Neelkanth Apt Phase II
Certificate SignedSajan, Palghar 401605 |Promoter: Om Developers
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 3
- Unit types
- 1BHK36 units in all
- Address
- 69, 70, Sajan, Sajan VillagePIN 401605
- Designated bank account
- 212
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 6 years
The latest completion date on record passed 1 year and 4 months ago.
- Registered
- 2 Feb 2018
- Promised
- 1 Jun 2019
- Revised
- 30 Jun 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000015141 | 2 Feb 2018 | 1 Jun 2019 | 30 Jun 2025 | Om Developers | Project page |
3 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Neelkanth Phase II Wing A | 4 | 12 |
| Neelkanth Phase II Wing B | 4 | 12 |
| Neelkanth Phase II Wing C | 4 | 12 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
3 of 36 units booked (8%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Neelkanth Phase II Wing A | 1BHK | 37.33 sq m · 402 sq ft | 12 | 0 |
| Neelkanth Phase II Wing B | 1BHK | 37.33 sq m · 402 sq ft | 12 | 0 |
| Neelkanth Phase II Wing C | 1BHK | 37.33 sq m · 402 sq ft | 12 | 3 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 57 filings listed on MahaRERA's project page
Legal
Migrated
- 1 Copy of the legal title reporttitle certificate Om Dev comp.pdf · uploaded 31 Jan 2018Source
- 1 Details of encumbrancesDECLARATION NO ENCRUMBRANCES.pdf · uploaded 31 Jan 2018Source
- 1 Copy of Layout Approval (in case of layout)plan and layout approval om dev com.PDF · uploaded 31 Jan 2018Source
- 1 Building Plan Approval (IOD)BUILDING PLAN APPROVAL.pdf · uploaded 31 Jan 2018Source
Show all 59 documentsShow fewer documents
Migrated
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMNT CERT COMP.pdf · uploaded 31 Jan 2018Source
- 1 Declaration in FORM BAFFIDAVIT OM Dev comp.pdf · uploaded 31 Jan 2018Source
- 1 Certificates of CA (Form 3)CA CERTIFICATE FORM 3 COMP.pdf · uploaded 31 Jan 2018Source
- 1 Proforma of Allotment letterallotment letter om developers comp.pdf · uploaded 31 Jan 2018Source
- 2 Proforma of Allotment letterom developers rera agreement sample comp.pdf · uploaded 31 Jan 2018Source
- 2 Certificates of CA (Form 3)Form 3 Om developers.pdf · uploaded 12 Nov 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 a wing.pdf · uploaded 22 Nov 2021Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 B wing.pdf · uploaded 22 Nov 2021Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 C wing.pdf · uploaded 22 Nov 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 a wing.pdf · uploaded 22 Nov 2021Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 b wing.pdf · uploaded 22 Nov 2021Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 c wing.pdf · uploaded 22 Nov 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form 2 a wing.pdf · uploaded 22 Nov 2021Source
- 1 Certificates of CA (Form 3)Form-3 March 18_compressed.pdf · uploaded 16 Nov 2024Source
- 1 Certificates of CA (Form 3)form-3 March 19_compressed.pdf · uploaded 16 Nov 2024Source
- 1 Certificates of CA (Form 3)Form-3 March 20_compressed.pdf · uploaded 16 Nov 2024Source
- 1 Certificates of CA (Form 3)Form-3 March 21_compressed.pdf · uploaded 16 Nov 2024Source
- 1 Certificates of CA (Form 3)Form-3 March 22_compressed.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 March 18.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 March 19.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 March 20.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 March 21.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 March 22.pdf · uploaded 16 Nov 2024Source
- 1 Certificates of CA (Form 3)Form-3 March 18_compressed.pdf · uploaded 16 Nov 2024Source
- 2 Certificates of CA (Form 3)form-3 March 19_compressed.pdf · uploaded 16 Nov 2024Source
- 3 Certificates of CA (Form 3)Form-3 March 20_compressed.pdf · uploaded 16 Nov 2024Source
- 4 Certificates of CA (Form 3)Form-3 March 21_compressed.pdf · uploaded 16 Nov 2024Source
- 5 Certificates of CA (Form 3)Form-3 March 22_compressed.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 March 18.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 March 19.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 March 20.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 March 21.pdf · uploaded 16 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 March 22.pdf · uploaded 16 Nov 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 March 23.pdf · uploaded 26 Feb 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Om developer - Form 1 March 24_compressed.pdf · uploaded 26 Feb 2025Source
- 1 Certificates of CA (Form 3)Form 3 March 23_compressed.pdf · uploaded 26 Feb 2025Source
- 2 Certificates of CA (Form 3)Form 3 March 24_compressed.pdf · uploaded 26 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Om Developer - Form 2 March 23.pdf · uploaded 26 Feb 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Om Developer - Form 2 March 24.pdf · uploaded 26 Feb 2025Source
- 1 Disclosure of sold/ booked inventorysold booked March 23.pdf · uploaded 26 Feb 2025Source
- 2 Disclosure of sold/ booked inventorysold booked march 24.pdf · uploaded 26 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 March 23.pdf · uploaded 26 Feb 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form 5 March 24.pdf · uploaded 26 Feb 2025Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Sajan, Vikramgad taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- 9 Mtr Wide Layout Road
- South
- 6 Mtr Wide Layout Road
- East
- Plot No 68 And 71 Of Layout
- West
- Land Of Survey No 35
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Sachin Potdar | — |
Source: MahaRERA project page. Contact details are not shown.