Prajapati Magnum
Completion date passedBokadvira, Raigarh 400702 |Promoter: Prajapati Developers
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
P52000001121The latest completion date on record passed 3 years and 4 months ago.
- Registered
- 26 Jul 2017
- Promised
- 30 Jun 2022
- Revised
- 28 Jun 2023
Completion pushed back 2 years and 6 months
P52000001425The latest completion date on record passed 10 months ago.
- Registered
- 28 Jul 2017
- Promised
- 30 Jun 2023
- Revised
- 28 Dec 2025
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000001121 | 26 Jul 2017 | 30 Jun 2022 | 28 Jun 2023 | Prajapati Developers | Project page |
| P52000001425 | 28 Jul 2017 | 30 Jun 2023 | 28 Dec 2025 | Prajapati Developers | Project page |
Documents
4 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bokadvira
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.