4/A, 4/B, 4/C · Mahaavir Majesty
Ghot · RERA P52000016434
IDBLD_0141016 floorsPromised date passed
6Sanctioned habitable floorsregistration certificate
30 Dec 2022Revised completionpromised 30 Dec 2022
62 of 62Units bookedMahaRERA project page
Floors
6 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52000016434 · registered 10 May 2018
- Promised completion
- 30 Dec 2022
- Revised completion
- 30 Dec 2022
- Sanctioned habitable floors
- 6
- ProjectId
- 17,870
- ProjectName
- Mahaavir Majesty - Phase II
- TotalUnitCount
- 0
- ProjectBuildingId
- 18,095
- BuildingNameNumber
- 4/A, 4/B, 4/C
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52000016434
- ProjectBuildingWingsId
- 18,095
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- 4/A, 4/B, 4/C
- NoOfBuildingWingFloorProposed
- 6
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 6
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 30 m² (323 sq.ft) | 24 | 24 |
| 1 BHK | 30.5 m² (328 sq.ft) | 24 | 24 |
| 1 BHK | 31.9 m² (343 sq.ft) | 4 | 4 |
| 1 BHK | 35 m² (377 sq.ft) | 5 | 5 |
| 1 RK | 22 m² (237 sq.ft) | 1 | 1 |
| 2 BHK | 48 m² (517 sq.ft) | 4 | 4 |
| Total | 62 | 62 |
Data through12 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology