Skip to content

Rd Park

Certificate Signed

Ulawe, Raigarh 410206 |Promoter: Rd Enterprises

19 Jul 2019Registered with MahaRERA
20 Jun 2022Promised completion
1Building
16Units registered2 booked (13%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1 BHK, Shop16 units in all
Address
306, Sector 19, Node UlwePIN 410206
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 20 Jun 2022

The latest completion date on record passed 4 years and 4 months ago.

Registered
19 Jul 2019
Promised
20 Jun 2022

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200002168319 Jul 201920 Jun 202220 Jun 2022Rd EnterprisesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Rd Park516

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

2 of 16 units booked (13%), as the promoter reported to MahaRERA

1 BHK · 12 unitsShop · 4 units
TypeCarpet areaUnitsBooked
1 BHK24.7 sq m · 266 sq ft41
1 BHK25.87 sq m · 278 sq ft40
1 BHK27.63 sq m · 297 sq ft41
Shop11.98 sq m · 129 sq ft30
Shop11.99 sq m · 129 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 42 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardcompany pancard.pdf · uploaded 3 Jul 2019Source

Legal

  • Legal Title reportTitle Clearance Certificate.pdf · uploaded 3 Jul 2019Source
  • Declaration Form Bfrom B.pdf · uploaded 16 Jul 2019Source

Migrated

  • 1 PAN Cardcompany pancard.pdf · uploaded 3 Jul 2019Source
  • 1 Copy of the legal title reportTitle Clearance Certificate.pdf · uploaded 3 Jul 2019Source
  • 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 3 Jul 2019Source
  • 1 Building Plan Approval (IOD)CC.pdf · uploaded 3 Jul 2019Source
Show all 43 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 3 Jul 2019Source
  • 1 Proforma of Allotment letterproforma allotment and agreement for sale.pdf · uploaded 3 Jul 2019Source
  • 1 Details of encumbrancesCERTIFICATE.pdf · uploaded 12 Jul 2019Source
  • 1 Certificates of CA (Form 3)FORM 3_compressed.pdf · uploaded 12 Jul 2019Source
  • 1 Declaration in FORM Bfrom B.pdf · uploaded 16 Jul 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form1.pdf · uploaded 17 Dec 2019Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form2.pdf · uploaded 17 Dec 2019Source
  • 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 17 Dec 2019Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Feb 2020Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 (1).pdf · uploaded 26 Feb 2020Source
  • 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 26 Feb 2020Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 18 Aug 2020Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 18 Aug 2020Source
  • 4 Certificates of CA (Form 3)FORM3-RD Enterprises.pdf · uploaded 18 Aug 2020Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Arcitect Certifcate.pdf · uploaded 19 Oct 2020Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Arcitect Certifcate.pdf · uploaded 19 Oct 2020Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Engineer Certificate.pdf · uploaded 19 Oct 2020Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Engineer Certificate.pdf · uploaded 19 Oct 2020Source
  • 5 Certificates of CA (Form 3)FORM 3.pdf · uploaded 19 Oct 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5-FY 2019-20.pdf · uploaded 19 Oct 2020Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA form 1.pdf · uploaded 18 Feb 2021Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 18 Feb 2021Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA form 1.pdf · uploaded 16 Mar 2021Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 16 Mar 2021Source
  • 6 Certificates of CA (Form 3)R D FORM3.pdf · uploaded 16 Mar 2021Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA form 1.pdf · uploaded 5 Apr 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 5 Apr 2022Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 5 Apr 2022Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 5 Apr 2022Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 5 Apr 2022Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY CERTIFICATE.pdf · uploaded 9 Mar 2023Source

Technical

  • DocumentCC.pdf · uploaded 3 Jul 2019Source
  • Documentlayout.pdf · uploaded 3 Jul 2019Source

Technical (Architect)

  • DocumentRERA form 1.pdf · uploaded 5 Apr 2022Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 5 Apr 2022Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ulawe, Panvel taluka

Survey, CTS, gat or plot numbers

306

Boundaries

North
Plot No 305
South
11 Mtr Wide Road
East
Plot No 306a
West
11 Mtr Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAtul Patel—
Chartered accountantPrakash M Khatri—
EngineerB S Sukhtankar—
Registered real estate agentPravin Madhukar Kadam—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology