Prime Villa
Certificate SignedUlawe, Raigarh 410206 |Promoter: Prime Developers
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 1RK, Shop15 units in all
- Address
- 41, Plot No 41, Pushpak Node, Ulwe, PanvelPIN 410206
- Designated bank account
- 220
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Mar 2023
The latest completion date on record passed 3 years and 7 months ago.
- Registered
- 19 Sep 2019
- Promised
- 30 Mar 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000022398 | 19 Sep 2019 | 30 Mar 2023 | 30 Mar 2023 | Prime Developers | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Prime Villa | 5 | 15 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 of 15 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 24.99 sq m · 269 sq ft | 4 | 0 |
| 1BHK | 26 sq m · 280 sq ft | 4 | 0 |
| 1RK | 16.14 sq m · 174 sq ft | 4 | 0 |
| Shop | 10.57 sq m · 114 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 24 filings listed on MahaRERA's project page
Finance
- PAN CardPrime Developers Pan.pdf · uploaded 8 Sep 2019Source
Legal
Migrated
- 1 PAN CardPrime Developers Pan.pdf · uploaded 8 Sep 2019Source
- 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 8 Sep 2019Source
- 1 Details of encumbrancesEncumbrances Letter.pdf · uploaded 8 Sep 2019Source
- 1 Copy of Layout Approval (in case of layout)Plan Copy.pdf · uploaded 8 Sep 2019Source
Show all 25 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentPlan Copy.pdf · uploaded 8 Sep 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 8 Sep 2019Source
- 1 Declaration in FORM BForm B Declaration.pdf · uploaded 8 Sep 2019Source
- 1 Proforma of Allotment letterDraft Sale Agreement.pdf · uploaded 8 Sep 2019Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 9 Sep 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5.pdf · uploaded 26 Mar 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineer Cert.pdf · uploaded 30 Dec 2021Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineer Cert 1.pdf · uploaded 30 Dec 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5.pdf · uploaded 30 Dec 2021Source
- 1 CERSAI detailsCERSAI Report.pdf · uploaded 26 May 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC Copy.pdf · uploaded 26 May 2022Source
- 2 Architect’s Certificate on Completion of Project (Form 4)Architect Certificate completion.pdf · uploaded 26 May 2022Source
- 3 Architect’s Certificate on Completion of Project (Form 4)Architect Form 4.pdf · uploaded 26 May 2022Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate.pdf · uploaded 26 May 2022Source
- 4 Architect’s Certificate on Completion of Project (Form 4)Form 4 New Format.pdf · uploaded 5 Apr 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Ulawe, Panvel taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 40
- South
- Plot No 42
- East
- 9 Meter Wide Road
- West
- Plot No 32
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Atul Patel | — |
| Chartered accountant | D N J & Associates | — |
| Engineer | Bs Sukthankar & Associates | — |
| Other | Chandrakant Rabadiya | — |
Source: MahaRERA project page. Contact details are not shown.