Skip to content

Green Villa

Certificate Signed

Sangavade, Pune 412101 |Promoter: Shubhashree Associates

Residential / Group HousingRERAP52100047120
10 Oct 2022Registered with MahaRERA
31 Dec 2026Promised completion
7Buildings
80Units registered20 booked (25%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
7
Unit types
Bungalow, 2BHK, 3BHK80 units in all
Address
306, 306, Near Terra Green Society, SangavadePIN 412101
Designated bank account
85
Developed in phases
Yes

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2026

Registered
10 Oct 2022
Promised
31 Dec 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210004712010 Oct 202231 Dec 202631 Dec 2026Shubhashree AssociatesProject page

7 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A27
A1739
B26
C27
D28
E27
F26

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

20 of 80 units booked (25%), as the promoter reported to MahaRERA

Bungalow · 41 units2BHK · 19 units3BHK · 20 units
BuildingTypeCarpet areaUnitsBooked
ABungalow107.25 sq m · 1,154 sq ft31
ABungalow159.1 sq m · 1,713 sq ft43
A12BHK57.8 sq m · 622 sq ft190
A13BHK76 sq m · 818 sq ft200
BBungalow107.25 sq m · 1,154 sq ft63
CBungalow107.25 sq m · 1,154 sq ft74
DBungalow118.8 sq m · 1,279 sq ft83
EBungalow107.25 sq m · 1,154 sq ft11
Show all 12 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
EBungalow118.8 sq m · 1,279 sq ft62
FBungalow118.8 sq m · 1,279 sq ft11
FBungalow120.99 sq m · 1,302 sq ft42
FBungalow142.81 sq m · 1,537 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 171 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 6 Sep 2022Source

Legal

  • Legal Title reportTitel Report.pdf · uploaded 6 Sep 2022Source
  • Declaration Form BForm B.pdf · uploaded 6 Sep 2022Source
  • Declaration Form BFORM B.pdf · uploaded 8 Nov 2024Source
  • Declaration Form BForm-B.pdf · uploaded 25 Nov 2024Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 6 Sep 2022Source
Show all 173 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportTitel Report.pdf · uploaded 6 Sep 2022Source
  • 1 a Details of encumbrances concerned to FinanceNo financial encrumber.pdf · uploaded 6 Sep 2022Source
  • 1 b Details of encumbrances concerned to Legalno legal encrumbrance.pdf · uploaded 6 Sep 2022Source
  • 1 Copy of Layout Approval (in case of layout)upload.pdf · uploaded 6 Sep 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentNA Order.pdf · uploaded 6 Sep 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Cetrificate.pdf · uploaded 6 Sep 2022Source
  • 1 Declaration about Commencement CertificateDeclaration for Commencement certificate.pdf · uploaded 6 Sep 2022Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 6 Sep 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 6 Sep 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 6 Sep 2022Source
  • 1 CERSAI detailsCERSAI_Search_Report_200246541925_For_Asset_Based_Search_06_09_2022_17_17_13_219.pdf · uploaded 6 Sep 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samebank details.pdf · uploaded 6 Sep 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentWING A_11zon.pdf · uploaded 12 Sep 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentWING A1 1,3,5_11zon.pdf · uploaded 12 Sep 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentWING B and C_11zon.pdf · uploaded 12 Sep 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentWING D and E_11zon.pdf · uploaded 12 Sep 2022Source
  • 6 Building Plan Approval / NA Order for plotted developmentCLUB HOUSE.pdf · uploaded 12 Sep 2022Source
  • 1 Proforma of Allotment letterfinal AL and AFS.pdf · uploaded 14 Sep 2022Source
  • 1 Deviation Report with respect to Allotment letterno deviation in AL.pdf · uploaded 14 Sep 2022Source
  • 1 Deviation Report with respect to model copy of Agreementno deviation in AFS.pdf · uploaded 14 Sep 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 FINAL-1-2-7_merged.pdf · uploaded 30 Sep 2022Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 20 Jan 2023Source
  • 2 Copy of Layout Approval (in case of layout)ENGINEERS CERTIFICATE.pdf · uploaded 26 May 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3-New_compressed (2).pdf · uploaded 12 Jul 2023Source
  • 7 Building Plan Approval / NA Order for plotted developmentscan 001.pdf · uploaded 7 Aug 2023Source
  • 8 Building Plan Approval / NA Order for plotted developmentscan 002.pdf · uploaded 7 Aug 2023Source
  • 9 Building Plan Approval / NA Order for plotted developmentscan 003.pdf · uploaded 7 Aug 2023Source
  • 10 Building Plan Approval / NA Order for plotted developmentscan 004.pdf · uploaded 7 Aug 2023Source
  • 11 Building Plan Approval / NA Order for plotted developmentscan 005.pdf · uploaded 7 Aug 2023Source
  • 12 Building Plan Approval / NA Order for plotted developmentscan 006.pdf · uploaded 7 Aug 2023Source
  • 13 Building Plan Approval / NA Order for plotted developmentscan 007.pdf · uploaded 7 Aug 2023Source
  • 14 Building Plan Approval / NA Order for plotted developmentscan 008.pdf · uploaded 7 Aug 2023Source
  • 15 Building Plan Approval / NA Order for plotted developmentscan 009.pdf · uploaded 7 Aug 2023Source
  • 16 Building Plan Approval / NA Order for plotted developmentscan 010.pdf · uploaded 7 Aug 2023Source
  • 17 Building Plan Approval / NA Order for plotted developmentscan 011.pdf · uploaded 7 Aug 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCOMMENCEMEMT CERTIFICATE.pdf · uploaded 7 Aug 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1.pdf · uploaded 7 Aug 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 8 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A.pdf · uploaded 8 Aug 2023Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 8 Aug 2023Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 8 Aug 2023Source
  • 3 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 8 Aug 2023Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 8 Aug 2023Source
  • 5 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 8 Aug 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 8 Aug 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 8 Aug 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 8 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5.pdf · uploaded 10 Aug 2023Source
  • 3 Copy of Layout Approval (in case of layout)new scan 001_compressed.pdf · uploaded 8 Sep 2023Source
  • 2 Declaration about Commencement CertificateDeclarartion about Comm.pdf · uploaded 11 Sep 2023Source
  • 6 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORIES 31082023.pdf · uploaded 14 Sep 2023Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 8 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -01 30092023_compressed.pdf · uploaded 8 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -01.pdf · uploaded 8 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -03 30092023.pdf · uploaded 9 Nov 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 9 Nov 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM -03.pdf · uploaded 9 Nov 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 9 Nov 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 9 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2 31032023.pdf · uploaded 9 Nov 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate 30 sept 2024 NEW.pdf · uploaded 9 Nov 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-02 30062024.pdf · uploaded 9 Nov 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-02 31032024.pdf · uploaded 9 Nov 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -02 31122023.pdf · uploaded 9 Nov 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-02 30092023.pdf · uploaded 9 Nov 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM -2.pdf · uploaded 9 Nov 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31122022_compressed.pdf · uploaded 9 Nov 2024Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 9 Nov 2024Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 9 Nov 2024Source
  • 3 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 9 Nov 2024Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 9 Nov 2024Source
  • 5 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY.pdf · uploaded 9 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM -2A 23-24.pdf · uploaded 9 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)ANNUAL REPORT FORM -5.pdf · uploaded 9 Nov 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FROM -01 MAR -24_compressed (1).pdf · uploaded 11 Nov 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-01 JUNE -24_compressed.pdf · uploaded 11 Nov 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM -01 SEPT -24.pdf · uploaded 11 Nov 2024Source
  • 2 Declaration in FORM BForm-B.pdf · uploaded 25 Nov 2024Source
  • Form 1FORM 1.pdf · uploaded 21 Jul 2025Source
  • Form 2FORM 2_compressed.pdf · uploaded 21 Jul 2025Source
  • Form 3FORM 3.pdf · uploaded 21 Jul 2025Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY.pdf · uploaded 21 Jul 2025Source
  • Form 1FORM-1.pdf · uploaded 3 Feb 2026Source
  • Form 2FORM -2.pdf · uploaded 3 Feb 2026Source
  • Form 3FORM 3.pdf · uploaded 3 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY 30062023.pdf · uploaded 3 Feb 2026Source
  • Form 1FORM 1.pdf · uploaded 3 Feb 2026Source
  • Form 2FORM -2.pdf · uploaded 3 Feb 2026Source
  • Form 3Form 3.pdf · uploaded 3 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY.pdf · uploaded 3 Feb 2026Source
  • Form 1FORM -01 SEPT -23.pdf · uploaded 4 Feb 2026Source
  • Form 2FROM -02_compressed.pdf · uploaded 4 Feb 2026Source
  • Form 3FORM NO-3.pdf · uploaded 4 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY.pdf · uploaded 4 Feb 2026Source
  • Form 1FORM -01 DEC-23.pdf · uploaded 4 Feb 2026Source
  • Form 2FORM -02 DEC -23.pdf · uploaded 4 Feb 2026Source
  • Form 3FORM 3.pdf · uploaded 4 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY..pdf · uploaded 4 Feb 2026Source
  • Form 1FROM -01 MAR -24 C.pdf · uploaded 4 Feb 2026Source
  • Form 2FORM -02 MAR -24.pdf · uploaded 4 Feb 2026Source
  • Form 3ilovepdf_merged (2).pdf · uploaded 4 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY.pdf · uploaded 4 Feb 2026Source
  • Form 1FORM-01 JUNE -24_compressed.pdf · uploaded 4 Feb 2026Source
  • Form 2FROM -02 JUNE -24_compressed.pdf · uploaded 4 Feb 2026Source
  • Form 3FORM 3.pdf · uploaded 4 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY.pdf · uploaded 4 Feb 2026Source
  • Form 1FORM -01 SEPT -24.pdf · uploaded 4 Feb 2026Source
  • Form 2form2.pdf · uploaded 4 Feb 2026Source
  • Form 3FORM 3.pdf · uploaded 4 Feb 2026Source
  • Disclosure of Sold and Booked InventorySOLD UNSOLD INVENTORY.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 130_06_2025.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 2Form 2.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 2sep25.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 2dec25.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 2dec25.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 3Form 3.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 2 May 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 2 May 2026Source
  • Form 1Form 1 Arch certificate 2.pdf · uploaded 5 May 2026Source
  • Form 2Dec 24 FORM 2.pdf · uploaded 5 May 2026Source
  • Form 3form 3.pdf · uploaded 5 May 2026Source
  • Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLDBOOKED INVENTORY.pdf · uploaded 5 May 2026Source
  • Form 1Form 1 Arch certificate 2.pdf · uploaded 5 May 2026Source
  • Form 2Dec 24 FORM 2.pdf · uploaded 5 May 2026Source
  • Form 3form 3.pdf · uploaded 5 May 2026Source
  • Disclosure of Sold and Booked InventoryDISCLOSURE OF SOLDBOOKED INVENTORY.pdf · uploaded 5 May 2026Source

Technical

  • Documentupload.pdf · uploaded 6 Sep 2022Source
  • DocumentNA Order.pdf · uploaded 6 Sep 2022Source
  • DocumentWING A_11zon.pdf · uploaded 12 Sep 2022Source
  • DocumentWING A1 1,3,5_11zon.pdf · uploaded 12 Sep 2022Source
  • DocumentWING B and C_11zon.pdf · uploaded 12 Sep 2022Source
  • DocumentWING D and E_11zon.pdf · uploaded 12 Sep 2022Source
  • DocumentCLUB HOUSE.pdf · uploaded 12 Sep 2022Source
  • DocumentENGINEERS CERTIFICATE.pdf · uploaded 26 May 2023Source
  • Documentscan 001.pdf · uploaded 7 Aug 2023Source
  • Documentscan 002.pdf · uploaded 7 Aug 2023Source
  • Documentscan 003.pdf · uploaded 7 Aug 2023Source
  • Documentscan 004.pdf · uploaded 7 Aug 2023Source
  • Documentscan 005.pdf · uploaded 7 Aug 2023Source
  • Documentscan 006.pdf · uploaded 7 Aug 2023Source
  • Documentscan 007.pdf · uploaded 7 Aug 2023Source
  • Documentscan 008.pdf · uploaded 7 Aug 2023Source
  • Documentscan 009.pdf · uploaded 7 Aug 2023Source
  • Documentscan 010.pdf · uploaded 7 Aug 2023Source
  • Documentscan 011.pdf · uploaded 7 Aug 2023Source
  • Documentnew scan 001_compressed.pdf · uploaded 8 Sep 2023Source

Technical (Architect)

  • DocumentFORM -01 30092023_compressed.pdf · uploaded 8 Nov 2024Source
  • DocumentFORM -01.pdf · uploaded 8 Nov 2024Source
  • DocumentFROM -01 MAR -24_compressed (1).pdf · uploaded 11 Nov 2024Source
  • DocumentFORM-01 JUNE -24_compressed.pdf · uploaded 11 Nov 2024Source
  • DocumentFORM -01 SEPT -24.pdf · uploaded 11 Nov 2024Source
  • DocumentFORM 1.pdf · uploaded 2 May 2026Source

Technical (Engineer)

  • DocumentFORM 2 31122022_compressed.pdf · uploaded 9 Nov 2024Source
  • DocumentFORM -2 31032023.pdf · uploaded 9 Nov 2024Source
  • DocumentFORM -2.pdf · uploaded 9 Nov 2024Source
  • DocumentFORM-02 30092023.pdf · uploaded 9 Nov 2024Source
  • DocumentFORM -02 31122023.pdf · uploaded 9 Nov 2024Source
  • DocumentFORM-02 31032024.pdf · uploaded 9 Nov 2024Source
  • DocumentFORM-02 30062024.pdf · uploaded 9 Nov 2024Source
  • DocumentEngineer certificate 30 sept 2024 NEW.pdf · uploaded 9 Nov 2024Source
  • Documentdec25.pdf · uploaded 2 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Sangavade, Mawal taluka

Survey, CTS, gat or plot numbers

306

Boundaries

North
Gat No 297
South
Gat No 312
East
Gat No 305
West
Gat No 307

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantGanesh Dnyaneshwar Devkar—
Chartered accountantHarshal Lahoti—
Chartered accountantSnehal Prakash Gaikwad—
EngineerPravin Tarate—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology