Sai Ornate
Certificate SignedUlawe, Raigarh 410206 |Promoter: Jay Gurudev Construction
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1 BHK, 1BHK, 1 RK with Terrace, Shop53 units in all
- Address
- Plot no. 14, Sector 9PIN 410206
- Designated bank account
- 76
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year and 6 months
The latest completion date on record passed 3 years and 10 months ago.
- Registered
- 8 Aug 2017
- Promised
- 30 Jun 2021
- Revised
- 30 Dec 2022
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000004164 | 8 Aug 2017 | 30 Jun 2021 | 30 Dec 2022 | Jay Gurudev Construction | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Sai Ornate | 15 | 53 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
51 of 53 units booked (96%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 21.58 sq m · 232 sq ft | 2 | 2 |
| 1 BHK | 23.63 sq m · 254 sq ft | 12 | 12 |
| 1 BHK | 23.71 sq m · 255 sq ft | 3 | 3 |
| 1 BHK | 24.66 sq m · 265 sq ft | 3 | 3 |
| 1 BHK | 25.82 sq m · 278 sq ft | 19 | 18 |
| 1 BHK | 26.63 sq m · 287 sq ft | 1 | 1 |
| 1BHK | 23.72 sq m · 255 sq ft | 1 | 1 |
| 1BHK | 24.67 sq m · 266 sq ft | 5 | 4 |
Show all 12 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 RK with Terrace | 16.98 sq m · 183 sq ft | 2 | 2 |
| Shop | 20.72 sq m · 223 sq ft | 3 | 3 |
| Shop | 23.62 sq m · 254 sq ft | 1 | 1 |
| Shop | 23.75 sq m · 256 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 58 filings listed on MahaRERA's project page
Finance
- PAN CardJAY GURUDEV CONSTRUCTION PAN CARD.pdf · uploaded 25 Jul 2017Source
Legal
Show all 60 documentsShow fewer documents
Migrated
- 1 Copy of Layout Approval (in case of layout)01 of 03.pdf · uploaded 25 Jul 2017Source
- 2 Copy of Layout Approval (in case of layout)02 of 03.pdf · uploaded 25 Jul 2017Source
- 3 Copy of Layout Approval (in case of layout)03 of 03.pdf · uploaded 25 Jul 2017Source
- 1 Building Plan Approval (IOD)CC COPY.pdf · uploaded 25 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCC COPY.pdf · uploaded 25 Jul 2017Source
- 1 Declaration in FORM BFORM B JGC.pdf · uploaded 25 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM -1 ARCHITECT'S CERTIFICATE.pdf · uploaded 25 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)JGC ENGINEER CERTIFICATE.pdf · uploaded 25 Jul 2017Source
- 1 Certificates of CA (Form 3)JGC CA Certificate final.pdf · uploaded 26 Jul 2017Source
- 1 Proforma of Allotment letterAgreement and Allotment JGC.pdf · uploaded 26 Jul 2017Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Jay Gurudev Construction 01-04-2018.pdf · uploaded 2 Apr 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate.pdf · uploaded 17 Jun 2019Source
- 2 Certificates of CA (Form 3)Form 3 - Sai Ornate-compressed.pdf · uploaded 17 Jun 2019Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate.pdf · uploaded 16 Sep 2019Source
- 3 Certificates of CA (Form 3)FORM 3 Sai Ornate.pdf · uploaded 16 Sep 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 Sai Ornate.pdf · uploaded 1 Nov 2019Source
- 4 Certificates of CA (Form 3)Form 3 Sai Ornate.pdf · uploaded 6 Jan 2020Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2 Sai Oranate.pdf · uploaded 11 Jan 2020Source
- 5 Certificates of CA (Form 3)Form 3 Sai Ornate.pdf · uploaded 26 Feb 2020Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form-2 Sai Ornate.pdf · uploaded 27 Feb 2020Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate 31st Mar 2020.pdf · uploaded 2 Sep 2020Source
- 6 Certificates of CA (Form 3)Form 3 Jay Gurudev 31st Mar 2020_compressed.pdf · uploaded 2 Sep 2020Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate Jun 2020_compressed.pdf · uploaded 30 Nov 2020Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate 30th Sept 2020_compressed.pdf · uploaded 30 Nov 2020Source
- 7 Certificates of CA (Form 3)Form 3 Sai Ornate 30th June 2020_compressed.pdf · uploaded 30 Nov 2020Source
- 8 Certificates of CA (Form 3)Form 3 Sai Ornate 30th September 2020_compressed.pdf · uploaded 30 Nov 2020Source
- 1 Disclosure of sold/ booked inventoryJGC Circular 29.pdf · uploaded 20 May 2021Source
- 1 Declaration about Commencement CertificateDeclaration About Commencement Certifica.pdf · uploaded 29 Jun 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 FY 19-20 Sai Ornate.pdf · uploaded 29 Jun 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FY 20-21 Sai Ornate.pdf · uploaded 29 Jun 2021Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate Dec 2020.pdf · uploaded 5 Aug 2021Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate Mar 2021.pdf · uploaded 5 Aug 2021Source
- 9 Certificates of CA (Form 3)Form 3 Sai Ornate 31st Dec 2020.pdf · uploaded 5 Aug 2021Source
- 10 Certificates of CA (Form 3)Form 3 Sai Ornate 31st Mar 2021.pdf · uploaded 5 Aug 2021Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 Sai Ornate June 2021.pdf · uploaded 20 Aug 2021Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate June 2021.pdf · uploaded 20 Aug 2021Source
- 11 Certificates of CA (Form 3)Form 3 Sai Ornate 30th June 2021.pdf · uploaded 20 Aug 2021Source
- 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate Sept 2021.pdf · uploaded 30 Nov 2021Source
- 12 Certificates of CA (Form 3)Form 3 Sai Ornate 30th September 2021_compressed.pdf · uploaded 30 Nov 2021Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Sai Ornate.pdf · uploaded 6 Jan 2022Source
- 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 Sai Ornate 3rd Jan 2022.pdf · uploaded 25 May 2022Source
- 1 CERSAI detailsSai Ornate.pdf · uploaded 25 May 2022Source
- 13 Certificates of CA (Form 3)Form 3 Sai Ornate 03rd January 2022_compressed.pdf · uploaded 25 May 2022Source
- 1 Architect’s Certificate on Completion of Project (Form 4)Form 4- Sai Ornate.pdf · uploaded 21 Jun 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 17-18.pdf · uploaded 7 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Certificate 222.pdf · uploaded 7 Apr 2023Source
Technical
Technical (Architect)
- DocumentForm 1 Sai Ornate June 2021.pdf · uploaded 20 Aug 2021Source
Technical (Engineer)
- DocumentForm 2 Sai Ornate 3rd Jan 2022.pdf · uploaded 25 May 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Ulawe, Panvel taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot 3
- South
- 24 mtr wide road
- East
- Plot 13
- West
- Plot 15
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Triarch Design Studio | — |
| Engineer | Agharkar Consultants | — |
Source: MahaRERA project page. Contact details are not shown.