The Crystal

Completion due May 2028

Taloje Panchnad, Raigarh 410208 |Promoter: Farooque Mahmood Miya Qazi

25 Nov 2024Registered with MahaRERA
30 May 2028Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

MahaRERA's search listing gives this project's name, promoter and location only.

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.07556, 73.09254
The Crystal is at latitude 19.07556, longitude 73.09254.
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 May 2028

Registered
25 Nov 2024
Promised
30 May 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200007813825 Nov 202430 May 2028—Farooque Mahmood Miya QaziProject page

Documents

1 document held by Deedo

Registration certificate

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Taloje Panchnad

Survey, CTS, gat or plot numbers

PLOT NO 36 Sector 11

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology