Krishna Imperial

Certificate Signed

Dapoli, Raigarh 410206 |Promoter: Krishna Enterprises

Residential / Group HousingRERAP52000026891
3 Nov 2020Registered with MahaRERA
30 Jun 2026Promised completion
30 Oct 2026Revised completionPushed back 4 months
1Building
111Units registered76 booked (68%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, Office space, Shop111 units in all
Address
Plot No.08, Sector No.08, Node Pushpak, DapoliPIN 410206
Designated bank account
1
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
3 Nov 2020
Promised
30 Jun 2026
Revised
30 Oct 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P520000268913 Nov 202030 Jun 202630 Oct 2026Krishna EnterprisesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Krishna Imperial11111

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

76 of 111 units booked (68%), as the promoter reported to MahaRERA

1BHK · 46 units2BHK · 47 unitsOffice space · 9 unitsShop · 9 units
TypeCarpet areaUnitsBooked
1BHK28.78 sq m · 310 sq ft87
1BHK28.84 sq m · 310 sq ft77
1BHK32.5 sq m · 350 sq ft1511
1BHK35.04 sq m · 377 sq ft10
1BHK35.04 sq m · 377 sq ft76
1BHK35.04 sq m · 377 sq ft87
2BHK56.47 sq m · 608 sq ft85
2BHK56.55 sq m · 609 sq ft87
Show all 25 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK57.16 sq m · 615 sq ft85
2BHK57.16 sq m · 615 sq ft77
2BHK57.83 sq m · 622 sq ft169
Office space35.25 sq m · 379 sq ft10
Office space35.26 sq m · 380 sq ft10
Office space35.83 sq m · 386 sq ft20
Office space39.07 sq m · 421 sq ft10
Office space39.36 sq m · 424 sq ft10
Office space39.36 sq m · 424 sq ft10
Office space40.86 sq m · 440 sq ft10
Office space40.92 sq m · 440 sq ft11
Shop41.1 sq m · 442 sq ft21
Shop41.12 sq m · 443 sq ft11
Shop41.37 sq m · 445 sq ft11
Shop41.78 sq m · 450 sq ft21
Shop45.9 sq m · 494 sq ft20
Shop58.16 sq m · 626 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 92 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFIRM PAN CARD.pdf · uploaded 29 Oct 2020Source

Legal

  • OtherCREDAI CERTIFICATE.pdf · uploaded 29 Oct 2020Source
  • Legal Title reportTITLE REPORT.pdf · uploaded 29 Oct 2020Source
  • Legal Title reportSEARCH REPORT.pdf · uploaded 29 Oct 2020Source
  • Declaration Form BFORM B.pdf · uploaded 29 Oct 2020Source

Migrated

  • 1 PAN CardFIRM PAN CARD.pdf · uploaded 29 Oct 2020Source
  • 1 Copy of the legal title reportTITLE REPORT.pdf · uploaded 29 Oct 2020Source
Show all 93 documentsShow fewer documents

Migrated

  • 2 Copy of the legal title reportSEARCH REPORT.pdf · uploaded 29 Oct 2020Source
  • 1 Details of encumbrancesENCUMBRANCES LETTER.pdf · uploaded 29 Oct 2020Source
  • 1 Copy of Layout Approval (in case of layout)BUILDING PLAN AND LAYOUT PLAN.pdf · uploaded 29 Oct 2020Source
  • 1 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN AND LAYOUT PLAN.pdf · uploaded 29 Oct 2020Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C.pdf · uploaded 29 Oct 2020Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 29 Oct 2020Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 29 Oct 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.pdf · uploaded 29 Oct 2020Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 29 Oct 2020Source
  • 1 Proforma of Allotment letterDRAFT ALLOTMENT LETTER.pdf · uploaded 29 Oct 2020Source
  • 2 Proforma of Allotment letterDRAFT SALE AGREEMENT.pdf · uploaded 29 Oct 2020Source
  • 1 OtherCREDAI CERTIFICATE.pdf · uploaded 29 Oct 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)KE KRISHNA IMPERIAL FORM 5.pdf · uploaded 1 Apr 2022Source
  • 2 Copy of Layout Approval (in case of layout)LAYOUT_9 FLOOR_11zon (1).pdf · uploaded 3 Nov 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentLAYOUT_9 FLOOR_11zon (1).pdf · uploaded 3 Nov 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC_FOR 9 FLOOR.pdf · uploaded 3 Nov 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 FY 2021-22 KRISHNA IMPERIAL.pdf · uploaded 25 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 KRISHNA IMPERIAL.pdf · uploaded 2 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 KRISHNA IMPERIAL.pdf · uploaded 10 Dec 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 FORM 1 IMPERIAL 30 6 2023.pdf · uploaded 21 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 FORM 1 IMPERIAL 30 9 2023.pdf · uploaded 21 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 FORM 1 IMPERIAL 31 12 2023.pdf · uploaded 21 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 FORM 1 IMPERIAL 31 03 2024.pdf · uploaded 21 Feb 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)6 FORM 1 IMPERIAL 30 6 2024.pdf · uploaded 21 Feb 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)7 FORM 1 IMPERIAL 30 9 2024.pdf · uploaded 21 Feb 2025Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)8 FORM 1 IMPERIAL 31 12 2024.pdf · uploaded 21 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 FORM 1 IMPERIAL 31 03 2023.pdf · uploaded 21 Feb 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentREVISED CC.pdf · uploaded 21 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)19 FORM 3 CA CERT 30 09 2023.pdf · uploaded 22 Feb 2025Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)24 FORM 3 CA CERT 31 12 2024.pdf · uploaded 22 Feb 2025Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)23 FORM 3 CA CERT 30 09 2024.pdf · uploaded 22 Feb 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)22 FORM 3 CA CERT 30 06 2024.pdf · uploaded 22 Feb 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)21 FORM 3 CA CERT 31 03 2024.pdf · uploaded 22 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)20 FORM 3 CA CERT 31 12 2023.pdf · uploaded 22 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)18 FORM 3 CA CERT 30 06 2023.pdf · uploaded 22 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)17 FORM 3 CA CERT 31 03 2023.pdf · uploaded 22 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)27 FORM 2 IMPERIAL 30 09 2023.pdf · uploaded 22 Feb 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)32 FORM 2 IMPERIAL 31 12 2024.pdf · uploaded 22 Feb 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)31 FORM 2 IMPERIAL 30 09 2024.pdf · uploaded 22 Feb 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)30 FORM 2 IMPERIAL 30 06 2024.pdf · uploaded 22 Feb 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)29 FORM 2 IMPERIAL 31 03 2024.pdf · uploaded 22 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)28 FORM 2 IMPERIAL 31 12 2023.pdf · uploaded 22 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)26 FORM 2 IMPERIAL 30 06 2023.pdf · uploaded 22 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)25 FORM 2 IMPERIAL 31 03 2023.pdf · uploaded 22 Feb 2025Source
  • 1 Disclosure of sold/ booked inventory9 IMPERIAL SOLD UNSOLD 31 03 2023.pdf · uploaded 22 Feb 2025Source
  • 2 Disclosure of sold/ booked inventory10 IMPERIAL SOLD UNSOLD 30 06 2023.pdf · uploaded 22 Feb 2025Source
  • 3 Disclosure of sold/ booked inventory11 IMPERIAL SOLD UNSOLD 30 09 2023.pdf · uploaded 22 Feb 2025Source
  • 4 Disclosure of sold/ booked inventory12 IMPERIAL SOLD UNSOLD 31 12 2023.pdf · uploaded 22 Feb 2025Source
  • 5 Disclosure of sold/ booked inventory13 IMPERIAL SOLD UNSOLD 31 03 2024.pdf · uploaded 22 Feb 2025Source
  • 6 Disclosure of sold/ booked inventory14 IMPERIAL SOLD UNSOLD 30 06 2024.pdf · uploaded 22 Feb 2025Source
  • 7 Disclosure of sold/ booked inventory15 IMPERIAL SOLD UNSOLD 30 09 2024.pdf · uploaded 22 Feb 2025Source
  • 8 Disclosure of sold/ booked inventory16 IMPERIAL SOLD UNSOLD 31 12 2024.pdf · uploaded 22 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A IMPERIAL 31 03 2023.pdf · uploaded 24 Feb 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A IMPERIAL 31 03 2024.pdf · uploaded 24 Feb 2025Source
  • Withdrawal Update Form 1FORM 1 KRISHNA IMPERIAL 30 06 2025.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 2FORM 2 KRISHNA IMPERIAL 30 06 2025.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 3FORM 3 KRISHNA IMPERIAL 30 06 2025 FINAL.pdf · uploaded 30 Jun 2026Source
  • Withdrawal Update Form 1FORM 1 IMPERIAL 30 09 2025.pdf · uploaded 1 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 IMPERIAL 30 09 2025.pdf · uploaded 1 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 IMPERIAL 30 09 2025 FINAL.pdf · uploaded 1 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 ARCHITECT 31 12 2025.pdf · uploaded 6 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 ENGINEER 31 12 2025.pdf · uploaded 6 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 CA IMPERIAL 31 12 2025.pdf · uploaded 6 Jul 2026Source

Technical

  • DocumentBUILDING PLAN AND LAYOUT PLAN.pdf · uploaded 29 Oct 2020Source
  • DocumentBUILDING PLAN AND LAYOUT PLAN.pdf · uploaded 29 Oct 2020Source
  • DocumentLAYOUT_9 FLOOR_11zon (1).pdf · uploaded 3 Nov 2022Source
  • DocumentLAYOUT_9 FLOOR_11zon (1).pdf · uploaded 3 Nov 2022Source

Technical (Architect)

  • Document1 FORM 1 IMPERIAL 31 03 2023.pdf · uploaded 21 Feb 2025Source
  • Document2 FORM 1 IMPERIAL 30 6 2023.pdf · uploaded 21 Feb 2025Source
  • Document3 FORM 1 IMPERIAL 30 9 2023.pdf · uploaded 21 Feb 2025Source
  • Document4 FORM 1 IMPERIAL 31 12 2023.pdf · uploaded 21 Feb 2025Source
  • Document5 FORM 1 IMPERIAL 31 03 2024.pdf · uploaded 21 Feb 2025Source
  • Document6 FORM 1 IMPERIAL 30 6 2024.pdf · uploaded 21 Feb 2025Source
  • Document7 FORM 1 IMPERIAL 30 9 2024.pdf · uploaded 21 Feb 2025Source
  • Document8 FORM 1 IMPERIAL 31 12 2024.pdf · uploaded 21 Feb 2025Source
  • DocumentFORM 1 ARCHITECT 31 12 2025.pdf · uploaded 6 Jul 2026Source

Technical (Engineer)

  • Document25 FORM 2 IMPERIAL 31 03 2023.pdf · uploaded 22 Feb 2025Source
  • Document26 FORM 2 IMPERIAL 30 06 2023.pdf · uploaded 22 Feb 2025Source
  • Document27 FORM 2 IMPERIAL 30 09 2023.pdf · uploaded 22 Feb 2025Source
  • Document28 FORM 2 IMPERIAL 31 12 2023.pdf · uploaded 22 Feb 2025Source
  • Document29 FORM 2 IMPERIAL 31 03 2024.pdf · uploaded 22 Feb 2025Source
  • Document30 FORM 2 IMPERIAL 30 06 2024.pdf · uploaded 22 Feb 2025Source
  • Document31 FORM 2 IMPERIAL 30 09 2024.pdf · uploaded 22 Feb 2025Source
  • Document32 FORM 2 IMPERIAL 31 12 2024.pdf · uploaded 22 Feb 2025Source
  • DocumentFORM 2 ENGINEER 31 12 2025.pdf · uploaded 6 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dapoli, Panvel taluka

Survey, CTS, gat or plot numbers

PLOT NO.08SECTOR NO.08

Boundaries

North
20 Mtr Wide Road
South
Plot No 12 And 13
East
Plot No 07
West
Plot No 09

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDestination—
Chartered accountantYogesh Nanda And Associates—
EngineerS R Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology