Rd Park
Certificate SignedUlawe, Raigarh 410206 |Promoter: Rd Enterprises
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1 BHK, Shop16 units in all
- Address
- 306, Sector 19, Node UlwePIN 410206
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 20 Jun 2022
The latest completion date on record passed 4 years and 4 months ago.
- Registered
- 19 Jul 2019
- Promised
- 20 Jun 2022
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000021683 | 19 Jul 2019 | 20 Jun 2022 | 20 Jun 2022 | Rd Enterprises | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Rd Park | 5 | 16 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
2 of 16 units booked (13%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 24.7 sq m · 266 sq ft | 4 | 1 |
| 1 BHK | 25.87 sq m · 278 sq ft | 4 | 0 |
| 1 BHK | 27.63 sq m · 297 sq ft | 4 | 1 |
| Shop | 11.98 sq m · 129 sq ft | 3 | 0 |
| Shop | 11.99 sq m · 129 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 42 filings listed on MahaRERA's project page
Show all 43 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 3 Jul 2019Source
- 1 Proforma of Allotment letterproforma allotment and agreement for sale.pdf · uploaded 3 Jul 2019Source
- 1 Details of encumbrancesCERTIFICATE.pdf · uploaded 12 Jul 2019Source
- 1 Certificates of CA (Form 3)FORM 3_compressed.pdf · uploaded 12 Jul 2019Source
- 1 Declaration in FORM Bfrom B.pdf · uploaded 16 Jul 2019Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form1.pdf · uploaded 17 Dec 2019Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form2.pdf · uploaded 17 Dec 2019Source
- 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 17 Dec 2019Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 26 Feb 2020Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 (1).pdf · uploaded 26 Feb 2020Source
- 3 Certificates of CA (Form 3)Form 3.pdf · uploaded 26 Feb 2020Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 18 Aug 2020Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 18 Aug 2020Source
- 4 Certificates of CA (Form 3)FORM3-RD Enterprises.pdf · uploaded 18 Aug 2020Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Arcitect Certifcate.pdf · uploaded 19 Oct 2020Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1- Arcitect Certifcate.pdf · uploaded 19 Oct 2020Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Engineer Certificate.pdf · uploaded 19 Oct 2020Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2-Engineer Certificate.pdf · uploaded 19 Oct 2020Source
- 5 Certificates of CA (Form 3)FORM 3.pdf · uploaded 19 Oct 2020Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5-FY 2019-20.pdf · uploaded 19 Oct 2020Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA form 1.pdf · uploaded 18 Feb 2021Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 18 Feb 2021Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA form 1.pdf · uploaded 16 Mar 2021Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 16 Mar 2021Source
- 6 Certificates of CA (Form 3)R D FORM3.pdf · uploaded 16 Mar 2021Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA form 1.pdf · uploaded 5 Apr 2022Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 5 Apr 2022Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 5 Apr 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 5 Apr 2022Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 5 Apr 2022Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)SOCIETY CERTIFICATE.pdf · uploaded 9 Mar 2023Source
Technical (Architect)
- DocumentRERA form 1.pdf · uploaded 5 Apr 2022Source
Technical (Engineer)
- DocumentFORM 2.pdf · uploaded 5 Apr 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Ulawe, Panvel taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 305
- South
- 11 Mtr Wide Road
- East
- Plot No 306a
- West
- 11 Mtr Wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atul Patel | — |
| Chartered accountant | Prakash M Khatri | — |
| Engineer | B S Sukhtankar | — |
| Registered real estate agent | Pravin Madhukar Kadam | — |
Source: MahaRERA project page. Contact details are not shown.