Bhagwati Elysia III

Certificate Signed

Dapoli, Raigarh 410206 |Promoter: Bhagwati Signature LLP

16 May 2024Registered with MahaRERA
31 Dec 2029Promised completion
30 Apr 2030Revised completionPushed back 4 months
1Building
153Units registered64 booked (42%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, 3BHK, Office space, Shop153 units in all
Address
Plot No 36 Sector 05, Plot No 36 Sector 05, PushpaknagarPIN 410206
Designated bank account
109
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
16 May 2024
Promised
31 Dec 2029
Revised
30 Apr 2030

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200005615816 May 202431 Dec 202930 Apr 2030Bhagwati Signature LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Bhagwati Elysia III10153

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

64 of 153 units booked (42%), as the promoter reported to MahaRERA

1BHK · 55 units2BHK · 68 units3BHK · 10 unitsOffice space · 10 unitsShop · 10 units
TypeCarpet areaUnitsBooked
1BHK34.47 sq m · 371 sq ft2710
1BHK35.37 sq m · 381 sq ft95
1BHK35.84 sq m · 386 sq ft90
1BHK39.38 sq m · 424 sq ft103
2BHK52.27 sq m · 563 sq ft103
2BHK52.57 sq m · 566 sq ft87
2BHK53.14 sq m · 572 sq ft91
2BHK53.15 sq m · 572 sq ft84
Show all 34 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK53.25 sq m · 573 sq ft104
2BHK53.57 sq m · 577 sq ft10
2BHK54.13 sq m · 583 sq ft10
2BHK54.15 sq m · 583 sq ft10
2BHK54.97 sq m · 592 sq ft100
2BHK55.72 sq m · 600 sq ft109
3BHK83.22 sq m · 896 sq ft1010
Office space44.51 sq m · 479 sq ft10
Office space45.92 sq m · 494 sq ft10
Office space46.07 sq m · 496 sq ft10
Office space47.02 sq m · 506 sq ft10
Office space47.37 sq m · 510 sq ft10
Office space47.64 sq m · 513 sq ft20
Office space48.04 sq m · 517 sq ft10
Office space49.53 sq m · 533 sq ft10
Office space50.47 sq m · 543 sq ft10
Shop46.36 sq m · 499 sq ft11
Shop47.95 sq m · 516 sq ft11
Shop48.7 sq m · 524 sq ft10
Shop50.28 sq m · 541 sq ft11
Shop50.81 sq m · 547 sq ft11
Shop51.5 sq m · 554 sq ft10
Shop51.97 sq m · 559 sq ft11
Shop52.2 sq m · 562 sq ft11
Shop52.64 sq m · 567 sq ft11
Shop54.3 sq m · 584 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 102 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardBHAGWATI SIGNATURE LLP PAN CARD.pdf · uploaded 24 Apr 2024Source
  • Other – FinanceMortgage Deed Plot 36.pdf · uploaded 10 May 2025Source

Legal

  • Declaration Form BFORM B P 36.pdf · uploaded 24 Apr 2024Source
  • Other – LegalP-36.pdf · uploaded 26 Apr 2024Source
  • Legal Title reportsearch p-36.pdf · uploaded 26 Apr 2024Source
  • Legal Title reportJURIS SALVATION ADVOCATES.pdf · uploaded 7 May 2024Source
  • Declaration Form BAFFIDAVIT CUM DECLARATION ELYSIA lll.pdf · uploaded 10 May 2025Source
Show all 103 documentsShow fewer documents

Migrated

  • 1 PAN CardBHAGWATI SIGNATURE LLP PAN CARD.pdf · uploaded 24 Apr 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentCC DRAWING PLOT 36.pdf · uploaded 24 Apr 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC LETTER.pdf · uploaded 24 Apr 2024Source
  • 1 Declaration in FORM BFORM B P 36.pdf · uploaded 24 Apr 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 P36 (1).pdf · uploaded 24 Apr 2024Source
  • 1 CERSAI detailsCERSAI LETTER.pdf · uploaded 24 Apr 2024Source
  • 1 Proforma of Allotment letterALLOT FOR RERA PLOT 36.pdf · uploaded 24 Apr 2024Source
  • 1 Deviation Report with respect to Allotment letterPLOT 36 allot DEVIATION .pdf · uploaded 24 Apr 2024Source
  • 1 Other – TechnicalPLOT 36 ORDER 50.pdf · uploaded 25 Apr 2024Source
  • 1 Copy of the legal title reportsearch p-36.pdf · uploaded 26 Apr 2024Source
  • 1 a Details of encumbrances concerned to FinanceFINANCE DECLARATION .pdf · uploaded 26 Apr 2024Source
  • 2 a Details of encumbrances concerned to FinanceLEGAL DECLARATION .pdf · uploaded 26 Apr 2024Source
  • 1 b Details of encumbrances concerned to LegalFINANCE DECLARATION .pdf · uploaded 26 Apr 2024Source
  • 2 b Details of encumbrances concerned to LegalLEGAL DECLARATION .pdf · uploaded 26 Apr 2024Source
  • 1 Copy of Layout Approval (in case of layout)P-36.pdf · uploaded 26 Apr 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsANNEXURE A.pdf · uploaded 26 Apr 2024Source
  • 1 Other – LegalP-36.pdf · uploaded 26 Apr 2024Source
  • 2 Other – TechnicalPLOT 36 CC UPLOAD.pdf · uploaded 26 Apr 2024Source
  • 1 Declaration about Commencement CertificateCC DECLARATION .pdf · uploaded 27 Apr 2024Source
  • 3 Other – TechnicalPLOT 36 PUSHPAK.pdf · uploaded 27 Apr 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameELYSIA 3.pdf · uploaded 4 May 2024Source
  • 1 Proforma of Agreement for sale05052024 AFS P 36.pdf · uploaded 6 May 2024Source
  • 1 Deviation Report with respect to model copy of AgreementPLOT 36 AFS DEVIATION 0605.pdf · uploaded 6 May 2024Source
  • 2 Copy of the legal title reportJURIS SALVATION ADVOCATES.pdf · uploaded 7 May 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 3-5-24.pdf · uploaded 9 May 2024Source
  • 2 Proforma of Agreement for saleafs p-36 (2).pdf · uploaded 25 May 2024Source
  • 2 Deviation Report with respect to model copy of Agreementafs deviation p-36 (1).pdf · uploaded 25 May 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01_ (1).pdf · uploaded 17 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 (Elysia-III).pdf · uploaded 17 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 17 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryElysia 3 sold unsold.pdf · uploaded 17 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 22 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3_compressed.pdf · uploaded 22 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2_compressed.pdf · uploaded 22 Mar 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD (2).pdf · uploaded 22 Mar 2025Source
  • 1 a Details of encumbrances concerned to FinanceTO WHOMSOEVER IT MAY CONCERN ELYSIA lll.pdf · uploaded 10 May 2025Source
  • 1 Declaration in FORM BAFFIDAVIT CUM DECLARATION ELYSIA lll.pdf · uploaded 10 May 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 01.pdf · uploaded 10 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 10 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 10 May 2025Source
  • 1 Disclosure of sold/ booked inventoryELYSIA 3.pdf · uploaded 10 May 2025Source
  • 1 CERSAI detailsMAHARERA AUTHORITY ELYSIA lll.pdf · uploaded 10 May 2025Source
  • 1 b Details of encumbrances concerned to LegalTO WHOMSOEVER IT MAY CONCERN ELYSIA lll.pdf · uploaded 10 May 2025Source
  • 1 Other – FinanceMortgage Deed Plot 36.pdf · uploaded 10 May 2025Source
  • Withdrawal Update Form 1FORM 01.pdf · uploaded 2 Oct 2025Source
  • Withdrawal Update Form 1FORM 01.pdf · uploaded 2 Oct 2025Source
  • Withdrawal Update Form 1FORM 01.pdf · uploaded 2 Oct 2025Source
  • Withdrawal Update Form 2FORM 02.pdf · uploaded 2 Oct 2025Source
  • Withdrawal Update Form 2FORM 02.pdf · uploaded 2 Oct 2025Source
  • Withdrawal Update Form 2FORM 02.pdf · uploaded 2 Oct 2025Source
  • Withdrawal Update Form 3Form -3.pdf · uploaded 2 Oct 2025Source
  • Withdrawal Update Form 3Form -3.pdf · uploaded 2 Oct 2025Source
  • Withdrawal Update Form 3Form -3.pdf · uploaded 2 Oct 2025Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 3Form3 Q2 (1)_.pdf · uploaded 6 Mar 2026Source
  • Withdrawal Update Form 110-01-2026 FORM 01.pdf · uploaded 23 Mar 2026Source
  • Withdrawal Update Form 110-01-2026 FORM 01.pdf · uploaded 23 Mar 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 23 Mar 2026Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 23 Mar 2026Source
  • Withdrawal Update Form 3Elysia-III Form3s.pdf · uploaded 23 Mar 2026Source
  • Withdrawal Update Form 3Elysia-III Form3s.pdf · uploaded 23 Mar 2026Source
  • Withdrawal Update Form 1Form 01.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1Form 01.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1Form 01.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1Form 01.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1Form 01.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1Form 01.pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2Form -2 Elysia III 01 (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2Form -2 Elysia III 01 (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2Form -2 Elysia III 01 (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2Form -2 Elysia III 01 (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2Form -2 Elysia III 01 (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 2Form -2 Elysia III 01 (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Q4 Elysia-III (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Q4 Elysia-III (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Q4 Elysia-III (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Q4 Elysia-III (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Q4 Elysia-III (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 3Form 3 Q4 Elysia-III (1).pdf · uploaded 8 Jun 2026Source
  • Withdrawal Update Form 1FORM 01.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 2FORM 2 ELYSIA III.pdf · uploaded 12 Aug 2026Source
  • Withdrawal Update Form 3Form 3 Q1 SIGN.pdf · uploaded 12 Aug 2026Source

Technical

  • DocumentCC DRAWING PLOT 36.pdf · uploaded 24 Apr 2024Source
  • Other – TechnicalPLOT 36 ORDER 50.pdf · uploaded 25 Apr 2024Source
  • DocumentP-36.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalPLOT 36 CC UPLOAD.pdf · uploaded 26 Apr 2024Source
  • Other – TechnicalPLOT 36 PUSHPAK.pdf · uploaded 27 Apr 2024Source

Technical (Architect)

  • DocumentFORM 01_ (1).pdf · uploaded 17 Oct 2024Source
  • DocumentFORM 1.pdf · uploaded 22 Mar 2025Source
  • DocumentFORM 01.pdf · uploaded 10 May 2025Source
  • DocumentFORM 01.pdf · uploaded 12 Aug 2026Source

Technical (Engineer)

  • DocumentFORM 2_compressed.pdf · uploaded 22 Mar 2025Source
  • DocumentFORM 2.pdf · uploaded 10 May 2025Source
  • DocumentFORM 2 ELYSIA III.pdf · uploaded 12 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dapoli, Panvel taluka

Survey, CTS, gat or plot numbers

PLOT NO 36 SECTOR 05

Boundaries

North
Plot No 37
South
Plot No 35
East
20 Mtrs Wide Road
West
Plot No 05

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSoyuz Talib Architects—
Chartered accountantH M Shah And Associates—
EngineerAg Gokhale & Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology