Skip to content
Deedo home
Menu

The Signature

Certificate Signed

Khopoli, Raigarh 410203 |Promoter: Arp Infra

29 Nov 2024Registered with MahaRERA
31 Dec 2029Promised completion
30 Apr 2030Revised completionPushed back 4 months
1Building
148Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—148 units in all
Address
C.T.S. NO. 1635/B/1, S. NO. 9/1B, Sector-3, Chinchavali ShekinPIN 410203
Designated bank account
76
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.80652, 73.32724
The Signature is at latitude 18.80652, longitude 73.32724.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
29 Nov 2024
Promised
31 Dec 2029
Revised
30 Apr 2030

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200007821429 Nov 202431 Dec 202930 Apr 2030Arp InfraProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Arp Infra9148

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

148 units registered

— · 148 units
TypeCarpet areaUnits
——148

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 54 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan card of the firm.pdf · uploaded 19 Oct 2024Source

Legal

  • Other – LegalD'souza Plot- Purchase Agreement (ARP INFRA)_11zon.pdf · uploaded 30 Oct 2024Source
  • Declaration Form BAffidavit cum Declaration (2).pdf · uploaded 30 Oct 2024Source
  • Legal Title reportTitle page 2 to 9_merged.pdf · uploaded 30 Oct 2024Source

Migrated

  • 1 PAN CardPan card of the firm.pdf · uploaded 19 Oct 2024Source
  • 1 a Details of encumbrances concerned to Finance1 a Details of encumbrances concerned to Finance .pdf · uploaded 19 Oct 2024Source
  • 2 a Details of encumbrances concerned to Finance1 b Details of encumbrances concerned to Legal .pdf · uploaded 19 Oct 2024Source
Show all 55 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentARP CC .pdf · uploaded 19 Oct 2024Source
  • 1 CERSAI details1 CERSAI details .pdf · uploaded 19 Oct 2024Source
  • 1 b Details of encumbrances concerned to Legal1 a Details of encumbrances concerned to Finance .pdf · uploaded 19 Oct 2024Source
  • 2 b Details of encumbrances concerned to Legal1 b Details of encumbrances concerned to Legal .pdf · uploaded 19 Oct 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of interest in other real estate organisation merged.pdf · uploaded 19 Oct 2024Source
  • 1 Disclosure for secured/unsecured finance availed for the project1 Disclosure for securedunsecured finance availed for the project .pdf · uploaded 19 Oct 2024Source
  • 1 Copy of the legal title reportTitle page 2 to 9_merged.pdf · uploaded 30 Oct 2024Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 30 Oct 2024Source
  • 1 Proforma of Allotment letterAL - The Signature.pdf · uploaded 30 Oct 2024Source
  • 1 Declaration in FORM BAffidavit cum Declaration (2).pdf · uploaded 30 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)ARP- FORM 3.pdf · uploaded 30 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted development1 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 30 Oct 2024Source
  • 1 Other – LegalD'souza Plot- Purchase Agreement (ARP INFRA)_11zon.pdf · uploaded 30 Oct 2024Source
  • 1 Declaration about Commencement CertificateFormat D - ARP INFRA.pdf · uploaded 30 Oct 2024Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format A ARP INFRA.pdf · uploaded 30 Oct 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation AL.pdf · uploaded 30 Oct 2024Source
  • 1 Other – TechnicalAnnexure A - Order no 50 - Arp Infra.pdf · uploaded 30 Oct 2024Source
  • 2 Other – TechnicalCC Verification mail of ARP Infra (1).pdf · uploaded 30 Oct 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation AFS.pdf · uploaded 30 Oct 2024Source
  • 1 Proforma of Agreement for saleFinal AFS-ARP Infra.pdf · uploaded 30 Oct 2024Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B - ARP Infra.pdf · uploaded 30 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Certificates of Architect.pdf · uploaded 19 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER’S CERTIFICATE-ARP INFRA.pdf · uploaded 19 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form 2A.pdf · uploaded 19 Apr 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 _ARP.pdf · uploaded 19 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryThe Signature - Sold Unsold Inventory (RERA).pdf · uploaded 21 Apr 2025Source
  • Form 2A (FY 2024-2025)form 2A.pdf · uploaded 18 Jul 2025Source
  • Form 2A (FY 2025-2026)form 2A second.pdf · uploaded 19 Jul 2025Source
  • Form 5 (FY 2024-2025)Form 5 _ARP.pdf · uploaded 19 Jul 2025Source
  • Withdrawal Update Form 1Form 1 30-09-2025.pdf · uploaded 20 Mar 2026Source
  • Withdrawal Update Form 1Form 1 30-12-2025.pdf · uploaded 20 Mar 2026Source
  • Withdrawal Update Form 2Form 2 30-09-2025.pdf · uploaded 20 Mar 2026Source
  • Withdrawal Update Form 2Form 2 30-09-2025.pdf · uploaded 20 Mar 2026Source
  • Withdrawal Update Form 3Form 3 30-09-2025.pdf · uploaded 20 Mar 2026Source
  • Withdrawal Update Form 3FORM-3 CA Certificate (31-12-2025).pdf · uploaded 20 Mar 2026Source
  • Withdrawal Update Form 1Form 1 Certificates of Architect.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 2form2.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 3FORM3 .pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 1Form 1 Certificates of Architect.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2form 2 ENGINEERs CERTIFICATE.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 20 Jul 2026Source

Technical

  • Document1 Building Plan Approval _ NA Order for plotted development.pdf · uploaded 30 Oct 2024Source
  • DocumentLayout.pdf · uploaded 30 Oct 2024Source
  • Other – TechnicalCC Verification mail of ARP Infra (1).pdf · uploaded 30 Oct 2024Source
  • Other – TechnicalAnnexure A - Order no 50 - Arp Infra.pdf · uploaded 30 Oct 2024Source

Technical (Architect)

  • DocumentForm 1 Certificates of Architect.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • Documentform 2 ENGINEERs CERTIFICATE.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Khopoli, Khalapur taluka

Survey, CTS, gat or plot numbers

C.T.S. NO. 1635/B/1S. NO. 9/1B

Boundaries

North
C S No 1635 A
South
C S No 1634
East
D P Road
West
C S No 1635 A

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPointline Architects—
Chartered accountantDevchand Vora—
Chartered accountantshailee shah—
EngineerSK Consultants and Engineers—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology