Twin Towers
Certificate SignedMamdapur, Raigarh 410101 |Promoter: A M Enterprises
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 2
- Unit types
- 1BHK, Shop73 units in all
- Address
- Survey No 168 Plot No 17 And 20, Kalyan Karjat Road, NeralPIN 410101
- Designated bank account
- 76
- Developed in phases
- Yes
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 25 Dec 2025
The latest completion date on record passed 10 months ago.
- Registered
- 11 Apr 2022
- Promised
- 25 Dec 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000034526 | 11 Apr 2022 | 25 Dec 2025 | 25 Dec 2025 | A M Enterprises | Project page |
2 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
26 of 73 units booked (36%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing A | 1BHK | 30.8 sq m · 332 sq ft | 1 | 1 |
| Wing A | 1BHK | 40 sq m · 431 sq ft | 25 | 11 |
| Wing A | 1BHK | 43 sq m · 463 sq ft | 2 | 2 |
| Wing A | Shop | 11.61 sq m · 125 sq ft | 2 | 1 |
| Wing A | Shop | 14.52 sq m · 156 sq ft | 4 | 2 |
| Wing B | 1BHK | 33.21 sq m · 357 sq ft | 6 | 0 |
| Wing B | 1BHK | 40 sq m · 431 sq ft | 24 | 6 |
| Wing B | Shop | 8.6 sq m · 93 sq ft | 1 | 0 |
Show all 14 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing B | Shop | 11.3 sq m · 122 sq ft | 1 | 1 |
| Wing B | Shop | 12 sq m · 129 sq ft | 2 | 0 |
| Wing B | Shop | 12.5 sq m · 135 sq ft | 1 | 1 |
| Wing B | Shop | 12.7 sq m · 137 sq ft | 1 | 1 |
| Wing B | Shop | 13.25 sq m · 143 sq ft | 1 | 0 |
| Wing B | Shop | 17.05 sq m · 184 sq ft | 2 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 76 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD COPY.pdf · uploaded 28 Mar 2022Source
Legal
- Legal Title reportSEARCH AND TITLE PLOT NO 17.pdf · uploaded 28 Mar 2022Source
- Legal Title reportSEARCH AND TITLE PLOT NO 20.pdf · uploaded 28 Mar 2022Source
- Declaration Form BFORM B (1).pdf · uploaded 29 Mar 2022Source
- Legal Title reportLAYOUT PLAN 02 (1) (1).pdf · uploaded 30 Mar 2022Source
- Legal Title reportLEGAL TITLE REPORT PLOT NO 17 CONVERT.pdf · uploaded 7 Apr 2022Source
- Legal Title reportLEGAL TITLE REPORT PLOT NO 20 CONVERT.pdf · uploaded 7 Apr 2022Source
Show all 77 documentsShow fewer documents
Migrated
- 1 PAN CardPAN CARD COPY.pdf · uploaded 28 Mar 2022Source
- 1 Copy of the legal title reportSEARCH AND TITLE PLOT NO 17.pdf · uploaded 28 Mar 2022Source
- 2 Copy of the legal title reportSEARCH AND TITLE PLOT NO 20.pdf · uploaded 28 Mar 2022Source
- 1 Details of encumbrancesNON ENCUMBRANCES CERTIFICATE PDF.pdf · uploaded 28 Mar 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentN A ORDER (2).pdf · uploaded 28 Mar 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentN A ORDER (2).pdf · uploaded 28 Mar 2022Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT C C.pdf · uploaded 28 Mar 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE (1).pdf · uploaded 28 Mar 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE (1).pdf · uploaded 28 Mar 2022Source
- 1 Disclosure of sold/ booked inventoryRERA CARPET (1).pdf · uploaded 28 Mar 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 C A LETTER (1).pdf · uploaded 28 Mar 2022Source
- 1 Declaration in FORM BFORM B (1).pdf · uploaded 29 Mar 2022Source
- 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 29 Mar 2022Source
- 3 Copy of the legal title reportLAYOUT PLAN 02 (1) (1).pdf · uploaded 30 Mar 2022Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN 01 (1) (1).pdf · uploaded 30 Mar 2022Source
- 1 Proforma of Allotment letterTWIN TOWER SALE AGREEMENT.pdf · uploaded 30 Mar 2022Source
- 4 Copy of the legal title reportLEGAL TITLE REPORT PLOT NO 17 CONVERT.pdf · uploaded 7 Apr 2022Source
- 5 Copy of the legal title reportLEGAL TITLE REPORT PLOT NO 20 CONVERT.pdf · uploaded 7 Apr 2022Source
- 2 Copy of Layout Approval (in case of layout)LAYOUT PLAN 02 (1) (1).pdf · uploaded 7 Apr 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)1ARCHITECT.pdf · uploaded 12 Aug 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)2ARCHITECT.pdf · uploaded 12 Aug 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)3ARCHITECT.pdf · uploaded 12 Aug 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)4ARCHITECT.pdf · uploaded 12 Aug 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)5ARCHITECT.pdf · uploaded 12 Aug 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)6ARCHITECT.pdf · uploaded 12 Aug 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)7ARCHITECT.pdf · uploaded 12 Aug 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)1ENGINEER.pdf · uploaded 12 Aug 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)2ENGINEER.pdf · uploaded 12 Aug 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)3ENGINEER.pdf · uploaded 12 Aug 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)4ENGINEER.pdf · uploaded 12 Aug 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)5ENGINEER.pdf · uploaded 12 Aug 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)6ENGINEER.pdf · uploaded 12 Aug 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)7ENGINEER.pdf · uploaded 12 Aug 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)JUNE22.pdf · uploaded 13 Aug 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)SEP22.pdf · uploaded 13 Aug 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)DEC22.pdf · uploaded 13 Aug 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)MAR23.pdf · uploaded 13 Aug 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)JUN23.pdf · uploaded 13 Aug 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)SEP23.pdf · uploaded 13 Aug 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)DEC23.pdf · uploaded 13 Aug 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 MAR 2024.pdf · uploaded 18 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 JUNE 2024.pdf · uploaded 18 Feb 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SEPT 2024.pdf · uploaded 18 Feb 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DEC 2024.pdf · uploaded 18 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MAR 2024_compressed (1).pdf · uploaded 18 Feb 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 JUNE 2024_compressed (1).pdf · uploaded 18 Feb 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 SEPT 2024_compressed.pdf · uploaded 18 Feb 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 DEC 2024_compressed.pdf · uploaded 18 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 MAR 2024.pdf · uploaded 18 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 JUNE 2024.pdf · uploaded 18 Feb 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 SEPT 2024.pdf · uploaded 18 Feb 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 DEC 2024.pdf · uploaded 18 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 22-23.pdf · uploaded 20 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 23-24.pdf · uploaded 20 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A MAR 2023.pdf · uploaded 21 Feb 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A MAR 2024.pdf · uploaded 21 Feb 2025Source
Technical
Technical (Architect)
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Mamdapur, Karjat taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Road
- South
- Road
- East
- Plot No 16
- West
- Plot No 19
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Brahmand Architect | — |
| Chartered accountant | Lakadia & Co | — |
| Engineer | Brahmand Architect | — |
Source: MahaRERA project page. Contact details are not shown.