildings
118Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Lapsed
Buildings
2
Unit types
2 bhk, 1 bhk118 units in all
Land area for this project
861 sq m (9,271 sq ft)
Permissible built-up area
6,000 sq m (64,582 sq ft)
Sanctioned built-up area
6,000 sq m (64,582 sq ft)
Recreational open space
250 sq m (2,691 sq ft)
Address
430pPIN 401107
Designated bank account
Kotak Mahindra Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.29329, 72.87844
Happy Home Residency is at latitude 19.29329, longitude 72.87844.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year

The latest completion date on record passed 7 years and 10 months ago.

Registered
22 Aug 2017
Promised
31 Dec 2017
Revised
31 Dec 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000983022 Aug 201731 Dec 201731 Dec 2018Happy Home ResidencyProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Happy Home Residency Wing A1471
Happy Home Residency Wing B1447

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

118 units registered

2 bhk · 71 units1 bhk · 47 units
BuildingTypeCarpet areaUnits
Happy Home Residency Wing A2 bhk50.83 sq m · 547 sq ft12
Happy Home Residency Wing A2 bhk51.19 sq m · 551 sq ft12
Happy Home Residency Wing A2 bhk57.71 sq m · 621 sq ft23
Happy Home Residency Wing A2 bhk58.43 sq m · 629 sq ft24
Happy Home Residency Wing B1 bhk35.39 sq m · 381 sq ft47

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Happy Home Residency Wing AClosed/Covered000022
Happy Home Residency Wing AOpen Space000014
Happy Home Residency Wing BClosed/Covered000010
Happy Home Residency Wing BOpen Space00002

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Happy Home Residency Wing A

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Happy Home Residency Wing B

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & Footpathscomplete100%
  • Water SupplyOnly after obtaining O.C.100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)STP Plat to be commissioned by MBMC100%
  • Storm Water Drainscomplete100%
  • Landscaping & Tree Plantingcomplete100%
  • Street Lightingcomplete100%
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingcomplete100%
  • Energy managemcntcomplete100%
  • Fire protection and fire safety requirementscomplete100%
  • Electrical meter room, sub-station, receiving stationcomplete100%
  • Aggregate area of recreational Open Spacecomplete100%
  • Open Parkingcomplete100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

12 documents held by Deedo, 15 filings listed on MahaRERA's project page

Title report

Encumbrance details

Form B

Form 1

Form 2

Registration certificate

Extension certificate

Other (2)

Show all 27 documentsShow fewer documents

Other (2)

Layout plan

Building plan

Allotment letter

Document library

  • Copy of Layout Approval (in case of layout)Layout scan.pdf · uploaded 29 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arch Certi Form 1.pdf · uploaded 29 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 29 Jul 2017View
  • Declaration in FORM BForm B.pdf · uploaded 29 Jul 2017View
  • Building Plan Approval (IOD)CC.pdf · uploaded 29 Jul 2017View
  • Copy of the legal title reportTitle Certi 2.pdf · uploaded 29 Jul 2017View
  • Proforma of Allotment letterDec for AFS.pdf · uploaded 29 Jul 2017View
  • Details of encumbrancesNo Litigation NOC.pdf · uploaded 29 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 27 Mar 2018View
  • Certificates of CA (Form 5)CC.pdf · uploaded 29 Mar 2018View

Promoter documents

  • Declaration Form BForm B.pdf · uploaded 29 Jul 2017View
  • Legal Title reportTitle Certi 2.pdf · uploaded 29 Jul 2017View

Technical documents

  • Building Plan ApprovalCC.pdfView
  • Layout ApprovalLayout scan.pdfView

Proforma allotment letter

  • Proforma allotment letterDec for AFS.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Mira-Bhayandar (M Corp.), Thane taluka

Survey, CTS, gat or plot numbers

430p430p

As published on MahaRERA's project page

430p

Boundaries

North
D P Road
South
436
East
281
West
430

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAvinash Mhatre & Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology