Skip to content

Delta Greens

Certificate Signed

Dapoli, Raigarh 410206 |Promoter: Shreenathji Enterprises

28 Apr 2022Registered with MahaRERA
31 Jul 2027Promised completion
2Buildings
204Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
—204 units in all
Address
08, Plot No 08 Sector 04 Pushpak Node Dapoli, Pushpak Node DapoliPIN 410206
Designated bank account
76
Developed in phases
Yes

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Jul 2027

Registered
28 Apr 2022
Promised
31 Jul 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200003490128 Apr 202231 Jul 202731 Jul 2027Shreenathji EnterprisesProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A Wing1287
B Wing12117

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

204 units registered

— · 204 units
BuildingTypeCarpet areaUnits
A Wing——87
B Wing——117

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 94 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardShreenathji Enterprises pan card.pdf · uploaded 21 Mar 2022Source
  • PAN CardNBG PAN and Aadhar.pdf · uploaded 21 Mar 2022Source

Legal

  • Declaration Form BForm B.pdf · uploaded 21 Mar 2022Source
  • Other1 TP SGE Plot 8 Sec 4 Pushpak-1-25_.pdf · uploaded 22 Mar 2022Source
  • Other2 TP SGE Plot 8 Sec 4 Pushpak-26-45.pdf · uploaded 22 Mar 2022Source
  • Other3 TP SGE Plot 8 Sec 4 Pushpak-46-68_.pdf · uploaded 22 Mar 2022Source
  • OtherFinal Order.pdf · uploaded 22 Mar 2022Source
Show all 95 documentsShow fewer documents

Legal

  • Legal Title reportLegal Report.pdf · uploaded 1 Apr 2022Source

Migrated

  • 1 PAN CardShreenathji Enterprises pan card.pdf · uploaded 21 Mar 2022Source
  • 2 PAN CardNBG PAN and Aadhar.pdf · uploaded 21 Mar 2022Source
  • 1 Details of encumbrancesDeclaration for Encumbrance.pdf · uploaded 21 Mar 2022Source
  • 1 Copy of Layout Approval (in case of layout)1 CC Plan.pdf · uploaded 21 Mar 2022Source
  • 1 Building Plan Approval / NA Order for plotted development1 CC Plan.pdf · uploaded 21 Mar 2022Source
  • 2 Building Plan Approval / NA Order for plotted development2 CC Plan.pdf · uploaded 21 Mar 2022Source
  • 3 Building Plan Approval / NA Order for plotted development3 CC Plan.pdf · uploaded 21 Mar 2022Source
  • 4 Building Plan Approval / NA Order for plotted development4 CC Plan.pdf · uploaded 21 Mar 2022Source
  • 5 Building Plan Approval / NA Order for plotted development5 CC Plan.pdf · uploaded 21 Mar 2022Source
  • 6 Building Plan Approval / NA Order for plotted development6 CC Plan.pdf · uploaded 21 Mar 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 21 Mar 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 Architect Certificate.pdf · uploaded 21 Mar 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Delta Greens.pdf · uploaded 21 Mar 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate D Greens.pdf · uploaded 21 Mar 2022Source
  • 1 CERSAI detailsUndertaking CERSAI.pdf · uploaded 22 Mar 2022Source
  • 1 Other1 TP SGE Plot 8 Sec 4 Pushpak-1-25_.pdf · uploaded 22 Mar 2022Source
  • 2 Other2 TP SGE Plot 8 Sec 4 Pushpak-26-45.pdf · uploaded 22 Mar 2022Source
  • 3 Other3 TP SGE Plot 8 Sec 4 Pushpak-46-68_.pdf · uploaded 22 Mar 2022Source
  • 4 OtherFinal Order.pdf · uploaded 22 Mar 2022Source
  • 1 Copy of the legal title reportLegal Report.pdf · uploaded 1 Apr 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate Plot No 08 up to 7th floor.pdf · uploaded 1 Apr 2022Source
  • 1 Declaration about Commencement CertificateDeclaration about CC Format - D.pdf · uploaded 1 Apr 2022Source
  • 1 Proforma of Allotment letterAllotment Letter - Plot 8 Sector 4 Pushpak Dapoli.pdf · uploaded 1 Apr 2022Source
  • 2 Proforma of Allotment letterAFS Plot 08.pdf · uploaded 15 Apr 2022Source
  • 7 Building Plan Approval / NA Order for plotted developmentAmended CC Drawing - Plot 8 Sector 4.pdf · uploaded 24 Nov 2022Source
  • 2 Commencement Certificates / NA Order for plotted developmentAmended CC - Plot 8 Sector 4.pdf · uploaded 24 Nov 2022Source
  • 1 Proforma of Agreement for saleMORTGAGE DRAFT NEW REVISED DELTA GREENS.pdf · uploaded 30 Jan 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)GREENS 02.pdf · uploaded 26 Sep 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Delta Greens_Form 5_FY 2022-23 scanned copy.pdf · uploaded 28 Sep 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)D Greens.pdf · uploaded 17 Oct 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Delta Greens_compressed.pdf · uploaded 21 Oct 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)DELTA GREENS RERA CERTIFICATE Form 1.pdf · uploaded 20 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Signed Q4 - 2023 D Greens Form No 2 Eng Certificate.pdf · uploaded 20 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Delta Greens - Form 3_11zon.pdf · uploaded 22 Jan 2024Source
  • 2 Proforma of Agreement for saleDRAFT AGREEMENT - DELTA GREENS.pdf · uploaded 15 Mar 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q1 2024 FORM 01 DELTA GREEN.pdf · uploaded 20 Apr 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Q1 2024 Form 2 D Greens below 1MB.pdf · uploaded 20 Apr 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q1 2024 Form 3 D Greens below 3MB.pdf · uploaded 25 Apr 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)D Elite FORM 1.pdf · uploaded 19 Jul 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)D Greens FORM 1.pdf · uploaded 19 Jul 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)D Elite - Form No 2 Eng Certificate.pdf · uploaded 19 Jul 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)D Greens- Form No 2 Eng Certificate.pdf · uploaded 19 Jul 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Delta Greens (Q1) FY 24-25.pdf · uploaded 26 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FLORA 06 RERA FORM 01.pdf · uploaded 25 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)GREEN 06 RERA FORM 1.pdf · uploaded 25 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Greens.pdf · uploaded 6 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)DELTA GREENS FORM 3 Q3[1] signed.pdf · uploaded 14 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 DELTA GREEN Signed.pdf · uploaded 7 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Delta Greens Form 1.pdf · uploaded 19 Apr 2025Source
  • Withdrawal Update Form 1Q1 2024 FORM 01 DELTA GREEN.pdf · uploaded 11 Jan 2026Source
  • Withdrawal Update Form 1FORM 1 RERA CERTIFICATE GREENS.pdf · uploaded 11 Jan 2026Source
  • Withdrawal Update Form 2Q1 2024 Form 2 D Greens below 1MB1.pdf · uploaded 11 Jan 2026Source
  • Withdrawal Update Form 2form-2 Delta Greens.pdf · uploaded 11 Jan 2026Source
  • Withdrawal Update Form 3Form 3 - Delta Greens (Q1) FY 24-25.pdf · uploaded 11 Jan 2026Source
  • Withdrawal Update Form 3RERA form 3.pdf · uploaded 11 Jan 2026Source
  • Withdrawal Update Form 1FORM 1 RERA CERTIFICATE GREENS.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2form-2 Delta Greens.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3RERA form 3.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1FORM 1 RERA CERTIFICATE GREENS.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 2form-2 Delta Greens.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 3RERA form 3.pdf · uploaded 25 Apr 2026Source
  • Withdrawal Update Form 1Form 1_Greens.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 2DELTA_GREENS_Form2_Q1_2026-27_06-08-2026_11-23.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 3Form 3 - DG - 30-06-2026 - signed_compressed.pdf · uploaded 12 Aug 2026Source
  • Form 2A (FY 2022-2023)Form 2A - FY 2022-23.pdf · uploaded 15 Sep 2026Source
  • Form 2A (FY 2023-2024)Form 2A - FY 2023-24.pdf · uploaded 15 Sep 2026Source
  • Form 2A (FY 2024-2025)Form 2A - FY 2024-25.pdf · uploaded 15 Sep 2026Source
  • Form 2A (FY 2025-2026)Form 2A - FY 2025-26 - Greens.pdf · uploaded 15 Sep 2026Source

Technical

  • Document1 CC Plan.pdf · uploaded 21 Mar 2022Source
  • Document3 CC Plan.pdf · uploaded 21 Mar 2022Source
  • Document4 CC Plan.pdf · uploaded 21 Mar 2022Source
  • Document5 CC Plan.pdf · uploaded 21 Mar 2022Source
  • Document6 CC Plan.pdf · uploaded 21 Mar 2022Source
  • Document1 CC Plan.pdf · uploaded 21 Mar 2022Source
  • Document2 CC Plan.pdf · uploaded 21 Mar 2022Source
  • DocumentAmended CC Drawing - Plot 8 Sector 4.pdf · uploaded 24 Nov 2022Source
  • DocumentPlan 1 - Built up area highlighted.pdf · uploaded 15 Sep 2026Source
  • DocumentPlan 2 - Parking and Tenement highlighted.pdf · uploaded 15 Sep 2026Source
  • DocumentPlan 3 - 8.pdf · uploaded 15 Sep 2026Source
  • DocumentPlan 9 - 13.pdf · uploaded 15 Sep 2026Source

Technical (Architect)

  • DocumentFLORA 06 RERA FORM 01.pdf · uploaded 25 Jan 2025Source
  • DocumentGREEN 06 RERA FORM 1.pdf · uploaded 25 Jan 2025Source
  • DocumentDelta Greens Form 1.pdf · uploaded 19 Apr 2025Source
  • DocumentForm 1_Greens.pdf · uploaded 12 Aug 2026Source

Technical (Engineer)

  • DocumentForm 2 - Greens.pdf · uploaded 6 Feb 2025Source
  • DocumentDELTA_GREENS_Form2_Q1_2026-27_06-08-2026_11-23.pdf · uploaded 12 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dapoli, Panvel taluka

Survey, CTS, gat or plot numbers

08

Boundaries

North
Plot No 07
South
20 Mtrs Wide Road
East
Plot No 18 And 19
West
24 Mtrs Wide Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSatish V Ahuja And Associates—
Chartered accountantCA Naina Jain—
Chartered accountantChetan Joshi & Co—
Chartered accountantSamarpit Ganesh Pingale—
EngineerAkshay Uttam Barakade—
EngineerAnish Kumar Yadav—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology