Nanesh Heights
Completion due Mar 2030Chendhre, Raigarh 402201 |Promoter: Meetshalin Infra Builds
Project summary
As registered with MahaRERA
- Buildings
- 2
Location
Coordinates as published by MahaRERA
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Mar 2030
- Registered
- 15 Sep 2025
- Promised
- 31 Mar 2030
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| PM1270002500775 | 15 Sep 2025 | 31 Mar 2030 | — | Meetshalin Infra Builds | Project page |
2 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Floors with CC | Units |
|---|---|---|---|
| Nanesh Heights A Wing | 7 | 7 | 29 |
| Nanesh Heights B Wing | 6 | 7 | 26 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Documents
1 document held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Chendhre
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.