Building No 6 · Skyi Manas Lake

Mulshi · RERA P52100025845

IDBLD_04216014 floorsPromised date passed
14Sanctioned habitable floorsregistration certificate
30 Mar 2024Revised completionpromised 30 Mar 2024
91 of 95Units bookedMahaRERA project page

Floors

14 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100025845 · registered 20 Jul 2020
Promised completion
30 Mar 2024
Revised completion
30 Mar 2024
Sanctioned habitable floors
14
ProjectId
28,308
ProjectName
Skyi Manas Lake Phase V
TotalUnitCount
0
ProjectBuildingId
57,815
BuildingNameNumber
Building No 6
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52100025845
ProjectBuildingWingsId
57,815
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Building No 6
NoOfBuildingWingFloorProposed
14
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
14

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK47.5 m² (511 sq.ft)9591
Total9591
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology