C Building · Sukool

Talegaon Dabhade (M Cl) · RERA P52100008373

IDBLD_0273415 floorsPromised date passed
5Sanctioned habitable floorsregistration certificate
31 May 2018Revised completionpromised 31 May 2018
19 of 24Units bookedMahaRERA project page

Floors

5 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100008373 · registered 18 Aug 2017
Promised completion
31 May 2018
Revised completion
31 May 2018
Sanctioned habitable floors
5
ProjectId
10,171
ProjectName
SUKOOL
TotalUnitCount
0
ProjectBuildingId
48,573
BuildingNameNumber
C BUILDING
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52100008373
ProjectBuildingWingsId
48,573
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
C BUILDING
NoOfBuildingWingFloorProposed
5
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
5

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK31.5 m² (339 sq.ft)88
1BHK32.2 m² (347 sq.ft)22
1BHK32.3 m² (348 sq.ft)21
1BHK32.6 m² (351 sq.ft)21
1BHK32.7 m² (352 sq.ft)21
1BHK33.1 m² (356 sq.ft)86
Total2419