C · Nirman Milestone
Kivale · RERA P52100022161
IDBLD_0381569 floorsExtended 7 mo
9Sanctioned habitable floorsregistration certificate
31 Jul 2024Revised completionpromised 30 Dec 2023
25 of 25Units bookedMahaRERA project page
Floors
9 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100022161 · registered 4 Sep 2019
- Promised completion
- 30 Dec 2023
- Revised completion
- 31 Jul 2024
- Sanctioned habitable floors
- 9
- ProjectId
- 24,898
- ProjectName
- Nirman Milestone
- TotalUnitCount
- 0
- ProjectBuildingId
- 55,656
- BuildingNameNumber
- C
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100022161
- ProjectBuildingWingsId
- 55,656
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- C
- NoOfBuildingWingFloorProposed
- 9
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 9
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 58.2 m² (627 sq.ft) | 4 | 4 |
| 2BHK | 68 m² (732 sq.ft) | 21 | 21 |
| Total | 25 | 25 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology