Skip to content

Redevelopment of Ajanta co-op hou.soc ltd

Certificate Signed

Vasai Virar City (M Corp), Palghar 401209 |Promoter: S R Builders & Developers

Residential / Group HousingRERAP99000013423
5 Oct 2017Registered with MahaRERA
31 Dec 2028Promised completion
30 Apr 2029Revised completionPushed back 4 months
1Building
35Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 1RK35 units in all
Address
S. no. 188 H. no.3, S NO 188, H NO 3PIN 401209
Designated bank account
82
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.40545, 72.83087
Redevelopment of Ajanta co-op hou.soc ltd is at latitude 19.40545, longitude 72.83087.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
5 Oct 2017
Promised
31 Dec 2028
Revised
30 Apr 2029

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000134235 Oct 201731 Dec 202830 Apr 2029S R Builders & DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Ajanta co op hou soc ltd435

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 35 units booked (0%), as the promoter reported to MahaRERA

1BHK · 21 units1RK · 14 units
TypeCarpet areaUnitsBooked
1BHK34.1 sq m · 367 sq ft70
1BHK34.31 sq m · 369 sq ft70
1BHK41.34 sq m · 445 sq ft70
1RK25.83 sq m · 278 sq ft70
1RK25.97 sq m · 280 sq ft70

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 39 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardsrbldrs pan.pdf · uploaded 25 Aug 2017Source

Legal

  • Legal Title reporttitle ajanta.pdf · uploaded 25 Aug 2017Source
  • Declaration Form Bnotarized b form ajnta_1.pdf · uploaded 25 Sep 2017Source
  • Declaration Form Bnotarized b form ajnta.pdf · uploaded 25 Sep 2017Source

Migrated

  • 1 PAN Cardsrbldrs pan.pdf · uploaded 25 Aug 2017Source
  • 1 Copy of the legal title reporttitle ajanta.pdf · uploaded 25 Aug 2017Source
  • 1 Details of encumbrancestitle ajanta.pdf · uploaded 25 Aug 2017Source
Show all 40 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)appd plan ajanta_3.pdf · uploaded 25 Aug 2017Source
  • 1 Building Plan Approval (IOD)ajanta cc.pdf · uploaded 25 Aug 2017Source
  • 2 Building Plan Approval (IOD)ajanta cc (1).pdf · uploaded 25 Aug 2017Source
  • 3 Building Plan Approval (IOD)ajanta cc_5.pdf · uploaded 25 Aug 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentajanta cc.pdf · uploaded 25 Aug 2017Source
  • 1 Certificates of CA (Form 3)CA cert ajanta.pdf · uploaded 25 Aug 2017Source
  • 1 Proforma of Allotment letterAjanta allotment.pdf · uploaded 21 Sep 2017Source
  • 1 Declaration in FORM Bnotarized b form ajnta_1.pdf · uploaded 25 Sep 2017Source
  • 2 Declaration in FORM Bnotarized b form ajnta.pdf · uploaded 25 Sep 2017Source
  • 2 Proforma of Allotment letteragreement letter ajanta.pdf · uploaded 25 Sep 2017Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate.pdf · uploaded 30 Oct 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)form 5.pdf · uploaded 30 Oct 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)FORM 5 - 17-18.pdf · uploaded 25 Nov 2019Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 20 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)form 2a.pdf · uploaded 20 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)form 2a.pdf · uploaded 20 Feb 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)form 2a.pdf · uploaded 20 Feb 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2_compressed.pdf · uploaded 21 Feb 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)S R BUILDERS FY 19-20.pdf · uploaded 4 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)S R BUILDERS FY 20-21.pdf · uploaded 4 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)S R BUILDERS FY 21-22.pdf · uploaded 4 Mar 2023Source
  • 2 a Details of encumbrances concerned to FinanceAdobe Scan Jan 18, 2024 (1).pdf · uploaded 18 Jan 2024Source
  • 1 b Details of encumbrances concerned to LegalAdobe Scan Jan 18, 2024 (1).pdf · uploaded 18 Jan 2024Source
  • Withdrawal Update Form 1FORM 1.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 2FORM 2.pdf · uploaded 24 Sep 2025Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 24 Sep 2025Source

Technical

  • Documentappd plan ajanta_3.pdf · uploaded 25 Aug 2017Source
  • Documentajanta cc.pdf · uploaded 25 Aug 2017Source
  • Documentajanta cc (1).pdf · uploaded 25 Aug 2017Source
  • Documentajanta cc_5.pdf · uploaded 25 Aug 2017Source

Technical (Architect)

  • DocumentFORM 1.pdf · uploaded 23 Sep 2025Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 23 Sep 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Vasai-Virar City (M Corp), Vasai taluka

Survey, CTS, gat or plot numbers

S. no. 188 H. no.3

Boundaries

North
28
South
16
East
30
West
31

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Architectmahesh mistry—
Chartered accountantashwin n nair—
Chartered accountantD S Solanki & Co—
Engineermahesh mistry—
OtherKeshav R Vasani—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology