Arini

Certificate Signed

Sus, Pune 411021 |Promoter: Aditya Jagannath Harne

Residential / Group HousingRERAP52100046907
Compare
19 Sep 2022Registered with MahaRERA
31 Dec 2026Promised completion
30 Apr 2027Revised completionPushed back 4 months
1Building
28Units registered9 booked (32%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK, 3BHK28 units in all
Address
41/2/2, Baner-sus road, SusPIN 411021
Designated bank account
86
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.55604, 73.76366
Arini is at latitude 18.55604, longitude 73.76366.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
19 Sep 2022
Promised
31 Dec 2026
Revised
30 Apr 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004690719 Sep 202231 Dec 202630 Apr 2027Aditya Jagannath HarneProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Arini228

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

9 of 28 units booked (32%), as the promoter reported to MahaRERA

2BHK · 21 units3BHK · 7 units
TypeCarpet areaUnitsBooked
2BHK74.78 sq m · 805 sq ft145
2BHK77.85 sq m · 838 sq ft72
3BHK104.43 sq m · 1,124 sq ft72

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 71 filings listed on MahaRERA's project page

Extension certificate

Finance

  • PAN Cardpancard Aditya Harne.pdf · uploaded 29 Aug 2022Source

Legal

  • Declaration Form BNotary_compressed.pdf · uploaded 29 Aug 2022Source
  • Legal Title reportLegal Title Report - Format A.pdf · uploaded 1 Sep 2022Source
  • Declaration Form BArini from B.pdf · uploaded 4 Nov 2024Source
  • Declaration Form BARINI- Form B - compressed.pdf · uploaded 16 Dec 2024Source

Migrated

  • 1 PAN Cardpancard Aditya Harne.pdf · uploaded 29 Aug 2022Source
  • 1 b Details of encumbrances concerned to Legalencumbrances concerned to Legal.pdf · uploaded 29 Aug 2022Source
Show all 72 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval / NA Order for plotted developmentcommencement certificate Baner 41_compressed.pdf · uploaded 29 Aug 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentcommencement certificate Baner 41_compressed.pdf · uploaded 29 Aug 2022Source
  • 1 Declaration about Commencement CertificateDeclaration on CC.pdf · uploaded 29 Aug 2022Source
  • 1 Declaration in FORM BNotary_compressed.pdf · uploaded 29 Aug 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 29 Aug 2022Source
  • 1 Copy of Layout Approval (in case of layout)Layout plan.pdf · uploaded 30 Aug 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect's Certificate.pdf · uploaded 30 Aug 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer's Certificate.pdf · uploaded 30 Aug 2022Source
  • 1 Copy of the legal title reportLegal Title Report - Format A.pdf · uploaded 1 Sep 2022Source
  • 1 CERSAI detailsCERSAI search.pdf · uploaded 1 Sep 2022Source
  • 1 Proforma of Allotment letterSales agreement and allotment letter.pdf · uploaded 1 Sep 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samebank account declaration.pdf · uploaded 1 Sep 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation allotment letter- Final.pdf · uploaded 1 Sep 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Sales agreement - Finalv1.pdf · uploaded 1 Sep 2022Source
  • 1 a Details of encumbrances concerned to FinanceCertificate on Encumbrances.pdf · uploaded 14 Sep 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5- ARINI.pdf · uploaded 18 Apr 2024Source
  • 1 Declaration in FORM BArini from B.pdf · uploaded 4 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Q2.pdf · uploaded 4 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3-1.pdf · uploaded 4 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form -2.pdf · uploaded 4 Nov 2024Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold-Booked Inventory-1.pdf · uploaded 4 Nov 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations-1.pdf · uploaded 4 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2A-1.pdf · uploaded 4 Nov 2024Source
  • 1 CERSAI detailsCERSAI_Search_Report_200326500315_For_Asset_Based_Search_04_11_2024_23_33_47_754.pdf · uploaded 6 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 FY 2023-24 signed.pdf · uploaded 6 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed CA certificate RERA Q2 FY 24-25.pdf · uploaded 13 Dec 2024Source
  • 2 Declaration in FORM BARINI- Form B - compressed.pdf · uploaded 16 Dec 2024Source
  • 1 Copy of Layout Approval (in case of layout)Building plan 1-1.pdf · uploaded 3 Jan 2025Source
  • 2 Copy of Layout Approval (in case of layout)Building plan approved.pdf · uploaded 3 Jan 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencment Arini 8th Nov 2024.pdf · uploaded 3 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q3 FY 2024-25.pdf · uploaded 16 Apr 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Q4 FY 2024-25.pdf · uploaded 16 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Q3.pdf · uploaded 16 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Q4 FY 2024-25.pdf · uploaded 16 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Q3.pdf · uploaded 16 Apr 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 Q4.pdf · uploaded 16 Apr 2025Source
  • Withdrawal Update Form 1Form 1 Q1 FY 25-26_Final.pdf · uploaded 28 Nov 2025Source
  • Withdrawal Update Form 2Form 2 Q1 FY 25-26_Final 1.pdf · uploaded 28 Nov 2025Source
  • Withdrawal Update Form 3Form 3 Q1 FY 25-26_Final.pdf · uploaded 28 Nov 2025Source
  • Form 5 (FY 2024-2025)Form 5_signed_FY 2024-25.pdf · uploaded 2 Dec 2025Source
  • Form 5 (FY 2022-2023)Arini Form 5 FY 22-23.pdf · uploaded 3 Dec 2025Source
  • Form 5 (FY 2023-2024)Form 5- 2023-24.pdf · uploaded 3 Dec 2025Source
  • Withdrawal Update Form 1Form 1 Q2 Architect Certificate_Final.pdf · uploaded 6 Dec 2025Source
  • Withdrawal Update Form 2Form 2 Q2 FY 25-26.pdf · uploaded 6 Dec 2025Source
  • Withdrawal Update Form 3Form 3 CA Certificate -Arini Realty-Q2-2025-26.pdf · uploaded 6 Dec 2025Source
  • Withdrawal Update Form 1Form I Q3 FY 25-26.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 2Form II Q3 FY 25-26.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 3Form III Q3 FY 25-26.pdf · uploaded 16 Feb 2026Source
  • Withdrawal Update Form 1Form 1 Architect Certificate 31_03_26.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 2Form 2 Engineers certificate - 31_03_26.pdf · uploaded 3 Jun 2026Source
  • Withdrawal Update Form 3Form 3 CA Certificate 20_04_26_Signed.pdf · uploaded 3 Jun 2026Source
  • Form 5 (FY 2025-2026)Arini_Form 5_FY 2025-26_Signed.pdf · uploaded 8 Jun 2026Source

Technical

  • Documentcommencement certificate Baner 41_compressed.pdf · uploaded 29 Aug 2022Source
  • DocumentLayout plan.pdf · uploaded 30 Aug 2022Source
  • DocumentBuilding plan 1-1.pdf · uploaded 3 Jan 2025Source
  • DocumentBuilding plan approved.pdf · uploaded 3 Jan 2025Source

Technical (Architect)

  • DocumentForm-1 Q2.pdf · uploaded 4 Nov 2024Source
  • DocumentForm 1 Q3 FY 2024-25.pdf · uploaded 16 Apr 2025Source
  • DocumentForm 1 Q4 FY 2024-25.pdf · uploaded 16 Apr 2025Source
  • DocumentForm 1 Architect Certificate 31_03_26.pdf · uploaded 3 Jun 2026Source

Technical (Engineer)

  • DocumentForm -2.pdf · uploaded 4 Nov 2024Source
  • DocumentFORM-2 Q3.pdf · uploaded 16 Apr 2025Source
  • DocumentFORM-2 Q4.pdf · uploaded 16 Apr 2025Source
  • DocumentForm 2 Engineers certificate - 31_03_26.pdf · uploaded 3 Jun 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Sus, Mulshi taluka

Survey, CTS, gat or plot numbers

41/2/2

Boundaries

North
S No 41 hissa no 1
South
Internal Road of Survey No 42 part
East
Remaining Land of Survey No 41
West
remaining road from Survey No 41

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSwarali Devale—
Chartered accountantRahul Sukwal—
Chartered accountantVipul Mandasiwala—
EngineerSunil R Patil—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology