J Building · Aikonic
Talegaon Dabhade (R) · RERA P52100028284
IDBLD_0383075 floorsPromised date passed
5Sanctioned habitable floorsregistration certificate
31 Jan 2023Revised completionpromised 31 Jan 2023
0 of 12Units bookedMahaRERA project page
Floors
5 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100028284 · registered 18 Feb 2021
- Promised completion
- 31 Jan 2023
- Revised completion
- 31 Jan 2023
- Sanctioned habitable floors
- 5
- ProjectId
- 29,171
- ProjectName
- AIKONIC
- TotalUnitCount
- 0
- ProjectBuildingId
- 59,205
- BuildingNameNumber
- J BUILDING
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100028284
- ProjectBuildingWingsId
- 59,205
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- J BUILDING
- NoOfBuildingWingFloorProposed
- 5
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 5
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 36.3 m² (391 sq.ft) | 8 | 0 |
| 2BHK | 50.2 m² (540 sq.ft) | 4 | 0 |
| Total | 12 | 0 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology