Palghar 401404 |Promoter: Giriraj Developers

15 Jan 2024Registered with MahaRERA
31 Dec 2029Promised completion
30 Apr 2030Revised completionPushed back 4 months
1Building
176Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—176 units in all
Address
26/2 27/2, Village Vevoor, VevoorPIN 401404
Designated bank account
41
Developed in phases
No

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
15 Jan 2024
Promised
31 Dec 2029
Revised
30 Apr 2030

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900005432915 Jan 202431 Dec 202930 Apr 2030Giriraj DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Mohan Complex12176

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

176 units registered

— · 176 units
TypeCarpet areaUnits
——176

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 105 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN - Giriraj Developers.pdf · uploaded 1 Nov 2023Source

Legal

  • Legal Title reportLegal Title.pdf · uploaded 1 Nov 2023Source
  • Legal Title reportFlow of Title.pdf · uploaded 1 Nov 2023Source
  • Declaration Form BForm B - Promoters.pdf · uploaded 1 Nov 2023Source
  • Other – LegalPartnership Deed - Giriraj.pdf · uploaded 19 Dec 2023Source
  • Other – LegalPartnership Deed Of Admission(C).pdf · uploaded 11 Feb 2025Source

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 5 May 2023Source
Show all 106 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN - Giriraj Developers.pdf · uploaded 1 Nov 2023Source
  • 1 Copy of the legal title reportLegal Title.pdf · uploaded 1 Nov 2023Source
  • 2 Copy of the legal title reportFlow of Title.pdf · uploaded 1 Nov 2023Source
  • 1 Copy of Layout Approval (in case of layout)Building Plan Layout.pdf · uploaded 1 Nov 2023Source
  • 1 Declaration in FORM BForm B - Promoters.pdf · uploaded 1 Nov 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate.pdf · uploaded 1 Nov 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 - Engineers Certificate.pdf · uploaded 1 Nov 2023Source
  • 1 CERSAI detailsCersai Report.pdf · uploaded 1 Nov 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation report - Allotment Letter.pdf · uploaded 1 Nov 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation report - Agreement of sale.pdf · uploaded 1 Nov 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Approval Plan.pdf · uploaded 2 Nov 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentBuilding Approval Plan (Eight Floor).pdf · uploaded 2 Nov 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration of Separate Bank Ac.pdf · uploaded 7 Nov 2023Source
  • 1 Disclosure of sold/ booked inventoryDiscloser Sold-Unsold.pdf · uploaded 8 Nov 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Dinesh Dube.pdf · uploaded 8 Nov 2023Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Kishor Dube.pdf · uploaded 8 Nov 2023Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Rajesh Dube.pdf · uploaded 8 Nov 2023Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Harish Meher.pdf · uploaded 8 Nov 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3.pdf · uploaded 11 Nov 2023Source
  • 1 Other – TechnicalDeclaration for Land Area.pdf · uploaded 11 Nov 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentLetter to Palghar NP.pdf · uploaded 20 Nov 2023Source
  • 1 a Details of encumbrances concerned to FinanceFinancial Encumbarance Letter.pdf · uploaded 22 Nov 2023Source
  • 2 a Details of encumbrances concerned to FinanceLegal Encumberance Letter.pdf · uploaded 22 Nov 2023Source
  • 1 b Details of encumbrances concerned to LegalFinancial Encumbarance Letter.pdf · uploaded 22 Nov 2023Source
  • 2 b Details of encumbrances concerned to LegalLegal Encumberance Letter.pdf · uploaded 22 Nov 2023Source
  • 3 Commencement Certificates / NA Order for plotted developmentArchitect Certificate.pdf · uploaded 7 Dec 2023Source
  • 4 Commencement Certificates / NA Order for plotted developmentSite Images.pdf · uploaded 7 Dec 2023Source
  • 5 Commencement Certificates / NA Order for plotted developmentCC Sent to MahaRERA by Athority.pdf · uploaded 7 Dec 2023Source
  • 1 Declaration about Commencement CertificateArchitect Certificate.pdf · uploaded 7 Dec 2023Source
  • 2 Declaration about Commencement CertificateCC Sent to MahaRERA by Athority.pdf · uploaded 7 Dec 2023Source
  • 1 Proforma of Agreement for saleGiriraj Developers-Sale Agreement Draft.pdf · uploaded 19 Dec 2023Source
  • 1 Proforma of Allotment letterAllotment Letter Format.pdf · uploaded 19 Dec 2023Source
  • 1 Other – LegalPartnership Deed - Giriraj.pdf · uploaded 19 Dec 2023Source
  • 6 Commencement Certificates / NA Order for plotted developmentGiriraj Developers.pdf · uploaded 3 Jan 2024Source
  • 7 Commencement Certificates / NA Order for plotted developmentAppendix-F.pdf · uploaded 6 Jan 2024Source
  • 3 Declaration about Commencement CertificateDeclaration about CC (Format D).pdf · uploaded 6 Jan 2024Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsAnnexure (A) - Shahzada Khan.pdf · uploaded 10 Feb 2024Source
  • 6 Disclosure of Interest in Other Real Estate OrganizationsAnnexure (A) - Arun Singh.pdf · uploaded 10 Feb 2024Source
  • 7 Disclosure of Interest in Other Real Estate OrganizationsAnnexure (A) - Jimmy AmrikSingh Bhullar.pdf · uploaded 10 Feb 2024Source
  • 8 Disclosure of Interest in Other Real Estate OrganizationsAnnexure (A) - Mahfuj Ahmad Khan.pdf · uploaded 10 Feb 2024Source
  • 9 Disclosure of Interest in Other Real Estate OrganizationsAnnexure (A) - Manoj Sudarshan Singh.pdf · uploaded 10 Feb 2024Source
  • 10 Disclosure of Interest in Other Real Estate OrganizationsAnnexure (A) - Mohammed Yunus.pdf · uploaded 10 Feb 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 as on 26-04-2024.pdf · uploaded 14 May 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 as on 31-03-2024.pdf · uploaded 14 May 2024Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Discloser.pdf · uploaded 14 May 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 as on 31-03-2024.pdf · uploaded 14 May 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 as on 30-06-2024.pdf · uploaded 20 Jul 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 as on 30-06-2024.pdf · uploaded 20 Jul 2024Source
  • 3 Disclosure of sold/ booked inventorySold Unsold.pdf · uploaded 20 Jul 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A 2023-24.pdf · uploaded 22 Jul 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Giriraj Developers - Form-3.pdf · uploaded 22 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM-5-ANNUAL REPORT ON STATEMENT OF ACCOUNTS-23-24.pdf · uploaded 15 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 as on 30-09-2024.pdf · uploaded 30 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 30th Sept 2024.pdf · uploaded 30 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 as on 30-09-2024.pdf · uploaded 30 Oct 2024Source
  • 1 Disclosure of sold/ booked inventorySOLD-UNSOLD DETAILS.pdf · uploaded 27 Nov 2024Source
  • 1 Other – LegalPartnership Deed Of Admission(C).pdf · uploaded 11 Feb 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Dec-24.pdf · uploaded 7 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 Dec-24.pdf · uploaded 7 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Dec-24.pdf · uploaded 7 Mar 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD DETAILS.pdf · uploaded 7 Mar 2025Source
  • Withdrawal Update Form 1FORM 1 JUN 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 SEP 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 DEC 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 MAR 26.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 MAR 26.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 JUN 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 SEP 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 1FORM 2 DEC 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 1FORM 1 DEC 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 JUN 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 SEP 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 DEC 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 MAR 26.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 MAR 26.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 JUN 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 SEP 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 DEC 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 2FORM 2 DEC 25.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 JUNE 25 SIGNED.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 SEP 25 SIGNED.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 DEC 25 SIGNED_compressed.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 MAR 26SIGNED.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 MAR 26SIGNED.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 JUNE 25 SIGNED.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 SEP 25 SIGNED.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 DEC 25 SIGNED_compressed.pdf · uploaded 2 Jul 2026Source
  • Withdrawal Update Form 3FORM 3 DEC 25 SIGNED_compressed.pdf · uploaded 2 Jul 2026Source

Technical

  • DocumentBuilding Plan Layout.pdf · uploaded 1 Nov 2023Source
  • DocumentBuilding Approval Plan.pdf · uploaded 2 Nov 2023Source
  • DocumentBuilding Approval Plan (Eight Floor).pdf · uploaded 2 Nov 2023Source
  • Other – TechnicalDeclaration for Land Area.pdf · uploaded 11 Nov 2023Source

Technical (Architect)

  • DocumentFORM 1 as on 30-09-2024.pdf · uploaded 30 Oct 2024Source
  • DocumentForm 1 Dec-24.pdf · uploaded 7 Mar 2025Source
  • DocumentFORM 1 DEC 25.pdf · uploaded 2 Jul 2026Source

Technical (Engineer)

  • DocumentFORM 2 as on 30-09-2024.pdf · uploaded 30 Oct 2024Source
  • DocumentForm 2 Dec-24.pdf · uploaded 7 Mar 2025Source
  • DocumentFORM 2 DEC 25.pdf · uploaded 2 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Palghar, Palghar taluka

Survey, CTS, gat or plot numbers

26/2 27/2

Boundaries

North
Palghar Manor Road
South
Property of Dhamoda
East
Property of Sheshnath Chauhan and Savita Barad
West
Property of Joshi

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAnjalis Associates - Shrikant Yevale—
Chartered accountantAshwin Nair—
Chartered accountantBharat Dhonde & Co.—
EngineerDarsh Consult - Yogesh Vaja—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology