Skip to content

Om Tapovan

Certificate Signed

Osade, Pune 411025 |Promoter: Om Tapovan

14 Mar 2024Registered with MahaRERA
31 Dec 2026Promised completion
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Certificate Signed
Address
547, 548 And 556, OsadePIN 411025
Designated bank account
119
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.38641, 73.68726
Om Tapovan is at latitude 18.38641, longitude 73.68726.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2026

Registered
14 Mar 2024
Promised
31 Dec 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005531814 Mar 202431 Dec 202631 Dec 2026Om TapovanProject page

Documents

1 document held by Deedo, 87 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD_OM TAPOVAN.pdf · uploaded 29 Nov 2023Source

Legal

  • Declaration Form BOM TAPOVAN RERA FORM B PROMOTOR.pdf · uploaded 29 Nov 2023Source
  • Other – LegalSale Deed GAT NO 548_compressed.pdf · uploaded 6 Jan 2024Source
  • Other – LegalSale Deed GAT NO 556_compressed.pdf · uploaded 6 Jan 2024Source
  • Other – LegalSUPPLIMENTARY Partnership Deed OM TAPOVAN.pdf · uploaded 6 Jan 2024Source
  • Other – LegalDeshpande kharedikhat Compressed.pdf · uploaded 6 Jan 2024Source
  • Other – LegalOM TAPOVAN PARTNERSHIP DEED_compressed.pdf · uploaded 6 Jan 2024Source
Show all 88 documentsShow fewer documents

Legal

  • Legal Title reportSearch and title report rera 547_compressed.pdf · uploaded 21 Feb 2024Source
  • Legal Title reportSearch and Title Report Rera 548_compressed.pdf · uploaded 21 Feb 2024Source
  • Legal Title reportsearch and title report rera 556_compressed.pdf · uploaded 21 Feb 2024Source

Migrated

  • 1 PAN CardPAN CARD_OM TAPOVAN.pdf · uploaded 29 Nov 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentNonAgriculturalOrder.pdf · uploaded 29 Nov 2023Source
  • 1 Declaration about Commencement CertificateRERA COMMENCEMENT CERTIFICATE056.pdf · uploaded 29 Nov 2023Source
  • 1 Declaration in FORM BOM TAPOVAN RERA FORM B PROMOTOR.pdf · uploaded 29 Nov 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samedeclaration about separate bank account .pdf · uploaded 30 Nov 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 ENGIEENIRS CIRTIFICATE.pdf · uploaded 6 Dec 2023Source
  • 1 Proforma of Allotment letterallotment letter.pdf · uploaded 7 Dec 2023Source
  • 1 Proforma of Agreement for saleModel_Agreement_for_Sale_Plotted_Layout.pdf · uploaded 7 Dec 2023Source
  • 1 Deviation Report with respect to Allotment letterdeviation allotment letter.pdf · uploaded 7 Dec 2023Source
  • 1 Deviation Report with respect to model copy of Agreementdeviation agreement to sale.pdf · uploaded 7 Dec 2023Source
  • 1 Copy of Layout Approval (in case of layout)PMRD SACTION PLAN 1_compressed.pdf · uploaded 18 Dec 2023Source
  • 2 Copy of Layout Approval (in case of layout)PMRD SACTION PLAN 2_compressed.pdf · uploaded 18 Dec 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCOMMECEMENT CERTIFICATE.pdf · uploaded 27 Dec 2023Source
  • 1 a Details of encumbrances concerned to FinanceLegal Encumbrance.pdf · uploaded 6 Jan 2024Source
  • 1 b Details of encumbrances concerned to LegalLegal Encumbrance.pdf · uploaded 6 Jan 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)TAPOVAN_FORM 1 compressed.pdf · uploaded 6 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A.pdf · uploaded 6 Jan 2024Source
  • 1 Other – LegalSale Deed GAT NO 548_compressed.pdf · uploaded 6 Jan 2024Source
  • 2 Other – LegalSale Deed GAT NO 556_compressed.pdf · uploaded 6 Jan 2024Source
  • 3 Other – LegalSUPPLIMENTARY Partnership Deed OM TAPOVAN.pdf · uploaded 6 Jan 2024Source
  • 4 Other – LegalDeshpande kharedikhat Compressed.pdf · uploaded 6 Jan 2024Source
  • 5 Other – LegalOM TAPOVAN PARTNERSHIP DEED_compressed.pdf · uploaded 6 Jan 2024Source
  • 1 Copy of the legal title reportSearch and title report rera 547_compressed.pdf · uploaded 21 Feb 2024Source
  • 2 Copy of the legal title reportSearch and Title Report Rera 548_compressed.pdf · uploaded 21 Feb 2024Source
  • 3 Copy of the legal title reportsearch and title report rera 556_compressed.pdf · uploaded 21 Feb 2024Source
  • 2 a Details of encumbrances concerned to FinanceDeclaration of Finance Encumbrance.pdf · uploaded 21 Feb 2024Source
  • 2 b Details of encumbrances concerned to LegalDeclaration of Finance Encumbrance.pdf · uploaded 21 Feb 2024Source
  • 1 CERSAI detailsCERSAI_Search Report_OM TAPOVAN.pdf · uploaded 21 Feb 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 A N Pathak compressed.pdf · uploaded 21 Feb 2024Source
  • 1 Other – TechnicalDeclaration of Project Om Tapovan.pdf · uploaded 21 Feb 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Om Tapovan as on March 2024.pdf · uploaded 11 Jun 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Om Tapovan - March 2024.pdf · uploaded 14 Jun 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Om Tapovan - March 2024.pdf · uploaded 14 Jun 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Om Tapovan - June 2024.pdf · uploaded 19 Jul 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 of Om Tapovan as on 30-06-2024.pdf · uploaded 19 Jul 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Om Tapovan as on Sep 2024.pdf · uploaded 14 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 20 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 CA Certificate on Project Cost Fund withdrawal (Form 3).pdf · uploaded 20 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 20 Feb 2025Source
  • Form 1Form 1 - Om Tapovan as on June 2025.pdf · uploaded 6 Jun 2026Source
  • Form 2Form 2 - Om Tapovan as on June 2025.pdf · uploaded 6 Jun 2026Source
  • Form 3Form 3 - Om Tapovan as on June 2025.pdf · uploaded 6 Jun 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Om Tapovan as on June 2025.pdf · uploaded 6 Jun 2026Source
  • Form 1Form 1 - Om Tapovan as on Sep 2025.pdf · uploaded 6 Jun 2026Source
  • Form 2Form 2 - Om Tapovan as on Sep 2025.pdf · uploaded 6 Jun 2026Source
  • Form 3Form 3 - Om Tapovan as on Sep 2025.pdf · uploaded 6 Jun 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Om Tapovan as on Sep 2025.pdf · uploaded 6 Jun 2026Source
  • Form 1Form 1 - Om Tapovan as on Dec 2025.pdf · uploaded 6 Jun 2026Source
  • Form 2Form 2 - Om Tapovan as on Dec 2025.pdf · uploaded 6 Jun 2026Source
  • Form 3Form 3 - Om Tapovan as on Dec 2025.pdf · uploaded 6 Jun 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Om Tapovan as on Dec 2025.pdf · uploaded 6 Jun 2026Source
  • Form 1Form 1 - Om Tapovan as on March 2026.pdf · uploaded 6 Jun 2026Source
  • Form 2Form 2 - Om Tapovan as on March 2026.pdf · uploaded 6 Jun 2026Source
  • Form 3Form 3 - Om Tapovan as on March 2026.pdf · uploaded 6 Jun 2026Source
  • Disclosure of Sold and Booked InventoryCircular 29 - Om Tapovan as on March 2026.pdf · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 1Form 1 - Om Tapovan as on March 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 2Form 2 - Om Tapovan as on March 2026.pdf · uploaded 30 Jul 2026Source
  • Withdrawal Update Form 3Form 3 - Om Tapovan as on March 2026.pdf · uploaded 30 Jul 2026Source
  • Form 2A (FY 2025-2026)FORM 2A_FY_2025-26.pdf · uploaded 21 Aug 2026Source
  • Withdrawal Update Form 1Form 1 - Om Tapovan as on June 2026.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 2Form 2 - Om Tapovan as on June 2026.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 3Form 3 - Om Tapovan as on June 2026.pdf · uploaded 17 Sep 2026Source
  • Withdrawal Update Form 1Form 1 - Om Tapovan as on June 2026.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 2Form 2 - Om Tapovan as on June 2026.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 3Form 3 - Om Tapovan as on June 2026.pdf · uploaded 18 Sep 2026Source
  • Withdrawal Update Form 1Form 1 - Om Tapovan as on June 2026.pdf · uploaded 21 Sep 2026Source
  • Withdrawal Update Form 2Form 2 - Om Tapovan as on June 2026.pdf · uploaded 21 Sep 2026Source
  • Withdrawal Update Form 3Form 3 - Om Tapovan as on June 2026.pdf · uploaded 21 Sep 2026Source

Technical

  • DocumentNonAgriculturalOrder.pdf · uploaded 29 Nov 2023Source
  • DocumentPMRD SACTION PLAN 1_compressed.pdf · uploaded 18 Dec 2023Source
  • DocumentPMRD SACTION PLAN 2_compressed.pdf · uploaded 18 Dec 2023Source
  • Other – TechnicalDeclaration of Project Om Tapovan.pdf · uploaded 21 Feb 2024Source

Technical (Architect)

  • DocumentForm 1 - Om Tapovan as on Sep 2024.pdf · uploaded 14 Nov 2024Source
  • Document3 Architect’s Certificate of Percentage of Completion of Work (Form 1).pdf · uploaded 20 Feb 2025Source
  • DocumentForm 1 - Om Tapovan as on June 2026.pdf · uploaded 17 Sep 2026Source

Technical (Engineer)

  • Document3 Engineer’s Certificate on Cost Incurred on Project (Form 2).pdf · uploaded 20 Feb 2025Source
  • DocumentForm 2 - Om Tapovan as on June 2026.pdf · uploaded 17 Sep 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Osade, Velhe taluka

Survey, CTS, gat or plot numbers

547548556

Boundaries

North
Gat No 489 Gat No 490 And 12 Mtrs Road
South
Gat No 549
East
Gat No 557
West
Gat No 521 Gat No 546 And 12 Mtrs Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNilesh Bide—
Chartered accountantAditya N Pathak—
Chartered accountantRutuja Narsingh & Associates—
EngineerSK Consultants & Engineers—
EngineerVinayak Lohokar—
OtherRERA Easy—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology