Skip to content

A Building · Anp Memento

Mulshi · RERA P52100026219

IDBLD_03759923 floorsExtended 4 mo
23Sanctioned habitable floorsregistration certificate
30 Jan 2027Revised completionpromised 30 Sep 2026
83 of 92Units bookedMahaRERA project page

Floors

23 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100026219 · registered 30 Aug 2020
Promised completion
30 Sep 2026
Revised completion
30 Jan 2027
Sanctioned habitable floors
23
ProjectId
28,451
ProjectName
ANP MEMENTO
TotalUnitCount
92
ProjectBuildingId
1,51,284
BuildingNameNumber
A BUILDING
FsiWithSanctionSqmts
32
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
92
ProjectRegistartionNo
P52100026219
ProjectBuildingWingsId
1,54,709
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
A BUILDING
NoOfBuildingWingFloorProposed
32
NoOfBuildingWingFloorHabitable
23
NoOfBuildingWingFloorSanctioned
32

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
3BHK74.1 m² (797 sq.ft)40
3BHK89.3 m² (962 sq.ft)4238
3BHK92.9 m² (1,000 sq.ft)2222
3BHK101.7 m² (1,095 sq.ft)2423
Total9283
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology