Roshan Milestone
Completion due Dec 2028Tathwade, Pune 411057 |Promoter: Rahul Bhagwandas Sankla
Project summary
As registered with MahaRERA
- RERA registrations
- 8
- Phases
- 8
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2026
P52100033170- Registered
- 9 Feb 2022
- Promised
- 31 Dec 2026
Completion promised for 31 Dec 2026
P52100033143- Registered
- 9 Feb 2022
- Promised
- 31 Dec 2026
Completion promised for 31 Dec 2026
P52100033798- Registered
- 8 Mar 2022
- Promised
- 31 Dec 2026
Completion promised for 31 Dec 2027
P52100034573- Registered
- 11 Apr 2022
- Promised
- 31 Dec 2027
Show 4 more registrations
Completion promised for 31 Dec 2028
P52100050418- Registered
- 12 Apr 2023
- Promised
- 31 Dec 2028
Completion promised for 31 Dec 2028
P52100050918- Registered
- 15 May 2023
- Promised
- 31 Dec 2028
Completion promised for 31 Dec 2028
P52100051473- Registered
- 23 Jun 2023
- Promised
- 31 Dec 2028
Completion promised for 31 Dec 2028
P52100051615- Registered
- 27 Jun 2023
- Promised
- 31 Dec 2028
8 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100033170 | 9 Feb 2022 | 31 Dec 2026 | — | Rahul Bhagwandas Sankla | Project page |
| P52100033143 | 9 Feb 2022 | 31 Dec 2026 | — | Rahul Bhagwandas Sankla | Project page |
| P52100033798 | 8 Mar 2022 | 31 Dec 2026 | — | Rahul Bhagwandas Sankla | Project page |
| P52100034573 | 11 Apr 2022 | 31 Dec 2027 | — | Rahul Bhagwandas Sankla | Project page |
| P52100050418 | 12 Apr 2023 | 31 Dec 2028 | — | Rahul Bhagwandas Sankla | Project page |
| P52100050918 | 15 May 2023 | 31 Dec 2028 | — | Rahul Bhagwandas Sankla | Project page |
| P52100051473 | 23 Jun 2023 | 31 Dec 2028 | — | Rahul Bhagwandas Sankla | Project page |
| P52100051615 | 27 Jun 2023 | 31 Dec 2028 | — | Rahul Bhagwandas Sankla | Project page |
Documents
8 documents held by Deedo
Registration certificates
- Registration certificateP52100033170 · 9 Feb 2022ViewSource
- Registration certificateP52100033143 · 9 Feb 2022ViewSource
- Registration certificateP52100033798 · 8 Mar 2022ViewSource
- Registration certificateP52100034573 · 11 Apr 2022ViewSource
- Registration certificateP52100050418 · 12 Apr 2023ViewSource
- Registration certificateP52100050918 · 15 May 2023ViewSource
- Registration certificateP52100051473 · 21 May 2024ViewSource
- Registration certificateP52100051615 · 5 Jun 2024ViewSource
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Tathwade
Survey, CTS, gat or plot numbers