Kuberakshe
Certificate SignedAlibag, Maharashtra 402201 |Promoter: Akshay Builders
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 1RK, 2BHK, 3BHK, Basement shop, First floor shop, Ground floor shop, Office, —128 units in all
- Address
- 904/1, 902, 900/2, 900a/3, 900a/2, 899, K900a/2, K900/B, K900/C, 900a/1, 900a/3, 900a/4, 900/1, 901, K898, 898/1, , Maharshi Karve Road, Maruti NakaPIN 402201
- Designated bank account
- 28
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2023
The latest completion date on record passed 2 years and 10 months ago.
- Registered
- 22 Feb 2019
- Promised
- 30 Dec 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000019698 | 22 Feb 2019 | 30 Dec 2023 | 30 Dec 2023 | Akshay Builders | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Kuberakshe | 8 | 128 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
64 of 128 units booked (50%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 25.73 sq m · 277 sq ft | 1 | 1 |
| 1BHK | 26.38 sq m · 284 sq ft | 3 | 3 |
| 1BHK | 26.57 sq m · 286 sq ft | 4 | 3 |
| 1BHK | 27.22 sq m · 293 sq ft | 3 | 3 |
| 1BHK | 31.68 sq m · 341 sq ft | 3 | 3 |
| 1BHK | 31.87 sq m · 343 sq ft | 5 | 4 |
| 1BHK | 32.42 sq m · 349 sq ft | 3 | 2 |
| 1BHK | 32.7 sq m · 352 sq ft | 3 | 3 |
Show all 67 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 34.37 sq m · 370 sq ft | 1 | 1 |
| 1RK | 22.84 sq m · 246 sq ft | 1 | 0 |
| 2BHK | 36.98 sq m · 398 sq ft | 3 | 2 |
| 2BHK | 38 sq m · 409 sq ft | 6 | 4 |
| 2BHK | 41.22 sq m · 444 sq ft | 11 | 6 |
| 2BHK | 41.34 sq m · 445 sq ft | 6 | 3 |
| 2BHK | 46.45 sq m · 500 sq ft | 3 | 1 |
| 3BHK | 51.84 sq m · 558 sq ft | 3 | 1 |
| Basement shop | 6.04 sq m · 65 sq ft | 1 | 0 |
| Basement shop | 6.69 sq m · 72 sq ft | 1 | 0 |
| Basement shop | 6.87 sq m · 74 sq ft | 4 | 0 |
| Basement shop | 7.15 sq m · 77 sq ft | 2 | 0 |
| Basement shop | 7.99 sq m · 86 sq ft | 1 | 0 |
| Basement shop | 8.92 sq m · 96 sq ft | 1 | 0 |
| Basement shop | 12.82 sq m · 138 sq ft | 1 | 0 |
| Basement shop | 13.38 sq m · 144 sq ft | 1 | 0 |
| Basement shop | 15.42 sq m · 166 sq ft | 2 | 0 |
| First floor shop | 6.87 sq m · 74 sq ft | 2 | 0 |
| First floor shop | 7.9 sq m · 85 sq ft | 2 | 1 |
| First floor shop | 10.5 sq m · 113 sq ft | 2 | 0 |
| First floor shop | 11.33 sq m · 122 sq ft | 1 | 0 |
| First floor shop | 14.96 sq m · 161 sq ft | 1 | 0 |
| First floor shop | 18.02 sq m · 194 sq ft | 1 | 0 |
| First floor shop | 18.95 sq m · 204 sq ft | 1 | 1 |
| Ground floor shop | 7.9 sq m · 85 sq ft | 2 | 2 |
| Ground floor shop | 9.94 sq m · 107 sq ft | 1 | 1 |
| Ground floor shop | 10.31 sq m · 111 sq ft | 1 | 1 |
| Ground floor shop | 10.5 sq m · 113 sq ft | 1 | 0 |
| Ground floor shop | 11.24 sq m · 121 sq ft | 1 | 1 |
| Ground floor shop | 11.52 sq m · 124 sq ft | 2 | 1 |
| Ground floor shop | 11.71 sq m · 126 sq ft | 1 | 1 |
| Ground floor shop | 11.8 sq m · 127 sq ft | 1 | 1 |
| Ground floor shop | 11.98 sq m · 129 sq ft | 2 | 1 |
| Ground floor shop | 12.36 sq m · 133 sq ft | 1 | 1 |
| Ground floor shop | 13.01 sq m · 140 sq ft | 2 | 2 |
| Ground floor shop | 14.96 sq m · 161 sq ft | 1 | 1 |
| Ground floor shop | 24.06 sq m · 259 sq ft | 1 | 1 |
| Ground floor shop | 24.34 sq m · 262 sq ft | 1 | 1 |
| Ground floor shop | 24.9 sq m · 268 sq ft | 2 | 1 |
| Ground floor shop | 25.64 sq m · 276 sq ft | 1 | 0 |
| Ground floor shop | 28.52 sq m · 307 sq ft | 1 | 0 |
| Ground floor shop | 28.89 sq m · 311 sq ft | 1 | 1 |
| Ground floor shop | 30.29 sq m · 326 sq ft | 1 | 0 |
| Ground floor shop | 32.05 sq m · 345 sq ft | 1 | 0 |
| Ground floor shop | 32.14 sq m · 346 sq ft | 1 | 1 |
| Ground floor shop | 34.56 sq m · 372 sq ft | 1 | 0 |
| Office | 20.72 sq m · 223 sq ft | 1 | 0 |
| Office | 22.48 sq m · 242 sq ft | 1 | 0 |
| Office | 25.08 sq m · 270 sq ft | 1 | 0 |
| Office | 27.59 sq m · 297 sq ft | 1 | 0 |
| Office | 32.33 sq m · 348 sq ft | 1 | 0 |
| Office | 33.07 sq m · 356 sq ft | 1 | 0 |
| Office | 34.19 sq m · 368 sq ft | 2 | 0 |
| Office | 34.84 sq m · 375 sq ft | 1 | 0 |
| Office | 40.23 sq m · 433 sq ft | 2 | 0 |
| Office | 41.34 sq m · 445 sq ft | 2 | 0 |
| Office | 41.62 sq m · 448 sq ft | 1 | 0 |
| — | 9.94 sq m · 107 sq ft | 2 | 2 |
| — | 9.94 sq m · 107 sq ft | 2 | 2 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 78 filings listed on MahaRERA's project page
Finance
- PAN Cardpan card.pdf · uploaded 7 Feb 2019Source
Legal
Show all 79 documentsShow fewer documents
Migrated
- 2 Copy of Layout Approval (in case of layout)plan1.pdf · uploaded 7 Feb 2019Source
- 3 Copy of Layout Approval (in case of layout)plan2.pdf · uploaded 7 Feb 2019Source
- 4 Copy of Layout Approval (in case of layout)plan3.pdf · uploaded 7 Feb 2019Source
- 1 Building Plan Approval (IOD)plan.pdf · uploaded 7 Feb 2019Source
- 2 Building Plan Approval (IOD)plan1.pdf · uploaded 7 Feb 2019Source
- 3 Building Plan Approval (IOD)plan2.pdf · uploaded 7 Feb 2019Source
- 4 Building Plan Approval (IOD)plan3.pdf · uploaded 7 Feb 2019Source
- 1 Commencement Certificates / NA Order for plotted developmentNagarpalika Order.pdf · uploaded 7 Feb 2019Source
- 1 Declaration in FORM Bform b.pdf · uploaded 7 Feb 2019Source
- 1 Certificates of CA (Form 3)CA CERTIFICATE.pdf · uploaded 7 Feb 2019Source
- 1 Proforma of Allotment letterAkshay Builders - Draft AFS RERA format - Final Version.pdf · uploaded 7 Feb 2019Source
- 1 Form 2AForm 2A.pdf · uploaded 12 Jun 2019Source
- 2 Form 2AForm 2A.pdf · uploaded 12 Jun 2019Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects certificate 1.pdf · uploaded 7 Aug 2019Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers certificate 1.pdf · uploaded 7 Aug 2019Source
- 2 Certificates of CA (Form 3)Form 3.pdf · uploaded 7 Aug 2019Source
- 3 Form 2AEngineers Certificate (Supervisor Certificate).pdf · uploaded 16 Oct 2019Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 2 Nov 2019Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 2 Nov 2019Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 2 Nov 2019Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 2 Nov 2019Source
- 3 Certificates of CA (Form 3)CA Certificate with Annexure.pdf · uploaded 2 Nov 2019Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 27 Jan 2020Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 27 Jan 2020Source
- 4 Form 2AForm-2A.pdf · uploaded 27 Jan 2020Source
- 4 Certificates of CA (Form 3)Form 3.pdf · uploaded 1 Feb 2020Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 6 Nov 2020Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 6 Nov 2020Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 6 Nov 2020Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 6 Nov 2020Source
- 5 Certificates of CA (Form 3)Form 3 Sep.pdf · uploaded 6 Nov 2020Source
- 6 Certificates of CA (Form 3)RERA FORM 3.pdf · uploaded 6 Nov 2020Source
- 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 6 Mar 2021Source
- 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 6 Mar 2021Source
- 7 Certificates of CA (Form 3)Form 3.pdf · uploaded 6 Mar 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form5.pdf · uploaded 2 Jul 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form5.pdf · uploaded 2 Jul 2021Source
- 8 Certificates of CA (Form 3)Form 3.pdf · uploaded 20 Jul 2021Source
- 9 Certificates of CA (Form 3)CA.pdf · uploaded 9 Oct 2021Source
- 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 24 Feb 2022Source
- 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 24 Feb 2022Source
- 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 25 Feb 2022Source
- 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architech Certificate.pdf · uploaded 25 Feb 2022Source
- 10 Certificates of CA (Form 3)Form 3 Final.pdf · uploaded 25 Feb 2022Source
- 11 Certificates of CA (Form 3)Form 3 Final.pdf · uploaded 25 Feb 2022Source
- 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect.pdf · uploaded 1 Jul 2022Source
- 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer Compressed.pdf · uploaded 1 Jul 2022Source
- 5 Form 2AForm 2A engineer.pdf · uploaded 1 Jul 2022Source
- 12 Certificates of CA (Form 3)Form 3 compress.pdf · uploaded 1 Jul 2022Source
- 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate.pdf · uploaded 6 Jan 2023Source
- 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 6 Jan 2023Source
- 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Certificate.pdf · uploaded 6 Jan 2023Source
- 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineers Cretificate.pdf · uploaded 6 Jan 2023Source
- 13 Certificates of CA (Form 3)Form 3 FINAL.pdf · uploaded 6 Jan 2023Source
- 14 Certificates of CA (Form 3)Form 3 FINAL.pdf · uploaded 6 Jan 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5.pdf · uploaded 31 Jan 2023Source
- 15 Certificates of CA (Form 3)FORM 3 NEW FORMAT- Dec 2022_ (1).pdf · uploaded 22 Jun 2023Source
- 16 Certificates of CA (Form 3)FORM 3 NEW FORMAT- Mar 2023_.pdf · uploaded 22 Jun 2023Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentAB (KUBERAKSHYE ) OCCUPANCY CERTIFICATE.pdf · uploaded 10 Jan 2024Source
- 17 Certificates of CA (Form 3)Form 3_Akshay Builders.pdf · uploaded 26 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 22-23.pdf · uploaded 20 Apr 2024Source
Technical
- Documentplan.pdf · uploaded 7 Feb 2019Source
- Documentplan1.pdf · uploaded 7 Feb 2019Source
- Documentplan2.pdf · uploaded 7 Feb 2019Source
- Documentplan3.pdf · uploaded 7 Feb 2019Source
- Documentplan.pdf · uploaded 7 Feb 2019Source
- Documentplan1.pdf · uploaded 7 Feb 2019Source
- Documentplan2.pdf · uploaded 7 Feb 2019Source
- Documentplan3.pdf · uploaded 7 Feb 2019Source
Technical (Architect)
- DocumentArchitects Certificate.pdf · uploaded 6 Jan 2023Source
Technical (Engineer)
- DocumentEngineers Cretificate.pdf · uploaded 6 Jan 2023Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Abhinay Jogi And Associates | — |
| Engineer | Associated Consulting Engineers | — |
Source: MahaRERA project page. Contact details are not shown.