Skip to content

Aranya

Certificate Signed

Shilatane, Pune 410405 |Promoter: Karmaa Builders

Residential / Group HousingRERAP52100054715
6 Feb 2024Registered with MahaRERA
31 Dec 2026Promised completion
30 Apr 2027Revised completionPushed back 4 months
30Buildings
60Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
30
Unit types
—60 units in all
Address
Gat No- 31, 33, 34, 35, 36, Shilatane, PunePIN 410405
Designated bank account
76
Developed in phases
Yes

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
6 Feb 2024
Promised
31 Dec 2026
Revised
30 Apr 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000547156 Feb 202431 Dec 202630 Apr 2027Karmaa BuildersProject page

30 buildings

Buildings and wings named in the registration

Show all 30 buildingsShow fewer buildings

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

60 units registered

— · 60 units
BuildingTypeCarpet areaUnits
Bungalow No A1——2
Bungalow No A10——2
Bungalow No A11——2
Bungalow No A12——2
Bungalow No A13——2
Bungalow No A2——2
Bungalow No A3——2
Bungalow No A4——2
Show all 30 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnits
Bungalow No A5——2
Bungalow No A6——2
Bungalow No A7——2
Bungalow No A8——2
Bungalow No A9——2
Bungalow No B1——2
Bungalow No B10——2
Bungalow No B11——2
Bungalow No B12——2
Bungalow No B13——2
Bungalow No B2——2
Bungalow No B3——2
Bungalow No B4——2
Bungalow No B5——2
Bungalow No B6——2
Bungalow No B7——2
Bungalow No B8——2
Bungalow No B9——2
Bungalow No C1——2
Bungalow No C2——2
Bungalow No C3——2
Bungalow No C4——2

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 72 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardKarmaaBuilders_Pan.pdf · uploaded 8 Dec 2023Source

Legal

  • Declaration Form BFORM B.pdf · uploaded 8 Dec 2023Source
  • Legal Title reportShilatne Legal Title Report Gut No 31, 33, 34, 35, 36.pdf · uploaded 13 Dec 2023Source

Migrated

  • 1 PAN CardKarmaaBuilders_Pan.pdf · uploaded 8 Dec 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 8 Dec 2023Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 8 Dec 2023Source
  • 1 CERSAI detailsCERSAI DECLARATION.pdf · uploaded 8 Dec 2023Source
Show all 73 documentsShow fewer documents

Migrated

  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBANK LETTER.pdf · uploaded 8 Dec 2023Source
  • 1 Copy of the legal title reportShilatne Legal Title Report Gut No 31, 33, 34, 35, 36.pdf · uploaded 13 Dec 2023Source
  • 1 a Details of encumbrances concerned to FinanceNO ENCUMBRANCE.pdf · uploaded 13 Dec 2023Source
  • 1 b Details of encumbrances concerned to LegalNO ENCUMBRANCE.pdf · uploaded 13 Dec 2023Source
  • 1 Copy of Layout Approval (in case of layout)Aranya_UnitLayout_Plan.pdf · uploaded 15 Dec 2023Source
  • 2 Copy of Layout Approval (in case of layout)Aranya_Block_Plan.pdf · uploaded 15 Dec 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentAranya_UnitLayout_Plan.pdf · uploaded 15 Dec 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentAranya_Block_Plan.pdf · uploaded 15 Dec 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Form 3.pdf · uploaded 15 Dec 2023Source
  • 1 Declaration about Commencement CertificateAranya_CC Declaration.pdf · uploaded 21 Dec 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A DOI.pdf · uploaded 5 Jan 2024Source
  • 1 Proforma of Allotment letterAranya_ALLOTMENT LETTER FINAL.pdf · uploaded 5 Jan 2024Source
  • 1 Deviation Report with respect to Allotment letterAranya_No Deviation Letter.pdf · uploaded 5 Jan 2024Source
  • 1 Deviation Report with respect to model copy of AgreementAranya_Deviation Letter_AgreementforSale_20240112 (1).pdf · uploaded 12 Jan 2024Source
  • 1 Proforma of Agreement for saleagreement karmaa.pdf · uploaded 30 Jan 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 3 May 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 3 May 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 3 May 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 14 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3.pdf · uploaded 14 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 14 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5 23-24.pdf · uploaded 14 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)form 2A 23-24.pdf · uploaded 24 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Compressed.pdf · uploaded 24 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA Form 3.pdf · uploaded 24 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 certificate.pdf · uploaded 24 Jan 2025Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameFormat A.pdf · uploaded 8 Apr 2025Source
  • 1 Other – TechnicalSelf Declaration.pdf · uploaded 8 Apr 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)Format B.pdf · uploaded 8 Apr 2025Source
  • 2 Other – TechnicalAnnexure A.pdf · uploaded 9 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate Form 1 With Sign 2_11zon.pdf · uploaded 4 May 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3_0001.pdf · uploaded 4 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aranya Form 2 Rera Submission_11zon.pdf · uploaded 4 May 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Aranya Form 2 Rera KY.pdf · uploaded 6 May 2025Source
  • Form 1Form 1 Architect Q2 FY 2025-26.pdf · uploaded 26 Oct 2025Source
  • Form 2Form 2 Engineer Q2 FY 2025-26.pdf · uploaded 26 Oct 2025Source
  • Form 3Form 3 Chartered Q2 FY 2025-26.pdf · uploaded 26 Oct 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold Inventory.pdf · uploaded 26 Oct 2025Source
  • Form 1Form-1 (FY 25-26).pdf · uploaded 27 Jan 2026Source
  • Form 2Form 2 (FY 25-26).pdf · uploaded 27 Jan 2026Source
  • Form 3Form 3 (FY 25-26).pdf · uploaded 27 Jan 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold_Unsold.pdf · uploaded 27 Jan 2026Source
  • Form 1Form 1 Q4 FY 2025-26.pdf · uploaded 28 Apr 2026Source
  • Form 2Form 2 Q4 FY 2025-26.pdf · uploaded 28 Apr 2026Source
  • Form 3Karma Builders Form 3 Q4 25-26.pdf · uploaded 28 Apr 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Q4 - signed.pdf · uploaded 28 Apr 2026Source
  • Form 1Form 1 FY 2026-27 Q1.pdf · uploaded 31 Jul 2026Source
  • Form 2Form 2 .pdf · uploaded 31 Jul 2026Source
  • Form 3Form 3 Q1 26-27_0001.pdf · uploaded 31 Jul 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of sold unsold.pdf · uploaded 31 Jul 2026Source

Technical

  • DocumentAranya_UnitLayout_Plan.pdf · uploaded 15 Dec 2023Source
  • DocumentAranya_UnitLayout_Plan.pdf · uploaded 15 Dec 2023Source
  • DocumentAranya_Block_Plan.pdf · uploaded 15 Dec 2023Source
  • DocumentAranya_Block_Plan.pdf · uploaded 15 Dec 2023Source
  • Other – TechnicalSelf Declaration.pdf · uploaded 8 Apr 2025Source
  • Other – TechnicalAnnexure A.pdf · uploaded 9 Apr 2025Source

Technical (Architect)

  • Documentform 1.pdf · uploaded 3 May 2024Source
  • Documentform 1.pdf · uploaded 14 Oct 2024Source
  • DocumentForm 1 Compressed.pdf · uploaded 24 Jan 2025Source
  • DocumentArchitech Certificate Form 1 With Sign 2_11zon.pdf · uploaded 4 May 2025Source

Technical (Engineer)

  • Documentform 2.pdf · uploaded 3 May 2024Source
  • Documentform 2.pdf · uploaded 14 Oct 2024Source
  • DocumentForm 2 certificate.pdf · uploaded 24 Jan 2025Source
  • DocumentAranya Form 2 Rera Submission_11zon.pdf · uploaded 4 May 2025Source
  • DocumentAranya Form 2 Rera KY.pdf · uploaded 6 May 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Shilatane, Mawal taluka

Survey, CTS, gat or plot numbers

33343536GAT NO 31

Boundaries

North
Gat No 30 And Road
South
Gat No 32 And 33
East
Gat No 34
West
Gat No 120 And Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Registered real estate agentSnehil Sunil Kumar Yadav—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology