Nishigandh, B Wing
Certificate SignedKasar Amboli, Pune 412108 |Promoter: Nirmiti Realities
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 2BHK32 units in all
- Address
- 251(Part), Paud Road, KasaramboliPIN 412108
- Designated bank account
- 85
- Developed in phases
- No
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
- Registered
- 3 Feb 2023
- Promised
- 22 Dec 2026
- Revised
- 22 Apr 2027
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100049240 | 3 Feb 2023 | 22 Dec 2026 | 22 Apr 2027 | Nirmiti Realities | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Nishigandh, B Wing | 6 | 32 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
0 of 32 units booked (0%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 39.66 sq m · 427 sq ft | 24 | 0 |
| 2BHK | 54.65 sq m · 588 sq ft | 8 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 77 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD- NIRMITI REALITIES.pdf · uploaded 5 Jan 2023Source
Legal
Migrated
- 1 PAN CardPAN CARD- NIRMITI REALITIES.pdf · uploaded 5 Jan 2023Source
- 1 Copy of Layout Approval (in case of layout)LAY OUT.PDF · uploaded 5 Jan 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentBUILDING SANCTION LAY OUT.PDF · uploaded 5 Jan 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentNA ORDER.pdf · uploaded 5 Jan 2023Source
Show all 78 documentsShow fewer documents
Migrated
- 2 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT CERTIFICATE.pdf · uploaded 5 Jan 2023Source
- 1 Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMNT CERTIFICATE- FORM NO D.pdf · uploaded 5 Jan 2023Source
- 1 Declaration in FORM BFORM B- DECLARATION BY PROMOTER.pdf · uploaded 5 Jan 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARTCHITECH CERTIFICATE- New.pdf · uploaded 5 Jan 2023Source
- 1 CERSAI detailsCERSAI- Search Report.pdf · uploaded 5 Jan 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsAnnexure A- Discloser of interest in other real estate orgnization.pdf · uploaded 5 Jan 2023Source
- 1 Proforma of Allotment letterProforma of Allotment letter as per order no 31.pdf · uploaded 5 Jan 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation report with respect to allotment letter.pdf · uploaded 5 Jan 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA- FORM 3.pdf · uploaded 13 Jan 2023Source
- 1 a Details of encumbrances concerned to FinanceDeclaration regarding encumbrances.pdf · uploaded 18 Jan 2023Source
- 1 b Details of encumbrances concerned to LegalDeclaration regarding encumbrances.pdf · uploaded 18 Jan 2023Source
- 1 Proforma of Agreement for saleAGREEMENT TO SALE - KASARAMBOLI- GAT NO 251-NIRMIT REALTIES.pdf · uploaded 18 Jan 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION- Separate Bank Account.pdf · uploaded 18 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report with respect to copy of Agreement- NIRMITI REALTIES.pdf · uploaded 18 Jan 2023Source
- 1 Copy of the legal title reportSearch FORMAT A- Nirmiti Realities.pdf · uploaded 25 Jan 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 4 q1 22-23.pdf · uploaded 5 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 q1 FY 23-24.pdf · uploaded 5 Jan 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 q2 FY 23-24.pdf · uploaded 5 Jan 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 q3 FY 23-24.pdf · uploaded 5 Jan 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Mar 2023.pdf · uploaded 5 Jan 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 June 2023.pdf · uploaded 5 Jan 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sep 2023.pdf · uploaded 5 Jan 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 2023.pdf · uploaded 5 Jan 2024Source
- 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Mar 2023.pdf · uploaded 5 Jan 2024Source
- 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 June 2023.pdf · uploaded 5 Jan 2024Source
- 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Sep 2023.pdf · uploaded 5 Jan 2024Source
- 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Dec 2023.pdf · uploaded 5 Jan 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- March 23.pdf · uploaded 5 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- June 23.pdf · uploaded 5 Jan 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Sep 23.pdf · uploaded 5 Jan 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Dec 23.pdf · uploaded 5 Jan 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 1 - Dec 2023.pdf · uploaded 5 Jan 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 1 - Dec 2023.pdf · uploaded 5 Jan 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Mar 2023.pdf · uploaded 5 Jan 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 June 2023.pdf · uploaded 5 Jan 2024Source
- 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Sep 2023.pdf · uploaded 5 Jan 2024Source
- 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec 2023.pdf · uploaded 5 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A- Nirmiti.pdf · uploaded 5 Jan 2024Source
- 1 Disclosure of sold/ booked inventorySold Unsold- Nishi.pdf · uploaded 5 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Mar 2023.pdf · uploaded 5 Jan 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 June 2023.pdf · uploaded 5 Jan 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Sep 2023.pdf · uploaded 5 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Dec 2023.pdf · uploaded 5 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Form 5 (2).pdf · uploaded 5 Jan 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)RERA Form 5.pdf · uploaded 5 Jan 2024Source
- 3 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Rera.pdf · uploaded 5 Jan 2024Source
- 2 Proforma of Agreement for saleAGREEMENT TO SALE RERA.pdf · uploaded 6 Jan 2024Source
- 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 q3 FY 23-24.pdf · uploaded 27 May 2024Source
- 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2- Nirmiti.pdf · uploaded 27 May 2024Source
- 2 Disclosure of sold/ booked inventorySold Unsold- Nirmiti.pdf · uploaded 27 May 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)SIGNED FORM Q4.pdf · uploaded 27 May 2024Source
- Withdrawal Update Form 1FORM 1 q3 FY 23-24.pdf · uploaded 17 Dec 2025Source
- Withdrawal Update Form 1FORM 1 q3 FY 23-24 (2).pdf · uploaded 17 Dec 2025Source
- Withdrawal Update Form 2Form 2- June 25.pdf · uploaded 17 Dec 2025Source
- Withdrawal Update Form 2Form 2- June 25.pdf · uploaded 17 Dec 2025Source
- Withdrawal Update Form 3Q1 FY 25-26 Nirmitee.pdf · uploaded 17 Dec 2025Source
- Withdrawal Update Form 3Q2 FY 25-26 Nirmitee.pdf · uploaded 17 Dec 2025Source
- Withdrawal Update Form 1FORM 1 Dec 25.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 1FORM 1 March 26.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 1FORM 1 June 26.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 2Form 2 Dec 25.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 2Form 2 March 26 nirmiti.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 2F2 June 2026.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 3Form 3 Nirmitee (1) (1)-7-12.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 3Form 3 Nirmitee (1) (1)-13-18.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 3Form 3 Nirmitee (1) (1)-19-24.pdf · uploaded 17 Aug 2026Source
Technical
Technical (Architect)
- DocumentFORM 1 June 26.pdf · uploaded 17 Aug 2026Source
Technical (Engineer)
- DocumentF2 June 2026.pdf · uploaded 17 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Kasar Amboli, Mulshi taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Adj S no 252
- South
- Adj S no 248
- East
- Adj S no 250
- West
- Adj Exiting 9 M wide Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Walhekar & Associates | — |
| Chartered accountant | Deepak Kshirsagar & Co | — |
| Engineer | Jitendra Madhukar Kendre | — |
Source: MahaRERA project page. Contact details are not shown.