Skip to content

Excellaa Florence

Certificate Signed

Pirangut, Pune 412115 |Promoter: The Kallyaanee Fortune Properties

13 Sep 2021Registered with MahaRERAFirst of 2 registrations
31 Dec 2028Promised completionLatest across registrations
30 Apr 2029Revised completion1 of 2 registrations pushed back, by up to 4 months
4Buildings2 phases
908Units registered330 booked (36%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
RERA registrations
2
Phases
2
Buildings
4
Unit types
1BHK, 2BHK908 units in all
Address
Gat No. 148/1, 149, 150, 151, 152 and 254, Pirangut, PirangutPIN 412115
Designated bank account
76
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.51546, 73.69496
Excellaa Florence is at latitude 18.51546, longitude 73.69496.

Also registered as

Excellaa Florence 1Excellaa Florence 2

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2028

P52100030786
Registered
13 Sep 2021
Promised
31 Dec 2028

Completion pushed back 4 months

P52100030760
Registered
13 Sep 2021
Promised
31 Dec 2028
Revised
30 Apr 2029

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210003078613 Sep 202131 Dec 202831 Dec 2028The Kallyaanee Fortune PropertiesProject page
P5210003076013 Sep 202131 Dec 202830 Apr 2029The Kallyaanee Fortune PropertiesProject page

4 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing - A13232
Wing - B13206
Wing - C13212
Wing - D5258

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

330 of 908 units booked (36%), as the promoter reported to MahaRERA

1BHK · 466 units2BHK · 442 units
RERABuildingTypeCarpet areaUnitsBooked
P52100030786Wing - A1BHK28.93 sq m · 311 sq ft232157
P52100030786Wing - B2BHK46.95 sq m · 505 sq ft10284
P52100030786Wing - B2BHK48.39 sq m · 521 sq ft10483
P52100030760Wing - C2BHK46.95 sq m · 505 sq ft1040
P52100030760Wing - C2BHK48.4 sq m · 521 sq ft1020
P52100030760Wing - C2BHK53.98 sq m · 581 sq ft22
P52100030760Wing - C2BHK55.43 sq m · 597 sq ft44
P52100030760Wing - D1BHK28.93 sq m · 311 sq ft2340
P52100030760Wing - D2BHK47.38 sq m · 510 sq ft240

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 203 filings listed on MahaRERA's project page

Registration certificate (2)

  • Registration certificateP52100030786 · 13 Sep 2021ViewSource
  • Registration certificateP52100030760 · 20 Jun 2024ViewSource

Finance

  • PAN CardP52100030786 · Pan Card The KFP.pdf · uploaded 1 Sep 2021Source
  • PAN CardP52100030760 · Pan Card The KFP.pdf · uploaded 1 Sep 2021Source

Legal

  • Legal Title reportP52100030786 · Title Search Report Annexure.pdf · uploaded 1 Sep 2021Source
  • Declaration Form BP52100030786 · Form B.pdf · uploaded 1 Sep 2021Source
  • Legal Title reportP52100030760 · Title Search Report Annexure.pdf · uploaded 1 Sep 2021Source
  • Declaration Form BP52100030760 · Form B.pdf · uploaded 1 Sep 2021Source
Show all 205 documentsShow fewer documents

Migrated

  • 1 PAN CardP52100030786 · Pan Card The KFP.pdf · uploaded 1 Sep 2021Source
  • 1 Copy of the legal title reportP52100030786 · Title Search Report Annexure.pdf · uploaded 1 Sep 2021Source
  • 1 Details of encumbrancesP52100030786 · Encumbrance Certificate.pdf · uploaded 1 Sep 2021Source
  • 1 Copy of Layout Approval (in case of layout)P52100030786 · Layout.pdf · uploaded 1 Sep 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 1 - Parking.pdf · uploaded 1 Sep 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 2 - A Wing.pdf · uploaded 1 Sep 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 3 - A Wing.pdf · uploaded 1 Sep 2021Source
  • 4 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 4 - A Wing.pdf · uploaded 1 Sep 2021Source
  • 5 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 5 - A Wing.pdf · uploaded 1 Sep 2021Source
  • 6 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 6 - B Wing.pdf · uploaded 1 Sep 2021Source
  • 7 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 7 - B Wing.pdf · uploaded 1 Sep 2021Source
  • 8 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 8 - B Wing.pdf · uploaded 1 Sep 2021Source
  • 9 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 9 - B Wing.pdf · uploaded 1 Sep 2021Source
  • 10 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 10 - B Wing.pdf · uploaded 1 Sep 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100030786 · Commencement Certificate.pdf · uploaded 1 Sep 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100030786 · 25) NA Order.pdf · uploaded 1 Sep 2021Source
  • 1 Declaration about Commencement CertificateP52100030786 · Format D - Florence 1.pdf · uploaded 1 Sep 2021Source
  • 1 Declaration in FORM BP52100030786 · Form B.pdf · uploaded 1 Sep 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100030786 · CA Certificate - Florence 1.pdf · uploaded 1 Sep 2021Source
  • 1 PAN CardP52100030760 · Pan Card The KFP.pdf · uploaded 1 Sep 2021Source
  • 1 Copy of the legal title reportP52100030760 · Title Search Report Annexure.pdf · uploaded 1 Sep 2021Source
  • 1 Details of encumbrancesP52100030760 · Encumbrance Certificate.pdf · uploaded 1 Sep 2021Source
  • 1 Copy of Layout Approval (in case of layout)P52100030760 · Layout.pdf · uploaded 1 Sep 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentP52100030760 · Plan 11 - C Wing.pdf · uploaded 1 Sep 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentP52100030760 · Plan 12 - C Wing.pdf · uploaded 1 Sep 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentP52100030760 · Plan 13 - D Wing.pdf · uploaded 1 Sep 2021Source
  • 4 Building Plan Approval / NA Order for plotted developmentP52100030760 · Plan 14 - D Wing.pdf · uploaded 1 Sep 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentP52100030760 · Commencement Certificate.pdf · uploaded 1 Sep 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentP52100030760 · 25) NA Order.pdf · uploaded 1 Sep 2021Source
  • 1 Declaration about Commencement CertificateP52100030760 · Format D - Florence 2.pdf · uploaded 1 Sep 2021Source
  • 1 Declaration in FORM BP52100030760 · Form B.pdf · uploaded 1 Sep 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100030760 · CA Certificate - Florence 2.pdf · uploaded 1 Sep 2021Source
  • 1 Proforma of Allotment letterP52100030786 · Draft Agreement Florence 1.pdf · uploaded 6 Sep 2021Source
  • 2 Proforma of Allotment letterP52100030786 · Allotment Letter.pdf · uploaded 6 Sep 2021Source
  • 1 Proforma of Allotment letterP52100030760 · Draft Agreement Florence 2.pdf · uploaded 6 Sep 2021Source
  • 2 Proforma of Allotment letterP52100030760 · Allotment Letter.pdf · uploaded 6 Sep 2021Source
  • 2 Copy of Layout Approval (in case of layout)P52100030786 · Layout.pdf · uploaded 1 Mar 2022Source
  • 11 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 1.pdf · uploaded 1 Mar 2022Source
  • 12 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 2.pdf · uploaded 1 Mar 2022Source
  • 13 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 3.pdf · uploaded 1 Mar 2022Source
  • 14 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 4.pdf · uploaded 1 Mar 2022Source
  • 15 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 5.pdf · uploaded 1 Mar 2022Source
  • 16 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 6.pdf · uploaded 1 Mar 2022Source
  • 17 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 7.pdf · uploaded 1 Mar 2022Source
  • 18 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 8.pdf · uploaded 1 Mar 2022Source
  • 19 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 9.pdf · uploaded 1 Mar 2022Source
  • 20 Building Plan Approval / NA Order for plotted developmentP52100030786 · Plan 10.pdf · uploaded 1 Mar 2022Source
  • 2 Copy of Layout Approval (in case of layout)P52100030760 · Layout.pdf · uploaded 1 Mar 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentP52100030760 · Plan 11.pdf · uploaded 1 Mar 2022Source
  • 6 Building Plan Approval / NA Order for plotted developmentP52100030760 · Plan 12.pdf · uploaded 1 Mar 2022Source
  • 7 Building Plan Approval / NA Order for plotted developmentP52100030760 · Plan 13.pdf · uploaded 1 Mar 2022Source
  • 8 Building Plan Approval / NA Order for plotted developmentP52100030760 · Plan 14.pdf · uploaded 1 Mar 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030786 · FORM - 01 EXCELLAA FLORENCE.pdf · uploaded 20 Dec 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030786 · Project Excellaa Florence RERA Form 1 june 22.pdf · uploaded 20 Dec 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030786 · Project Excellaa Florence RERA Form 1 sep 22.pdf · uploaded 20 Dec 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100030786 · Project Excellaa Florence A and B Wing Form 2 march 22.pdf · uploaded 20 Dec 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100030786 · Project Excellaa Florence A and B Wing Form 2 june 22.pdf · uploaded 20 Dec 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100030786 · Project Excellaa Florence A and B Wing Form 2 sep 22.pdf · uploaded 20 Dec 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100030786 · Florence CA Signed form 3 31 03 2022_compressed.pdf · uploaded 20 Dec 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100030786 · Florence CA Signed form 3 30 06 22_compressed.pdf · uploaded 20 Dec 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100030786 · Florence CA Signed form 3 30 09 2022_compressed.pdf · uploaded 20 Dec 2023Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100030786 · Florence CA Signed form 3 31 12 22_compressed.pdf · uploaded 20 Dec 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030760 · FORM - 01 EXCELLAA FLORENCE.pdf · uploaded 20 Dec 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030760 · Project Excellaa Plazzo RERA Form 1 june 22.pdf · uploaded 20 Dec 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030760 · Project Excellaa Plazzo RERA Form 1 sep 22.pdf · uploaded 20 Dec 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100030760 · Project Excellaa Florence C and D Wing Form 2 march 22.pdf · uploaded 20 Dec 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100030760 · Project Excellaa Florence C and D Wing Form 2 june 22.pdf · uploaded 20 Dec 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)P52100030760 · Project Excellaa Florence C and D Wing Form 2 sep 22.pdf · uploaded 20 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100030786 · Signed Form 5 Florence FY 21-22.pdf · uploaded 26 Dec 2023Source
  • 1 Disclosure of sold/ booked inventoryP52100030786 · DISCLOSURE FLORENCE MARCH 22.pdf · uploaded 17 Feb 2024Source
  • 2 Disclosure of sold/ booked inventoryP52100030786 · DISCLOSURE FLORANCE JUNE 22.pdf · uploaded 17 Feb 2024Source
  • 3 Disclosure of sold/ booked inventoryP52100030786 · DISCLOSURE FLORANCE SEP 22.pdf · uploaded 17 Feb 2024Source
  • 4 Disclosure of sold/ booked inventoryP52100030786 · DISCLOSURE FLORANCE DEC 22.pdf · uploaded 17 Feb 2024Source
  • 5 Disclosure of sold/ booked inventoryP52100030786 · DISCLOSURE FLORANCE MARCH 23.pdf · uploaded 17 Feb 2024Source
  • 6 Disclosure of sold/ booked inventoryP52100030786 · DISCLOSURE FLORANCE JUNE 23.pdf · uploaded 17 Feb 2024Source
  • 7 Disclosure of sold/ booked inventoryP52100030786 · DISCLOSURE FLORANCE SEP 23.pdf · uploaded 17 Feb 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030786 · Florence RERA (FORM 1).pdf · uploaded 8 Nov 2024Source
  • 1 Disclosure of sold/ booked inventoryP52100030786 · Sold Disclosure August.pdf · uploaded 8 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100030786 · Florence Form 2A.pdf · uploaded 8 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030760 · Florence RERA (FORM 1).pdf · uploaded 8 Nov 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100030760 · Florence Form 2A-2.pdf · uploaded 8 Nov 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100030786 · Florance 1_Form 3_Dec24.pdf · uploaded 15 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100030786 · Florence 1_Form 5 2022_2023.pdf · uploaded 15 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100030786 · Florence 1_Form 5 2023_2024.pdf · uploaded 15 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)P52100030760 · Florence 2_Form 5 2021_2022.pdf · uploaded 15 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)P52100030760 · Florence 2_Form 5 2022_2023.pdf · uploaded 15 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)P52100030760 · Florence 2_Form 5 2023_2024.pdf · uploaded 15 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030786 · Florence - 1 Form 1 31-03-2025.pdf · uploaded 22 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)P52100030786 · Florence - 1 Form 3 31-03-2025.pdf · uploaded 22 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100030786 · Sold unsold Inventory - Florence - 1 20-04-2025.pdf · uploaded 22 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100030786 · Florence-1 Form 2A -20-04-2025.pdf · uploaded 22 Apr 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)P52100030760 · Florence - 2 Form 1 31-03-2025.pdf · uploaded 22 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryP52100030760 · Sold unsold Inventory - Florence - 2 20-04-2025.pdf · uploaded 22 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)P52100030760 · Florence-2 Form 2A -20-04-2025.pdf · uploaded 22 Apr 2025Source
  • Form 5 (FY 2024-2025)P52100030786 · KFP FORM 5 NO 3_001 signed (1).pdf · uploaded 27 Sep 2025Source
  • Form 5 (FY 2024-2025)P52100030760 · KFP FORM 5 NO 4_001 760 signed.pdf · uploaded 27 Sep 2025Source
  • Form 5 (FY 2021-2022)P52100030786 · fLORENCE 1 21-22.pdf · uploaded 29 Sep 2025Source
  • Form 5 (FY 2022-2023)P52100030786 · fLORENCE 1 22-23.pdf · uploaded 29 Sep 2025Source
  • Form 5 (FY 2023-2024)P52100030786 · fLORENCE 1 23-24.pdf · uploaded 29 Sep 2025Source
  • Form 5 (FY 2021-2022)P52100030760 · fLORENCE2 2021-2022.pdf · uploaded 29 Sep 2025Source
  • Form 5 (FY 2022-2023)P52100030760 · fLORENCE 2 2022-2023.pdf · uploaded 29 Sep 2025Source
  • Form 5 (FY 2023-2024)P52100030760 · fLORECNE 2 2023-2024.pdf · uploaded 29 Sep 2025Source
  • Form 1P52100030786 · Form 1 31032022.pdf · uploaded 24 Oct 2025Source
  • Form 2P52100030786 · Form 2 3132022.pdf · uploaded 24 Oct 2025Source
  • Form 3P52100030786 · FORM 3 31032022.pdf · uploaded 24 Oct 2025Source
  • Disclosure of Sold and Booked InventoryP52100030786 · Disclosure of sold_ booked inventory 31032022.pdf · uploaded 24 Oct 2025Source
  • Form 1P52100030786 · Form 1 30062022.pdf · uploaded 24 Oct 2025Source
  • Form 2P52100030786 · Form 2 30062022.pdf · uploaded 24 Oct 2025Source
  • Form 3P52100030786 · Form 3 30062022.pdf · uploaded 24 Oct 2025Source
  • Disclosure of Sold and Booked InventoryP52100030786 · Inventory 30062022.pdf · uploaded 24 Oct 2025Source
  • Form 1P52100030786 · Form 1 30062022.pdf · uploaded 24 Oct 2025Source
  • Form 2P52100030786 · Form 2 30062022.pdf · uploaded 24 Oct 2025Source
  • Form 3P52100030786 · Form 3 30062022.pdf · uploaded 24 Oct 2025Source
  • Disclosure of Sold and Booked InventoryP52100030786 · Inventory 30062022.pdf · uploaded 24 Oct 2025Source
  • Form 1P52100030786 · FORM 1_FLORENCE 1 A & B.pdf · uploaded 11 Nov 2025Source
  • Form 2P52100030786 · FLORENCE 1 A & B WING_FORM 2 ENGINEERS CERTIFICATE.pdf · uploaded 11 Nov 2025Source
  • Form 3P52100030786 · Florence 1 Form 3.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP52100030786 · FLORENCE 1 Discloure of inventory.pdf · uploaded 11 Nov 2025Source
  • Form 1P52100030760 · FORM 1_FLORENCE 2 C & D.pdf · uploaded 11 Nov 2025Source
  • Form 2P52100030760 · FLORENCE 2 C & D WING_FORM 2 ENGINEERS CERTIFICATE.pdf · uploaded 11 Nov 2025Source
  • Form 3P52100030760 · Florence 2 Form 3.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventoryP52100030760 · FLORENCE 2 Discloure of inventory.pdf · uploaded 11 Nov 2025Source
  • Form 1P52100030786 · FORM 1.pdf · uploaded 24 Jan 2026Source
  • Form 2P52100030786 · FORM 2_compressed.pdf · uploaded 24 Jan 2026Source
  • Form 3P52100030786 · Form 3.pdf · uploaded 24 Jan 2026Source
  • Disclosure of Sold and Booked InventoryP52100030786 · Inventroy.pdf · uploaded 24 Jan 2026Source
  • Form 1P52100030760 · FORM 1.pdf · uploaded 24 Jan 2026Source
  • Form 2P52100030760 · FORM 2 (2).pdf · uploaded 24 Jan 2026Source
  • Form 3P52100030760 · Form 3.pdf · uploaded 24 Jan 2026Source
  • Disclosure of Sold and Booked InventoryP52100030760 · INVENTORY.pdf · uploaded 24 Jan 2026Source
  • Form 1P52100030786 · Form 1.pdf · uploaded 16 Jun 2026Source
  • Form 2P52100030786 · Form 2 Florence ABwing signed copy.pdf · uploaded 16 Jun 2026Source
  • Form 3P52100030786 · Form 3_Florence 1_Mar-26.pdf · uploaded 16 Jun 2026Source
  • Disclosure of Sold and Booked InventoryP52100030786 · Florence 1 inventory.pdf · uploaded 16 Jun 2026Source
  • Form 1P52100030760 · Florence form 1.pdf · uploaded 30 Jun 2026Source
  • Form 2P52100030760 · Form 2 Florence.pdf · uploaded 30 Jun 2026Source
  • Form 3P52100030760 · Florence 2 Form 3.pdf · uploaded 30 Jun 2026Source
  • Disclosure of Sold and Booked InventoryP52100030760 · Florence 2 inventory.pdf · uploaded 30 Jun 2026Source
  • Form 1P52100030786 · Form1.pdf · uploaded 3 Aug 2026Source
  • Form 2P52100030786 · Florence 1 Form 2 signed.pdf · uploaded 3 Aug 2026Source
  • Form 3P52100030786 · Form3.pdf · uploaded 3 Aug 2026Source
  • Disclosure of Sold and Booked InventoryP52100030786 · Inventory.pdf · uploaded 3 Aug 2026Source
  • Form 1P52100030760 · Form1.pdf · uploaded 3 Aug 2026Source
  • Form 2P52100030760 · Florence 2 Form 2 signed.pdf · uploaded 3 Aug 2026Source
  • Form 3P52100030760 · form3.pdf · uploaded 3 Aug 2026Source
  • Disclosure of Sold and Booked InventoryP52100030760 · Inventory.pdf · uploaded 3 Aug 2026Source
  • Withdrawal Update Form 1P52100030786 · Form 1 30-06-2025.pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 2P52100030786 · FORM 2 .pdf · uploaded 11 Aug 2026Source
  • Withdrawal Update Form 3P52100030786 · Form 3_Excella Florence 1_June 2025_compressed (1).pdf · uploaded 11 Aug 2026Source
  • Form 2A (FY 2021-2022)P52100030786 · Form 2A 2021-2022.pdf · uploaded 12 Aug 2026Source
  • Form 2A (FY 2022-2023)P52100030786 · Form 2A 2023-2024.pdf · uploaded 23 Aug 2026Source
  • Form 2A (FY 2023-2024)P52100030786 · Form 2A 2023-2024 1.pdf · uploaded 23 Aug 2026Source
  • Form 2A (FY 2024-2025)P52100030786 · Form 2A 2024-2025.pdf · uploaded 23 Aug 2026Source
  • Form 2A (FY 2025-2026)P52100030786 · Form 2A 2025-2026.pdf · uploaded 23 Aug 2026Source
  • Occupational CertificateP52100030786 · A and B Building Completion Certificate.pdf · uploaded 23 Aug 2026Source
  • Form 5 (FY 2025-2026)P52100030786 · Florence 1.pdf · uploaded 28 Sep 2026Source
  • Form 5 (FY 2025-2026)P52100030760 · Florence 2 form 5.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentP52100030786 · Layout.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 1 - Parking.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 2 - A Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 3 - A Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 4 - A Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 5 - A Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 6 - B Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 7 - B Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 8 - B Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 9 - B Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Plan 10 - B Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030760 · Plan 11 - C Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030760 · Plan 12 - C Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030760 · Plan 13 - D Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030760 · Plan 14 - D Wing.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030760 · Layout.pdf · uploaded 1 Sep 2021Source
  • DocumentP52100030786 · Layout.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 1.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 2.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 3.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 4.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 5.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 6.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 7.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 8.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 9.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030786 · Plan 10.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030760 · Layout.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030760 · Plan 11.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030760 · Plan 12.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030760 · Plan 13.pdf · uploaded 1 Mar 2022Source
  • DocumentP52100030760 · Plan 14.pdf · uploaded 1 Mar 2022Source

Technical (Architect)

  • DocumentP52100030760 · Project Excellaa Plazzo RERA Form 1 sep 22.pdf · uploaded 20 Dec 2023Source
  • DocumentP52100030786 · Florence RERA (FORM 1).pdf · uploaded 8 Nov 2024Source
  • DocumentP52100030760 · Florence RERA (FORM 1).pdf · uploaded 8 Nov 2024Source
  • DocumentP52100030786 · Florence - 1 Form 1 31-03-2025.pdf · uploaded 22 Apr 2025Source
  • DocumentP52100030760 · Florence - 2 Form 1 31-03-2025.pdf · uploaded 22 Apr 2025Source
  • DocumentP52100030786 · Form 1 30-06-2025.pdf · uploaded 11 Aug 2026Source

Technical (Engineer)

  • DocumentP52100030760 · Project Excellaa Florence C and D Wing Form 2 sep 22.pdf · uploaded 20 Dec 2023Source
  • DocumentP52100030786 · FORM 2 .pdf · uploaded 11 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Pirangut, Mulshi taluka

Survey, CTS, gat or plot numbers

149150151152254Gat No. 148/1

Boundaries

North
Gat No 153 155 and 156
South
Gat No 147 and 148 and remaining area of 254
East
Pirangut - Lavle State Highway 115
West
Gat No 171 and Nala

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.RERA
ArchitectCubix Architect Associates—P52100030760
ArchitectCubix Architect Associates—P52100030786
Chartered accountantPushpa Bogati—P52100030786
Chartered accountantPushpa Bogati—P52100030760
Chartered accountantS P A K & Co—P52100030760
Chartered accountantSushant Mahekar—P52100030760
Chartered accountantV C Shah & Co—P52100030786
Chartered accountantV C Shah & Co—P52100030760
Show all 11 professionalsShow fewer professionals
RoleNameRegistration no.RERA
EngineerNilesh Thombare—P52100030786
EngineerStructure Vizion—P52100030760
EngineerStructure Vizion—P52100030786

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology