Skip to content

Om Harmony

Certificate Signed

Ulawe, Raigarh 410206 |Promoter: Om Builders & Developers

7 Aug 2025Registered with MahaRERA
31 May 2029Promised completion
30 Sep 2029Revised completionPushed back 4 months
4Buildings
68Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Mixed
Status on MahaRERA
Certificate Signed
Buildings
4
Unit types
—68 units in all
Address
Street, UlwePIN 410206
Designated bank account
190
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.97108, 73.01585
Om Harmony is at latitude 18.97108, longitude 73.01585.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
7 Aug 2025
Promised
31 May 2029
Revised
30 Sep 2029

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PM12700025005157 Aug 202531 May 202930 Sep 2029Om Builders & DevelopersProject page

4 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
A-Wing8—34
B-Wing7—34
Residential Cum A-Wing8834
Residential Cum B-Wing7834

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

68 units registered

— · 68 units
BuildingTypeCarpet areaUnits
A-Wing——34
B-Wing——34

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 35 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Card1_PAN Card.pdf · uploaded 18 May 2025Source
  • OthersOther_Declaration.pdf · uploaded 21 May 2025Source

Legal

  • Declaration Form BForm B Affidavit cum Declaration Ashish Kawde.pdf · uploaded 14 May 2025Source
  • OthersOther_Declaration.pdf · uploaded 21 May 2025Source
  • Declaration Form BLease Agreement1.pdf · uploaded 21 May 2025Source
  • Declaration Form BTripartite Agreement2.pdf · uploaded 21 May 2025Source
  • Declaration Form B3_Final order New Licensees.pdf · uploaded 21 May 2025Source
Show all 36 documentsShow fewer documents

Legal

  • Declaration Form BHeirship Certificate.pdf · uploaded 21 May 2025Source
  • Declaration Form BFinal order for Legal Heirs.pdf · uploaded 21 May 2025Source
  • OthersAnnexure A Dharam Pawar.pdf · uploaded 17 Jun 2025Source
  • OthersAnnexure A Manasi Shinde.pdf · uploaded 17 Jun 2025Source
  • OthersAnnexure A Ashish Kawde.pdf · uploaded 18 Jun 2025Source
  • Declaration Form BOm Harmony Title.pdf · uploaded 10 Jul 2025Source
  • OthersInventory Division_Part1of2.pdf · uploaded 17 Jul 2025Source
  • OthersInventory Division_Part2of2.pdf · uploaded 17 Jul 2025Source

Migrated

  • Withdrawal Update Form 1Om Harmony Form-1 Sep 2025.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 2Om Harmony Form-2 Sep 2025.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 3Om Harmony Form-3 Sep 2025.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 1Om Harmony Form-1 Dec 2025.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 2Om Harmony Form-2 Dec 2025.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 3Om Harmony Form-3 Dec 2025.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 1Om Harmony Form-1 March 2026.pdf · uploaded 19 May 2026Source
  • Withdrawal Update Form 2Om Harmony Form-2 March 2026.pdf · uploaded 19 May 2026Source
  • Withdrawal Update Form 3Om Harmony Form-3 March 2026.pdf · uploaded 19 May 2026Source
  • Withdrawal Update Form 1Om Harmony Form-1 June 2026.pdf · uploaded 19 Jul 2026Source
  • Withdrawal Update Form 2Om Harmony Form-2 June 2026.pdf · uploaded 19 Jul 2026Source
  • Withdrawal Update Form 3Om Harmony Form-3 June 2026.pdf · uploaded 19 Jul 2026Source

Technical

  • DocumentIOD Drawing.pdf · uploaded 14 May 2025Source
  • DocumentOm Builders & Developers - Declaration Cum Undertaking.pdf · uploaded 21 May 2025Source
  • OthersOther_Declaration.pdf · uploaded 21 May 2025Source
  • OthersF 1 New.pdf · uploaded 21 May 2025Source
  • DocumentOm Harmony IoD and CC.pdf · uploaded 18 Jun 2025Source
  • OthersDeclaration Regarding Land Cost.pdf · uploaded 5 Aug 2025Source

Technical (Architect)

  • DocumentOm Harmony Form-1 June 2026.pdf · uploaded 19 Jul 2026Source

Technical (Engineer)

  • DocumentOm Harmony Form-2 June 2026.pdf · uploaded 19 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Ulawe, Panvel taluka

Survey, CTS, gat or plot numbers

Plot No. 162 of Sector 9

Boundaries

North
North
South
South
East
East
West
West

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantTrich design studio—
EngineerFulchand Vithalrao Adsul—
EngineerRajesh K Kale—
EngineerShravani Consultant—
OtherAr Dhavale—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology