Gokuldhaam
Certificate SignedKondhapuri, Pune 412208 |Promoter: Setu Developers
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 5
- Unit types
- 1BHK180 units in all
- Address
- GAT NO 638 P, Kondhapuri, SHIRURPIN 412208
- Designated bank account
- 82
- Developed in phases
- Yes
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 22 Feb 2022
- Promised
- 31 Dec 2028
- Revised
- 30 Apr 2029
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100033484 | 22 Feb 2022 | 31 Dec 2028 | 30 Apr 2029 | Setu Developers | Project page |
5 buildings
Buildings and wings named in the registration
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
23 of 180 units booked (13%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing A1 | 1BHK | 34.02 sq m · 366 sq ft | 12 | 1 |
| Wing A1 | 1BHK | 34.42 sq m · 370 sq ft | 12 | 12 |
| Wing A1 | 1BHK | 35.71 sq m · 384 sq ft | 12 | 6 |
| Wing A2 | 1BHK | 34.02 sq m · 366 sq ft | 12 | 0 |
| Wing A2 | 1BHK | 34.42 sq m · 370 sq ft | 12 | 4 |
| Wing A2 | 1BHK | 35.71 sq m · 384 sq ft | 12 | 0 |
| Wing A3 | 1BHK | 34.02 sq m · 366 sq ft | 12 | 0 |
| Wing A3 | 1BHK | 34.42 sq m · 370 sq ft | 12 | 0 |
Show all 15 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Wing A3 | 1BHK | 35.71 sq m · 384 sq ft | 12 | 0 |
| Wing A4 | 1BHK | 34.02 sq m · 366 sq ft | 12 | 0 |
| Wing A4 | 1BHK | 34.42 sq m · 370 sq ft | 12 | 0 |
| Wing A4 | 1BHK | 35.71 sq m · 384 sq ft | 12 | 0 |
| Wing A5 | 1BHK | 34.02 sq m · 366 sq ft | 12 | 0 |
| Wing A5 | 1BHK | 34.42 sq m · 370 sq ft | 12 | 0 |
| Wing A5 | 1BHK | 35.71 sq m · 384 sq ft | 12 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 151 filings listed on MahaRERA's project page
Finance
- PAN CardPan card.pdf · uploaded 25 Jan 2022Source
Legal
Migrated
- 1 PAN CardPan card.pdf · uploaded 25 Jan 2022Source
- 1 Details of encumbrancesLetter of Encumberance.pdf · uploaded 25 Jan 2022Source
- 1 Copy of Layout Approval (in case of layout)4 Layout approval_compressed.pdf · uploaded 25 Jan 2022Source
- 2 Copy of Layout Approval (in case of layout)4 layout approval-2_compressed.pdf · uploaded 25 Jan 2022Source
Show all 152 documentsShow fewer documents
Migrated
- 1 Building Plan Approval / NA Order for plotted developmentBuilding Approval_compressed.pdf · uploaded 25 Jan 2022Source
- 1 Commencement Certificates / NA Order for plotted development10 comencement certificate_compressed.pdf · uploaded 25 Jan 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)7 Cerificates of Architect-1.pdf · uploaded 25 Jan 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate 1.pdf · uploaded 25 Jan 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)7 Cerificates of Architect-2.pdf · uploaded 25 Jan 2022Source
- 1 Proforma of Allotment letterSpecimen of Allotment letter.pdf · uploaded 25 Jan 2022Source
- 1 Declaration about Commencement Certificate11 Format-D.pdf · uploaded 2 Feb 2022Source
- 1 Copy of the legal title report2 Form-A.pdf · uploaded 12 Feb 2022Source
- 1 Declaration in FORM BForm-B (final).pdf · uploaded 12 Feb 2022Source
- 1 CERSAI detailsCersai Search and Undertaking.pdf · uploaded 12 Feb 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate (Final)_compressed.pdf · uploaded 16 Feb 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 11 Mar 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate.pdf · uploaded 11 Mar 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameBank Account Declaration.pdf · uploaded 11 Mar 2023Source
- 1 Disclosure of sold/ booked inventoryDisclosure of sold booked inventory.pdf · uploaded 3 Apr 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Final.pdf · uploaded 19 Mar 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Qua4-22-23_0001.pdf · uploaded 5 Jun 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Qua1-22-23_0001.pdf · uploaded 5 Jun 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Qua2-22-23_0001_0001.pdf · uploaded 5 Jun 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Qua3-22-23_0001.pdf · uploaded 5 Jun 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Qua4-22-23_0001.pdf · uploaded 5 Jun 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Qua1-23-24_0001.pdf · uploaded 5 Jun 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Qua2-23-24_0001.pdf · uploaded 5 Jun 2024Source
- 2 Disclosure of sold/ booked inventoryBooking List_0001.pdf · uploaded 5 Jun 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA_Certificate_SD_Q4_FY 21-22.pdf · uploaded 5 Jun 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q1 22-23.pdf · uploaded 5 Jun 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q2 22-23.pdf · uploaded 5 Jun 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q3 22-23.pdf · uploaded 5 Jun 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q4 22-23.pdf · uploaded 5 Jun 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q1 23-24.pdf · uploaded 5 Jun 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q2 23-24.pdf · uploaded 5 Jun 2024Source
- 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q3 23-24.pdf · uploaded 5 Jun 2024Source
- 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Q4 23-24.pdf · uploaded 5 Jun 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Qua3-FY 23-24_0001.pdf · uploaded 6 Jun 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Qua4-24-25_0001.pdf · uploaded 6 Jun 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc Certificate Qu4 21-22.pdf · uploaded 13 Jun 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc Certificate Qu1-22-23.pdf · uploaded 13 Jun 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc Certificate Qu2 22-23.pdf · uploaded 13 Jun 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc Certificate Qu3 22-23.pdf · uploaded 13 Jun 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc Certificate Qu4 22-23.pdf · uploaded 13 Jun 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc Certificate Qu1-23-24.pdf · uploaded 13 Jun 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc Certificate Qu2 23-24.pdf · uploaded 13 Jun 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc Certificate Qu3 23-24.pdf · uploaded 13 Jun 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arc Certificate Qua4-FY2023-24.pdf · uploaded 13 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)F2A March End 2021_0001.pdf · uploaded 14 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)F2A March End 2022_0001.pdf · uploaded 14 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)F2A March End 2023_0001.pdf · uploaded 14 Jun 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)F2A March End 2024_0001.pdf · uploaded 14 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FY 20-21.pdf · uploaded 21 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FY 21-22.pdf · uploaded 21 Jun 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FY 23-24.pdf · uploaded 21 Jun 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate Q1 15-07-2024.pdf · uploaded 20 Dec 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate Q2 15-10-2024.pdf · uploaded 20 Dec 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA_Certificate_SD_Q1_FY 24-25_compressed.pdf · uploaded 20 Dec 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA_Certificate_SD_Q2_FY 24-25_compressed.pdf · uploaded 20 Dec 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate Q1 15-07-2024.pdf · uploaded 20 Dec 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate Q2 15-10-2024.pdf · uploaded 20 Dec 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 7 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 CA Certificate SD Q3 FY 2024 25.pdf · uploaded 7 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 7 Feb 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate.pdf · uploaded 30 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Signed Form 3 CA Certificate Q4 FY23-24.pdf · uploaded 30 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate.pdf · uploaded 30 Apr 2025Source
- Form 1ASETU-15-JUN-2025.pdf · uploaded 29 Sep 2026Source
- Form 2Eng Certificate For Rera Updation.pdf · uploaded 29 Sep 2026Source
- Form 3FCA1.pdf · uploaded 29 Sep 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 29 Sep 2026Source
- Form 1ASETU-15-SEP-2025.pdf · uploaded 29 Sep 2026Source
- Form 2Eng Certificate For Rera Updation.pdf · uploaded 29 Sep 2026Source
- Form 3FCA2.pdf · uploaded 29 Sep 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 29 Sep 2026Source
- Form 1ASETU-15-DEC-2025.pdf · uploaded 29 Sep 2026Source
- Form 2Eng Certificate For Rera Updation.pdf · uploaded 29 Sep 2026Source
- Form 3FCA3.pdf · uploaded 29 Sep 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 29 Sep 2026Source
- Form 1ASETU-15-March-2026.pdf · uploaded 29 Sep 2026Source
- Form 2Eng Certificate For Rera Updation.pdf · uploaded 29 Sep 2026Source
- Form 3FCA4.pdf · uploaded 29 Sep 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Sold Booked Inventory.pdf · uploaded 29 Sep 2026Source
- Form 1June 22 - CA.pdf · uploaded 6 Oct 2026Source
- Form 2June 22 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3June 22 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 6 Oct 2026Source
- Form 1Sept 22 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2Sept 22 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3Sept 22 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 6 Oct 2026Source
- Form 1Dec 22 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2Dec 22 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3Dec 22 -CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 6 Oct 2026Source
- Form 1March 23 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2March 23 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3March 23 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 6 Oct 2026Source
- Form 1June 23 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2June 23 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3June 23 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 6 Oct 2026Source
- Form 1Sept 23 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2Sept 23 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3Sept 23 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 6 Oct 2026Source
- Form 1Dec 23 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2Dec 23 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3Dec 23 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 6 Oct 2026Source
- Form 1March 24 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2March 24 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3March 24 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 6 Oct 2026Source
- Form 1March 22 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2March 22 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3March 22 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure.pdf · uploaded 6 Oct 2026Source
- Form 1June 24 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2June 24 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3June 24 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Units.pdf · uploaded 6 Oct 2026Source
- Form 1Sept 24 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2Sept 24 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3Sept 24 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Units.pdf · uploaded 6 Oct 2026Source
- Form 1Dec 24 - AR.pdf · uploaded 6 Oct 2026Source
- Form 2Dec 24 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3Dec 24 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Units.pdf · uploaded 6 Oct 2026Source
- Form 1March 25 -AR.pdf · uploaded 6 Oct 2026Source
- Form 2March 25 - ER.pdf · uploaded 6 Oct 2026Source
- Form 3March 25 - CA.pdf · uploaded 6 Oct 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of Units.pdf · uploaded 6 Oct 2026Source
Technical
Technical (Architect)
- DocumentArc Certificate Qua4-FY2023-24.pdf · uploaded 13 Jun 2024Source
- DocumentForm 1 Architect Certificate Q1 15-07-2024.pdf · uploaded 20 Dec 2024Source
- DocumentForm 1 Architect Certificate Q2 15-10-2024.pdf · uploaded 20 Dec 2024Source
- DocumentForm 1 Architect Certificate.pdf · uploaded 7 Feb 2025Source
- DocumentForm 1 Architect Certificate.pdf · uploaded 30 Apr 2025Source
Technical (Engineer)
- DocumentEngineer Certificate Qua4-24-25_0001.pdf · uploaded 6 Jun 2024Source
- DocumentForm 2 Engineers Certificate Q1 15-07-2024.pdf · uploaded 20 Dec 2024Source
- DocumentForm 2 Engineers Certificate Q2 15-10-2024.pdf · uploaded 20 Dec 2024Source
- DocumentForm 2 Engineer Certificate.pdf · uploaded 7 Feb 2025Source
- DocumentForm 2 Engineers Certificate.pdf · uploaded 30 Apr 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Kondhapuri, Shirur taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Concrete Road For Gaothan And Ganegaon
- South
- Gat No 638 Part Mr Subhash Nanasaheb Sandbhor
- East
- Gat No 639 Part
- West
- Gat No 638 Part Mr Navnath Bapurao Gaikwad
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Roofline Design Studio | — |
| Chartered accountant | B K Kothari & Associates LLP | — |
| Chartered accountant | Sudam Dinkar Ghongatepatil | — |
| Engineer | Kalpesh Borhade And Co | — |
Source: MahaRERA project page. Contact details are not shown.