Skip to content

Building Type-C · Nest Leaf

Palghar · RERA P99000019103

IDBLD_0916485 floorsPromised date passed
5Sanctioned habitable floorsregistration certificate
30 Jan 2026Revised completionpromised 30 Jan 2026
0 of 30Units bookedMahaRERA project page

Floors

5 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P99000019103 · registered 4 Jan 2019
Promised completion
30 Jan 2026
Revised completion
30 Jan 2026
Sanctioned habitable floors
5
ProjectId
20,095
ProjectName
Nest Leaf Phase-2
TotalUnitCount
0
ProjectBuildingId
20,935
BuildingNameNumber
Building Type-C
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P99000019103
ProjectBuildingWingsId
20,935
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Building Type-C
NoOfBuildingWingFloorProposed
5
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
5

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
FLAT24.6 m² (265 sq.ft)10
FLAT26.1 m² (281 sq.ft)20
FLAT26.6 m² (286 sq.ft)50
FLAT27 m² (291 sq.ft)80
FLAT27.1 m² (291 sq.ft)40
FLAT38.5 m² (414 sq.ft)50
FLAT39.7 m² (428 sq.ft)10
FLAT40.8 m² (439 sq.ft)40
Total300
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology