Hrishikesh 3

Certificate Signed

Nevali, Raigarh 410206 |Promoter: Rare Livspace

15 Sep 2023Registered with MahaRERA
31 Oct 2025Promised completion
1Building
87Units registered72 booked (83%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, Shop87 units in all
Address
Survey No. 3/3/B, Survey No. 3/3/B, NevaliPIN 410206
Designated bank account
76
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.02310, 73.12658
Hrishikesh 3 is at latitude 19.02310, longitude 73.12658.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Oct 2025

The latest completion date on record passed 1 year ago.

Registered
15 Sep 2023
Promised
31 Oct 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200005266615 Sep 202331 Oct 202531 Oct 2025Rare LivspaceProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building- Wing A, Wing B, Wing C and Wing D687

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

72 of 87 units booked (83%), as the promoter reported to MahaRERA

1BHK · 82 unitsShop · 5 units
TypeCarpet areaUnitsBooked
1BHK30.99 sq m · 334 sq ft1110
1BHK31.19 sq m · 336 sq ft6152
1BHK34.42 sq m · 370 sq ft1010
Shop4.95 sq m · 53 sq ft10
Shop6.95 sq m · 75 sq ft10
Shop9.28 sq m · 100 sq ft10
Shop9.38 sq m · 101 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 87 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPANCARD RARELIVSPACE.pdf · uploaded 22 Aug 2023Source

Legal

  • Declaration Form BForm B- Promoter(1).pdf · uploaded 22 Aug 2023Source
  • Legal Title reportSHORT TITLE_HRISHIKESH 3.pdf · uploaded 28 Aug 2023Source
  • Other – LegalSALE DEED NEVALI_11zon.pdf · uploaded 5 Sep 2023Source

Migrated

  • 1 PAN CardPANCARD RARELIVSPACE.pdf · uploaded 22 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)Rare-pg 1_11zon.pdf · uploaded 22 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentRare-pg 1_11zon.pdf · uploaded 22 Aug 2023Source
Show all 88 documentsShow fewer documents

Migrated

  • 2 Building Plan Approval / NA Order for plotted developmentRare-pg 2,3_11zon.pdf · uploaded 22 Aug 2023Source
  • 3 Building Plan Approval / NA Order for plotted developmentRare-pg 4,5_11zon.pdf · uploaded 22 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentBP-00665_2023_CCLetter.pdf · uploaded 22 Aug 2023Source
  • 1 Declaration in FORM BForm B- Promoter(1).pdf · uploaded 22 Aug 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 22 Aug 2023Source
  • 1 Proforma of Agreement for saleAFS-Hrishikesh 3.pdf · uploaded 25 Aug 2023Source
  • 1 Proforma of Allotment letterAl_Hrishikesh 3.pdf · uploaded 25 Aug 2023Source
  • 1 Copy of the legal title reportSHORT TITLE_HRISHIKESH 3.pdf · uploaded 28 Aug 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report-AFS.pdf · uploaded 28 Aug 2023Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance Finance.pdf · uploaded 31 Aug 2023Source
  • 2 a Details of encumbrances concerned to FinanceEncumbrance Legal.pdf · uploaded 31 Aug 2023Source
  • 1 b Details of encumbrances concerned to LegalEncumbrance Finance.pdf · uploaded 31 Aug 2023Source
  • 2 b Details of encumbrances concerned to LegalEncumbrance Legal.pdf · uploaded 31 Aug 2023Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 31 Aug 2023Source
  • 1 CERSAI detailsDeclaration on CERSAI.pdf · uploaded 31 Aug 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3_11zon.pdf · uploaded 31 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFORMAT A rare livspace.pdf · uploaded 31 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report- AL.pdf · uploaded 31 Aug 2023Source
  • 1 Other – LegalSALE DEED NEVALI_11zon.pdf · uploaded 5 Sep 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Hrishikesh 3 as on September 2023.pdf · uploaded 5 Dec 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Hrishikesh 3 as on 30-09-2023.pdf · uploaded 5 Dec 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Hrishikesh 3 as on 30-09-2023.pdf · uploaded 16 Dec 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Hrishikesh III - Dec 23.pdf · uploaded 20 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Hrishikesh 3 as on 31-12-2023.pdf · uploaded 20 Jan 2024Source
  • 1 Disclosure of sold/ booked inventoryCIRCULAR 29 - Hrishikesh 3 as on Dec 2023.pdf · uploaded 18 Mar 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Hrishikesh 3 as on March 2024.pdf · uploaded 15 Apr 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Hrishikesh 3 as on March 2024.pdf · uploaded 15 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Hrishikesh 3 as on March 2024.pdf · uploaded 26 Apr 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Hrishikesh III - June 2024.pdf · uploaded 19 Jul 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Hrishikesh 3 as on 30-06-2024.pdf · uploaded 19 Jul 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Hrishikesh 3 as on 30-09-2024.pdf · uploaded 19 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Hrishikesh III - Sept 2024.pdf · uploaded 19 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Hrishikesh 3 as on 31-12-2024.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Hrishikesh III - 31-12-2024.pdf · uploaded 20 Jan 2025Source
  • 1 Copy of Layout Approval (in case of layout)Plan 1.pdf · uploaded 29 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 29 Jan 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 29 Jan 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 29 Jan 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 4.pdf · uploaded 29 Jan 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentPlan 5.pdf · uploaded 29 Jan 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentPlan 6.pdf · uploaded 29 Jan 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 - Hrishikesh 3 for FY 23-24.pdf · uploaded 22 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - June 2024.pdf · uploaded 13 Mar 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - September 2024.pdf · uploaded 13 Mar 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - December 2024.pdf · uploaded 13 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Dec 2024.pdf · uploaded 13 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Dec 2024.pdf · uploaded 13 Mar 2025Source
  • 1 Disclosure of sold/ booked inventoryCircular 29.pdf · uploaded 13 Mar 2025Source
  • 1 Declaration about Commencement CertificateFormat D.pdf · uploaded 13 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A FY 2023-24.pdf · uploaded 13 Mar 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 FY 2023-24.pdf · uploaded 13 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Hrishikesh 3 as on 31st March 2025.pdf · uploaded 20 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Hrishikesh 3 as on March 2025.pdf · uploaded 20 Apr 2025Source
  • Form 5 (FY 2023-2024)2 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24) (2).pdf · uploaded 26 Jun 2025Source
  • Form 1ARCHITECT LETTER (2).pdf · uploaded 11 Jul 2025Source
  • Form 2Hrishikesh III-FORM 2.pdf · uploaded 11 Jul 2025Source
  • Form 3Hrishikesh III-FORM 3.pdf · uploaded 11 Jul 2025Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Hrishkesh III.pdf · uploaded 11 Jul 2025Source
  • Withdrawal Update Form 1Form 1 - Hrishikesh 3 as on June 2025.pdf · uploaded 9 Sep 2025Source
  • Withdrawal Update Form 2Form 2 - Hrishikesh 3 as on June 2025.pdf · uploaded 9 Sep 2025Source
  • Withdrawal Update Form 3Form 3 - Hrishikesh 3 as on June 2025.pdf · uploaded 9 Sep 2025Source

Technical

  • DocumentRare-pg 1_11zon.pdf · uploaded 22 Aug 2023Source
  • DocumentRare-pg 1_11zon.pdf · uploaded 22 Aug 2023Source
  • DocumentRare-pg 2,3_11zon.pdf · uploaded 22 Aug 2023Source
  • DocumentRare-pg 4,5_11zon.pdf · uploaded 22 Aug 2023Source
  • DocumentPlan 1.pdf · uploaded 29 Jan 2025Source
  • DocumentPlan 2.pdf · uploaded 29 Jan 2025Source
  • DocumentPlan 3.pdf · uploaded 29 Jan 2025Source
  • DocumentPlan 4.pdf · uploaded 29 Jan 2025Source
  • DocumentPlan 5.pdf · uploaded 29 Jan 2025Source
  • DocumentPlan 6.pdf · uploaded 29 Jan 2025Source

Technical (Architect)

  • DocumentForm 1 - June 2024.pdf · uploaded 13 Mar 2025Source
  • DocumentForm 1 - September 2024.pdf · uploaded 13 Mar 2025Source
  • DocumentForm 1 - December 2024.pdf · uploaded 13 Mar 2025Source
  • DocumentForm 1 - Hrishikesh 3 as on June 2025.pdf · uploaded 9 Sep 2025Source

Technical (Engineer)

  • DocumentForm 2 - Hrishikesh III - Sept 2024.pdf · uploaded 19 Oct 2024Source
  • DocumentForm 2 - Hrishikesh III - 31-12-2024.pdf · uploaded 20 Jan 2025Source
  • DocumentForm 2 - Dec 2024.pdf · uploaded 13 Mar 2025Source
  • DocumentForm 2 - Hrishikesh 3 as on March 2025.pdf · uploaded 20 Apr 2025Source
  • DocumentForm 2 - Hrishikesh 3 as on June 2025.pdf · uploaded 9 Sep 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nevali, Panvel taluka

Survey, CTS, gat or plot numbers

Survey No. 3/3/B

Boundaries

North
Open plot
South
Open plot
East
Open plot
West
Survey No-3 Hissa No- 3 4 and 5

Source: registration certificates and MahaRERA's project page, as stated there.