C Type · Anandtara Iris Residences Phase I

Keshavnagar Mundwa · RERA P52100054845

IDBLD_03884114 floorsExtended 4 mo
14Sanctioned habitable floorsregistration certificate
30 Apr 2027Revised completionpromised 31 Dec 2026
6 of 52Units bookedMahaRERA project page

Floors

14 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100054845 · registered 15 Feb 2024
Promised completion
31 Dec 2026
Revised completion
30 Apr 2027
Sanctioned habitable floors
14
ProjectId
42,812
ProjectName
ANANDTARA IRIS RESIDENCES PHASE I
TotalUnitCount
52
ProjectBuildingId
1,30,478
BuildingNameNumber
C Type
FsiWithSanctionSqmts
17
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
52
ProjectRegistartionNo
P52100054845
ProjectBuildingWingsId
1,33,895
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
C Type
NoOfBuildingWingFloorProposed
17
NoOfBuildingWingFloorHabitable
14
NoOfBuildingWingFloorSanctioned
17

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK59.1 m² (636 sq.ft)20
3BHK77.7 m² (836 sq.ft)131
3BHK78.3 m² (842 sq.ft)110
3BHK89.8 m² (966 sq.ft)133
3BHK92.6 m² (997 sq.ft)132
Total526
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology