Skip to content

B wing · Trio Alpha

Tathwade · RERA P52100051396

IDBLD_07955512 floorsExtended 4 mo
12Sanctioned habitable floorsregistration certificate
30 Apr 2027Revised completionpromised 31 Dec 2026
29 of 48Units bookedMahaRERA project page

Floors

12 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100051396 · registered 8 Jun 2023
Promised completion
31 Dec 2026
Revised completion
30 Apr 2027
Sanctioned habitable floors
12
ProjectId
41,109
ProjectName
TRIO ALPHA
TotalUnitCount
48
ProjectBuildingId
1,34,800
BuildingNameNumber
B wing
FsiWithSanctionSqmts
14
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
48
ProjectRegistartionNo
P52100051396
ProjectBuildingWingsId
1,38,217
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
B wing
NoOfBuildingWingFloorProposed
14
NoOfBuildingWingFloorHabitable
12
NoOfBuildingWingFloorSanctioned
14

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK78.4 m² (843 sq.ft)2417
3BHK102.2 m² (1,100 sq.ft)2412
Total4829
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology