Parth Pride
Certificate SignedRui, Pune 413133 |Promoter: Indrayani Developers
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 2BHK, Shop41 units in all
- Address
- Gat No 57 Plot No 19 And 20, SitaramnagarPIN 413133
- Designated bank account
- 119
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Mar 2025
The latest completion date on record passed 1 year and 7 months ago.
- Registered
- 8 Nov 2021
- Promised
- 31 Mar 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100031733 | 8 Nov 2021 | 31 Mar 2025 | 31 Mar 2025 | Indrayani Developers | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Parth Pride | 8 | 41 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 of 41 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 44.15 sq m · 475 sq ft | 6 | 0 |
| 1BHK | 44.38 sq m · 478 sq ft | 6 | 0 |
| 1BHK | 44.8 sq m · 482 sq ft | 3 | 0 |
| 1BHK | 47.63 sq m · 513 sq ft | 3 | 0 |
| 1BHK | 47.65 sq m · 513 sq ft | 3 | 0 |
| 1BHK | 48.12 sq m · 518 sq ft | 3 | 0 |
| 2BHK | 57.94 sq m · 624 sq ft | 3 | 0 |
| 2BHK | 58.25 sq m · 627 sq ft | 3 | 0 |
Show all 12 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 69.18 sq m · 745 sq ft | 3 | 0 |
| 2BHK | 69.5 sq m · 748 sq ft | 3 | 0 |
| Shop | 13.15 sq m · 142 sq ft | 2 | 0 |
| Shop | 15.24 sq m · 164 sq ft | 3 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 85 filings listed on MahaRERA's project page
Finance
- PAN CardIndrayani-Pan_Firm.pdf · uploaded 23 Oct 2021Source
Legal
- Other7_12_-_Plot_No_19_Indrayani.pdf · uploaded 23 Oct 2021Source
- Other7_12-_Plot_No_20_Indrayani.pdf · uploaded 23 Oct 2021Source
- Legal Title reportSearch Report-Indrayani.pdf · uploaded 26 Oct 2021Source
- Declaration Form BForm B-Partner Aniket Choudhar.pdf · uploaded 26 Oct 2021Source
- Declaration Form BForm B-Plot Owner Aniket Choudhar Indrayani.pdf · uploaded 26 Oct 2021Source
- Declaration Form BForm B- Plot Owner Sumit Choudhar Indrayani.pdf · uploaded 26 Oct 2021Source
Show all 86 documentsShow fewer documents
Legal
- Declaration Form BForm B-Partner Harshal Choudhar Indrayani.pdf · uploaded 26 Oct 2021Source
- Declaration Form BForm B-Plot Owner Pravin Sable Indrayani.pdf · uploaded 26 Oct 2021Source
- Declaration Form BForm B-Plot Owner Tejan Choudhar Indrayani.pdf · uploaded 26 Oct 2021Source
- Declaration Form BForm B-Partner Pravin Sable Indrayani.pdf · uploaded 26 Oct 2021Source
- Declaration Form BForm B-Partner Vaishali Sable.pdf · uploaded 26 Oct 2021Source
Migrated
- 1 PAN CardIndrayani-Pan_Firm.pdf · uploaded 23 Oct 2021Source
- 1 Copy of Layout Approval (in case of layout)Lay_out DOWNLOAD.pdf · uploaded 23 Oct 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentbuilding_plan COMPRESS.pdf · uploaded 23 Oct 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentcommencement-_Indrayani.pdf · uploaded 23 Oct 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer_Certificate_Indrayani.pdf · uploaded 23 Oct 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_CERTIFICATE-compressed.pdf · uploaded 23 Oct 2021Source
- 1 Other7_12_-_Plot_No_19_Indrayani.pdf · uploaded 23 Oct 2021Source
- 2 Other7_12-_Plot_No_20_Indrayani.pdf · uploaded 23 Oct 2021Source
- 1 Copy of the legal title reportSearch Report-Indrayani.pdf · uploaded 26 Oct 2021Source
- 1 Details of encumbrancesDeclaration for Encumbrances-Indrayani.pdf · uploaded 26 Oct 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentN A Order-indrayani.pdf · uploaded 26 Oct 2021Source
- 1 Declaration about Commencement CertificateDeclaration for Commencement Certficate Indrayani.pdf · uploaded 26 Oct 2021Source
- 1 Declaration in FORM BForm B-Partner Aniket Choudhar.pdf · uploaded 26 Oct 2021Source
- 2 Declaration in FORM BForm B-Plot Owner Aniket Choudhar Indrayani.pdf · uploaded 26 Oct 2021Source
- 3 Declaration in FORM BForm B- Plot Owner Sumit Choudhar Indrayani.pdf · uploaded 26 Oct 2021Source
- 4 Declaration in FORM BForm B-Partner Harshal Choudhar Indrayani.pdf · uploaded 26 Oct 2021Source
- 5 Declaration in FORM BForm B-Plot Owner Pravin Sable Indrayani.pdf · uploaded 26 Oct 2021Source
- 6 Declaration in FORM BForm B-Plot Owner Tejan Choudhar Indrayani.pdf · uploaded 26 Oct 2021Source
- 7 Declaration in FORM BForm B-Partner Pravin Sable Indrayani.pdf · uploaded 26 Oct 2021Source
- 8 Declaration in FORM BForm B-Partner Vaishali Sable.pdf · uploaded 26 Oct 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate-Indrayani.pdf · uploaded 26 Oct 2021Source
- 1 Proforma of Allotment letterDeclaration for Agreement to sale Indrayani.pdf · uploaded 26 Oct 2021Source
- 2 Building Plan Approval / NA Order for plotted developmentIst Building Plan Indrayani.pdf · uploaded 5 Jul 2022Source
- 3 Commencement Certificates / NA Order for plotted developmentnew commencement -indrayani.pdf · uploaded 5 Jul 2022Source
- 2 Declaration about Commencement Certificatenew commencement -indrayani.pdf · uploaded 5 Jul 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate-Indrayani.pdf · uploaded 5 Jul 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Cerssai-Indrayani Developers.pdf · uploaded 5 Jul 2022Source
- 1 CERSAI detailsCerssai-Indrayani Developers.pdf · uploaded 5 Jul 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate Indarayani.PDF · uploaded 5 Jul 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec31122022.pdf · uploaded 17 Jul 2025Source
- 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec31032025.pdf · uploaded 17 Jul 2025Source
- 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec24.pdf · uploaded 17 Jul 2025Source
- 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec24.pdf · uploaded 17 Jul 2025Source
- 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec23.pdf · uploaded 17 Jul 2025Source
- 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec2122.pdf · uploaded 17 Jul 2025Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec31032025.pdf · uploaded 17 Jul 2025Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec31122024.pdf · uploaded 17 Jul 2025Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec30092024.pdf · uploaded 17 Jul 2025Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form330062024.pdf · uploaded 17 Jul 2025Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec31032024.pdf · uploaded 17 Jul 2025Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form331122023.pdf · uploaded 17 Jul 2025Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec30092023.pdf · uploaded 17 Jul 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec30062023.pdf · uploaded 17 Jul 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Ec31032023.pdf · uploaded 17 Jul 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form330092022.pdf · uploaded 17 Jul 2025Source
- 1 Disclosure of sold/ booked inventoryInventory Parth Pride.pdf · uploaded 17 Jul 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form32122.pdf · uploaded 17 Jul 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)cERSAI.pdf · uploaded 17 Jul 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form32023.pdf · uploaded 17 Jul 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form32024.pdf · uploaded 17 Jul 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)Form331032025.pdf · uploaded 17 Jul 2025Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2024-25)IndrayaniForm5.pdf · uploaded 17 Jul 2025Source
Technical
Technical (Architect)
- DocumentArchitech Certificate-Indrayani.pdf · uploaded 5 Jul 2022Source
Technical (Engineer)
- DocumentCerssai-Indrayani Developers.pdf · uploaded 5 Jul 2022Source
- DocumentForm330092022.pdf · uploaded 17 Jul 2025Source
- DocumentEc31122022.pdf · uploaded 17 Jul 2025Source
- DocumentEc31032023.pdf · uploaded 17 Jul 2025Source
- DocumentEc30062023.pdf · uploaded 17 Jul 2025Source
- DocumentEc30092023.pdf · uploaded 17 Jul 2025Source
- DocumentForm331122023.pdf · uploaded 17 Jul 2025Source
- DocumentEc31032024.pdf · uploaded 17 Jul 2025Source
- DocumentForm330062024.pdf · uploaded 17 Jul 2025Source
- DocumentEc30092024.pdf · uploaded 17 Jul 2025Source
- DocumentEc31122024.pdf · uploaded 17 Jul 2025Source
- DocumentEc31032025.pdf · uploaded 17 Jul 2025Source
- DocumentEc2122.pdf · uploaded 17 Jul 2025Source
- DocumentEc23.pdf · uploaded 17 Jul 2025Source
- DocumentEc24.pdf · uploaded 17 Jul 2025Source
- DocumentEc24.pdf · uploaded 17 Jul 2025Source
- DocumentEc31032025.pdf · uploaded 17 Jul 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Rui, Baramati taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Open Space Plot No A
- South
- 9 Mtr Wide Internal Road
- East
- Plot No 21
- West
- 12 Mtr Wide Internal Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Gopal Suthar | — |
| Chartered accountant | Girish Patwa | — |
| Engineer | Sumit Chaudhar | — |
Source: MahaRERA project page. Contact details are not shown.