Om Shanti Heights

Certificate Signed

Bhuwaneshwar (Ct), Raigarh 402116 |Promoter: Mahboob Abbasali Khan

Residential / Group HousingRERAP52000081026
20 Oct 2025Registered with MahaRERA
31 Dec 2027Promised completion
30 Apr 2028Revised completionPushed back 4 months
1Building
49Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 1BHK LAND OWNER, 2BHK, 2BHK LAND OWNER, Office LAND OWNER, Office space, Shop49 units in all
Address
SURVEY NO. 38/6, Plot No 1, ROHA, ROHAPIN 402116
Designated bank account
196
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.43400, 73.12659
Om Shanti Heights is at latitude 18.43400, longitude 73.12659.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
20 Oct 2025
Promised
31 Dec 2027
Revised
30 Apr 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200008102620 Oct 202531 Dec 202730 Apr 2028Mahboob Abbasali KhanProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Om Shanti Heights649

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 49 units booked (0%), as the promoter reported to MahaRERA

1BHK · 32 units1BHK LAND OWNER · 4 units2BHK · 4 units2BHK LAND OWNER · 2 unitsOffice LAND OWNER · 2 unitsOffice space · 2 unitsShop · 3 units
TypeCarpet areaUnitsBooked
1BHK36.71 sq m · 395 sq ft20
1BHK37.64 sq m · 405 sq ft50
1BHK38.1 sq m · 410 sq ft30
1BHK38.57 sq m · 415 sq ft30
1BHK38.66 sq m · 416 sq ft20
1BHK39.03 sq m · 420 sq ft10
1BHK39.31 sq m · 423 sq ft10
1BHK39.41 sq m · 424 sq ft30
Show all 26 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1BHK39.87 sq m · 429 sq ft40
1BHK40.52 sq m · 436 sq ft30
1BHK40.71 sq m · 438 sq ft30
1BHK41.54 sq m · 447 sq ft10
1BHK43.96 sq m · 473 sq ft10
1BHK LAND OWNER37.64 sq m · 405 sq ft10
1BHK LAND OWNER39.03 sq m · 420 sq ft10
1BHK LAND OWNER39.31 sq m · 423 sq ft10
1BHK LAND OWNER49.35 sq m · 531 sq ft10
2BHK53.53 sq m · 576 sq ft20
2BHK54.28 sq m · 584 sq ft20
2BHK LAND OWNER53.53 sq m · 576 sq ft10
2BHK LAND OWNER57.16 sq m · 615 sq ft10
Office LAND OWNER11.52 sq m · 124 sq ft10
Office LAND OWNER13.45 sq m · 145 sq ft10
Office space11.52 sq m · 124 sq ft20
Shop11.52 sq m · 124 sq ft10
Shop16.91 sq m · 182 sq ft20

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 105 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan Card.pdf · uploaded 27 Mar 2025Source
  • PAN CardPan Card.pdf · uploaded 27 Mar 2025Source
  • Other – FinanceDeclaration.pdf · uploaded 9 Oct 2025Source
  • Other – FinanceDeclaration.pdf · uploaded 9 Oct 2025Source

Legal

  • Legal Title reportLegal Title Report.pdf · uploaded 20 Mar 2025Source
  • Legal Title reportLegal Title Report.pdf · uploaded 20 Mar 2025Source
  • Legal Title reportLegal Title Report.pdf · uploaded 2 Aug 2025Source
Show all 106 documentsShow fewer documents

Legal

  • Declaration Form BForm-B Promotor.pdf · uploaded 2 Aug 2025Source
  • Declaration Form BForm-B Landowner.pdf · uploaded 2 Aug 2025Source
  • Legal Title reportLegal Title Report.pdf · uploaded 2 Aug 2025Source
  • Declaration Form BForm-B Promotor.pdf · uploaded 2 Aug 2025Source
  • Declaration Form BForm-B Landowner.pdf · uploaded 2 Aug 2025Source

Migrated

  • 1 Copy of Layout Approval (in case of layout)Approved PlanUP.pdf · uploaded 3 May 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate (C C).pdf · uploaded 3 May 2024Source
  • 1 Copy of Layout Approval (in case of layout)Approved PlanUP.pdf · uploaded 3 May 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate (C C).pdf · uploaded 3 May 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentApproved PlanUP.pdf · uploaded 23 Dec 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentApproved PlanUP.pdf · uploaded 23 Dec 2024Source
  • 1 Other – TechnicalEmail from Tehsildar.pdf · uploaded 18 Jan 2025Source
  • 1 Other – TechnicalEmail from Tehsildar.pdf · uploaded 18 Jan 2025Source
  • 1 Deviation Report with respect to Allotment letterDeviation to Allotment.pdf · uploaded 19 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation to Agreement.pdf · uploaded 19 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterDeviation to Allotment.pdf · uploaded 19 Mar 2025Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation to Agreement.pdf · uploaded 19 Mar 2025Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 20 Mar 2025Source
  • 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 20 Mar 2025Source
  • 1 PAN CardPan Card.pdf · uploaded 27 Mar 2025Source
  • 1 PAN CardPan Card.pdf · uploaded 27 Mar 2025Source
  • 1 a Details of encumbrances concerned to Financelegal (1).pdf · uploaded 7 Apr 2025Source
  • 1 b Details of encumbrances concerned to Legallegal (1).pdf · uploaded 7 Apr 2025Source
  • 1 a Details of encumbrances concerned to Financelegal (1).pdf · uploaded 7 Apr 2025Source
  • 1 b Details of encumbrances concerned to Legallegal (1).pdf · uploaded 7 Apr 2025Source
  • 2 Copy of the legal title reportLegal Title Report.pdf · uploaded 2 Aug 2025Source
  • 2 a Details of encumbrances concerned to FinanceFinacial encum.pdf · uploaded 2 Aug 2025Source
  • 1 Declaration in FORM BForm-B Promotor.pdf · uploaded 2 Aug 2025Source
  • 2 Declaration in FORM BForm-B Landowner.pdf · uploaded 2 Aug 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 2 Aug 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 v2 om Shanti.pdf · uploaded 2 Aug 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 2 Aug 2025Source
  • 2 Commencement Certificates / NA Order for plotted developmentAppendix F.pdf · uploaded 2 Aug 2025Source
  • 1 Declaration about Commencement CertificateForm D.pdf · uploaded 2 Aug 2025Source
  • 2 b Details of encumbrances concerned to LegalFinacial encum.pdf · uploaded 2 Aug 2025Source
  • 2 Other – Technical1 Copy of Layout Approval (in case of layout).pdf · uploaded 2 Aug 2025Source
  • 3 Other – TechnicalDeclaration_Cum_Undertaking_Annexure_A.pdf · uploaded 2 Aug 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnex A Disclosure of Interest.pdf · uploaded 2 Aug 2025Source
  • 2 Copy of the legal title reportLegal Title Report.pdf · uploaded 2 Aug 2025Source
  • 2 a Details of encumbrances concerned to FinanceFinacial encum.pdf · uploaded 2 Aug 2025Source
  • 1 Declaration in FORM BForm-B Promotor.pdf · uploaded 2 Aug 2025Source
  • 2 Declaration in FORM BForm-B Landowner.pdf · uploaded 2 Aug 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1.pdf · uploaded 2 Aug 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 v2 om Shanti.pdf · uploaded 2 Aug 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2.pdf · uploaded 2 Aug 2025Source
  • 2 Commencement Certificates / NA Order for plotted developmentAppendix F.pdf · uploaded 2 Aug 2025Source
  • 1 Declaration about Commencement CertificateForm D.pdf · uploaded 2 Aug 2025Source
  • 2 b Details of encumbrances concerned to LegalFinacial encum.pdf · uploaded 2 Aug 2025Source
  • 2 Other – Technical1 Copy of Layout Approval (in case of layout).pdf · uploaded 2 Aug 2025Source
  • 3 Other – TechnicalDeclaration_Cum_Undertaking_Annexure_A.pdf · uploaded 2 Aug 2025Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnex A Disclosure of Interest.pdf · uploaded 2 Aug 2025Source
  • 1 Proforma of Agreement for saleModel_Agreement_for_Sale[1].pdf · uploaded 3 Sep 2025Source
  • 1 Proforma of Agreement for saleModel_Agreement_for_Sale[1].pdf · uploaded 3 Sep 2025Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 29 Sep 2025Source
  • 1 Proforma of Allotment letterAllotment letter.pdf · uploaded 29 Sep 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format-A_compressed.pdf · uploaded 9 Oct 2025Source
  • 1 Other – FinanceDeclaration.pdf · uploaded 9 Oct 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B.pdf · uploaded 9 Oct 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure.pdf · uploaded 9 Oct 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)Format-A_compressed.pdf · uploaded 9 Oct 2025Source
  • 1 Other – FinanceDeclaration.pdf · uploaded 9 Oct 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B.pdf · uploaded 9 Oct 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectDisclosure.pdf · uploaded 9 Oct 2025Source
  • 1 CERSAI detailsCERSAI_Search_Report_200382247589_For_Asset_Based_Search_27_09_2025_17_48_33_241 (1).pdf · uploaded 10 Oct 2025Source
  • 4 Other – Technical1 Copy of Layout Approval (in case of layout)_compressed.pdf · uploaded 10 Oct 2025Source
  • 1 CERSAI detailsCERSAI_Search_Report_200382247589_For_Asset_Based_Search_27_09_2025_17_48_33_241 (1).pdf · uploaded 10 Oct 2025Source
  • 4 Other – Technical1 Copy of Layout Approval (in case of layout)_compressed.pdf · uploaded 10 Oct 2025Source
  • Withdrawal Update Form 1Form-1.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 2Form-2.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 28 Mar 2026Source
  • Withdrawal Update Form 1Form 1 31-03-2026.pdf · uploaded 9 Apr 2026Source
  • Withdrawal Update Form 2Form 2 31-03-2026.pdf · uploaded 9 Apr 2026Source
  • Withdrawal Update Form 3Withdrawal Application Form3.pdf · uploaded 9 Apr 2026Source
  • Form 5 (FY 2025-2026)Form 5.pdf · uploaded 9 Apr 2026Source
  • Withdrawal Update Form 1Form 1 31-03-2026.pdf · uploaded 10 Apr 2026Source
  • Withdrawal Update Form 2Form 2 31-03-2026.pdf · uploaded 10 Apr 2026Source
  • Withdrawal Update Form 3Withdrawal Application Form3.pdf · uploaded 10 Apr 2026Source
  • Withdrawal Update Form 1Form 1.pdf · uploaded 5 Aug 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 5 Aug 2026Source
  • Withdrawal Update Form 3Withdrawal Application Form3 sIGNED.pdf · uploaded 5 Aug 2026Source
  • Form 2A (FY 2025-2026)Form 2A.pdf · uploaded 21 Aug 2026Source
  • Form 2A (FY 2026-2027)Form 2A.pdf · uploaded 21 Aug 2026Source

Technical

  • DocumentApproved PlanUP.pdf · uploaded 3 May 2024Source
  • DocumentApproved PlanUP.pdf · uploaded 3 May 2024Source
  • DocumentApproved PlanUP.pdf · uploaded 23 Dec 2024Source
  • DocumentApproved PlanUP.pdf · uploaded 23 Dec 2024Source
  • Other – TechnicalEmail from Tehsildar.pdf · uploaded 18 Jan 2025Source
  • Other – TechnicalEmail from Tehsildar.pdf · uploaded 18 Jan 2025Source
  • Other – Technical1 Copy of Layout Approval (in case of layout).pdf · uploaded 2 Aug 2025Source
  • Other – TechnicalDeclaration_Cum_Undertaking_Annexure_A.pdf · uploaded 2 Aug 2025Source
  • Other – Technical1 Copy of Layout Approval (in case of layout).pdf · uploaded 2 Aug 2025Source
  • Other – TechnicalDeclaration_Cum_Undertaking_Annexure_A.pdf · uploaded 2 Aug 2025Source
  • Other – Technical1 Copy of Layout Approval (in case of layout)_compressed.pdf · uploaded 10 Oct 2025Source
  • Other – Technical1 Copy of Layout Approval (in case of layout)_compressed.pdf · uploaded 10 Oct 2025Source

Technical (Architect)

  • DocumentForm-1.pdf · uploaded 2 Aug 2025Source
  • DocumentForm 1.pdf · uploaded 5 Aug 2026Source

Technical (Engineer)

  • DocumentForm-2.pdf · uploaded 2 Aug 2025Source
  • DocumentForm 2.pdf · uploaded 5 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Bhuwaneshwar (CT), Roha taluka

Survey, CTS, gat or plot numbers

Plot No 1SURVEY NO. 38/6

Boundaries

North
Plot No 3
South
Plot No 2
East
9 M Internal Road
West
Village Bhuvaneshwar

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectVastu Consultant& Engineers—
Chartered accountantPravin Bhrasadiya—
Chartered accountantRahul Bera—
EngineerMr C B Joshi—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology