Vaikunth Pride
Certificate SignedUlawe, Raigarh 410206 |Promoter: Divyesh Nakrani
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 1RK, Shop15 units in all
- Address
- 30a, Plot No 30a, Sector 25aPIN 410206
- Designated bank account
- 148
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2022
The latest completion date on record passed 3 years and 10 months ago.
- Registered
- 6 Oct 2020
- Promised
- 30 Dec 2022
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000026582 | 6 Oct 2020 | 30 Dec 2022 | 30 Dec 2022 | Divyesh Nakrani | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Vaikunth Pride | 6 | 15 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 of 15 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 25.49 sq m · 274 sq ft | 1 | 0 |
| 1BHK | 26.66 sq m · 287 sq ft | 3 | 0 |
| 1RK | 15.09 sq m · 162 sq ft | 1 | 0 |
| 1RK | 17.05 sq m · 184 sq ft | 3 | 0 |
| 1RK | 17.16 sq m · 185 sq ft | 3 | 0 |
| 1RK | 19.45 sq m · 209 sq ft | 1 | 0 |
| Shop | 12.93 sq m · 139 sq ft | 1 | 0 |
| Shop | 14.79 sq m · 159 sq ft | 1 | 0 |
| Shop | 16.43 sq m · 177 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 31 filings listed on MahaRERA's project page
Legal
- Legal Title reportTitle Search Report.pdf · uploaded 2 Oct 2020Source
- Declaration Form BForm B_compressed.pdf · uploaded 2 Oct 2020Source
- Legal Title reportTitle Certificate Part 1 with Search Report.pdf · uploaded 22 Apr 2023Source
- Legal Title reportTitle Certificate Part 2.pdf · uploaded 22 Apr 2023Source
Show all 32 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentCC Drawing.pdf · uploaded 2 Oct 2020Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 2 Oct 2020Source
- 1 Declaration in FORM BForm B_compressed.pdf · uploaded 2 Oct 2020Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA form 1.pdf · uploaded 2 Oct 2020Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)AREA (3).pdf · uploaded 2 Oct 2020Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate.pdf · uploaded 2 Oct 2020Source
- 1 Proforma of Allotment letterLETTER OF ALLOTMENT - RERA ACT -.pdf · uploaded 2 Oct 2020Source
- 2 Proforma of Allotment letterAgreement to Sale Draft.pdf · uploaded 2 Oct 2020Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3-compressed.pdf · uploaded 3 Oct 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 Shree Om Enterprises FY 20-21.pdf · uploaded 18 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Shree Om Enterprises FY 21-22.pdf · uploaded 18 Apr 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC (1).pdf · uploaded 18 Apr 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)PUSHPAK FORM 4 (1).pdf · uploaded 18 Apr 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)30A-25A-PUSHPAK RERA (2022 MARCH) (2) (1).pdf · uploaded 19 Apr 2023Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)30A-25A-PUSHPAK RERA (2022 MARCH) (1).pdf · uploaded 19 Apr 2023Source
- 1 Proforma of Agreement for saleDraft - Agreement for sale.pdf · uploaded 19 Apr 2023Source
- 1 Other – TechnicalCidco Final Order Heirship.pdf · uploaded 19 Apr 2023Source
- 2 Copy of the legal title reportTitle Certificate Part 1 with Search Report.pdf · uploaded 22 Apr 2023Source
- 3 Copy of the legal title reportTitle Certificate Part 2.pdf · uploaded 22 Apr 2023Source
Technical
Technical (Architect)
- Document30A-25A-PUSHPAK RERA (2022 MARCH) (1).pdf · uploaded 19 Apr 2023Source
Technical (Engineer)
- DocumentEngineer Certificate.pdf · uploaded 2 Oct 2020Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Ulawe, Panvel taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- 11 Meter Wide Road
- South
- Plot No 33h
- East
- Plot No 30b
- West
- 11 Meter Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atul Patel Architects | — |
| Chartered accountant | Priyavrat And Associates | — |
| Engineer | S R Consultants | — |
Source: MahaRERA project page. Contact details are not shown.