Skip to content
Deedo home
Menu

Swagat Heights

Completed

Mira Bhayandar (M Corp.), Thane 401107 |Promoter: Swagat Property Developers

Residential / Group HousingRERAP51700008280
18 Aug 2017Registered with MahaRERA
31 Mar 2019Promised completion
2Buildings
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
2
Land area for this project
2,980 sq m (32,076 sq ft)
Permissible built-up area
6,790 sq m (73,087 sq ft)
Sanctioned built-up area
6,790 sq m (73,087 sq ft)
Address
Survey number 77, Hissa number 1, 2 and 3PT, Mira Bhayandar Road, Mira Road EastPIN 401107
Designated bank account
Kotak Mahindra Bank Limited
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.28371, 72.87904
Swagat Heights is at latitude 19.28371, longitude 72.87904.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2019

The latest completion date on record passed 7 years and 7 months ago.

Registered
18 Aug 2017
Promised
31 Mar 2019

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170000828018 Aug 201731 Mar 2019—Swagat Property DevelopersProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing A15—
Wing B11—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

BuildingTypeTwo-wheelerFour-wheelerBusVisitorTotal
Wing AClosed/Covered000027
Wing AOpen Space00000
Wing BClosed/Covered000012
Wing BOpen Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Wing A

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises40%
  • Sanitary Fittings within the flats / premises10%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%

Wing B

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor0%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises95%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Common areas and amenities

  • Internal Roads & Footpathscompleted100%
  • Water SupplyM.B.M.C. Connection balance50%
  • Sewerage (Chamber, Lines, Septic Tank , STP)work completed100%
  • Storm Water Drainswork completed100%
  • Landscaping & Tree Plantingwork in progress0%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvesting0%
  • Energy managemcntWork in progress50%
  • Fire protection and fire safety requirementswork in progress10%
  • Electrical meter room, sub-station, receiving stationwork completed100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

23 documents held by Deedo, 32 filings listed on MahaRERA's project page

Commencement certificate

Form 1 (2)

Form 2 (3)

Title report

Encumbrance details

Show all 55 documentsShow fewer documents

Form B

Registration certificate

Form 5

Occupancy / completion certificate

  • Occupancy / completion certificate18 Sep 2019ViewSource

Form 4

Other (3)

Layout plan

Building plan (5)

Allotment letter

Document library

  • Copy of Layout Approval (in case of layout)Approve Plans.PDF · uploaded 29 Jul 2017View
  • Proforma of Allotment letterProfarma.PDF · uploaded 29 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architec Certificate.PDF · uploaded 29 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentCC Copy.PDF · uploaded 29 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.PDF · uploaded 29 Jul 2017View
  • OtherLayout Letter.PDF · uploaded 30 Jul 2017View
  • Declaration in FORM BForm B.PDF · uploaded 30 Jul 2017View
  • Copy of the legal title reportTitle report1.pdf · uploaded 30 Jul 2017View
  • Details of encumbrancesEncumbrances Letter.PDF · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)Developement Agreement Letter.PDF · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)IOD.pdf · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)1.pdf · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)2.pdf · uploaded 30 Jul 2017View
  • Building Plan Approval (IOD)3.pdf · uploaded 30 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.PDF · uploaded 31 Oct 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engg ddecl.pdf · uploaded 31 Oct 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Enginer's certificate.PDF · uploaded 20 Nov 2017View
  • Certificates of CA (Form 5)Form 5.pdf · uploaded 15 Oct 2018View
  • OtherOC.pdf · uploaded 30 Mar 2019View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentSwagat OC.pdf · uploaded 18 Sep 2019View
  • Architect’s Certificate on Completion of Project (Form 4)Form 4.pdf · uploaded 13 Dec 2019View

Promoter documents

  • Declaration Form BForm B.PDF · uploaded 30 Jul 2017View
  • Legal Title reportTitle report1.pdf · uploaded 30 Jul 2017View

Technical documents

  • Layout ApprovalApprove Plans.PDFView
  • Building Plan ApprovalDevelopement Agreement Letter.PDFView
  • Building Plan ApprovalIOD.pdfView
  • Building Plan Approval1.pdfView
  • Building Plan Approval2.pdfView
  • Building Plan Approval3.pdfView

Other legal documents

  • OtherLayout Letter.PDFView
  • OtherOC.pdfView

Proforma allotment letter

  • Proforma allotment letterProfarma.PDFView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Mira-Bhayandar (M Corp.), Thane taluka

Survey, CTS, gat or plot numbers

223PT3PTHissa number 1Hissa number 1Survey number 77Survey number 77

As published on MahaRERA's project page

Survey number 77, Hissa number 1,2 and 3PT

Boundaries

North
Nullah and Road
South
GCC International School
East
Ritu Paradise Phase 2 Building
West
Balaji Enclave Building

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDinesh N Patel—
EngineerAnish and Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology