Makvin Hillview Towers

Certificate Signed

Kopri, Palghar 401305 |Promoter: Makwana Associates

Residential / Group HousingRERAP99000048052
8 Dec 2022Registered with MahaRERA
31 Dec 2028Promised completion
30 Apr 2029Revised completionPushed back 4 months
1Building
222Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, Shop222 units in all
Address
S. No.114, H No. A/1 & A2, S No 115 H No 1, S No 118 H No 3&4, S No 121 H No19/B, 19/C, 20/1, 20/3 & 21, Chandansar Road, Kopri NakaPIN 401305
Designated bank account
19
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.48034, 72.82276
Makvin Hillview Towers is at latitude 19.48034, longitude 72.82276.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
8 Dec 2022
Promised
31 Dec 2028
Revised
30 Apr 2029

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000480528 Dec 202231 Dec 202830 Apr 2029Makwana AssociatesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Makvin Hillview Towers- A, B Wing19222

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 222 units booked (0%), as the promoter reported to MahaRERA

1BHK · 122 units2BHK · 90 unitsShop · 10 units
TypeCarpet areaUnitsBooked
1BHK28.5 sq m · 307 sq ft180
1BHK28.65 sq m · 308 sq ft360
1BHK28.66 sq m · 308 sq ft680
2BHK37.91 sq m · 408 sq ft180
2BHK39.24 sq m · 422 sq ft360
2BHK39.98 sq m · 430 sq ft180
2BHK42.74 sq m · 460 sq ft180
Shop11.66 sq m · 126 sq ft20
Show all 14 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop12.75 sq m · 137 sq ft10
Shop14.99 sq m · 161 sq ft10
Shop15.26 sq m · 164 sq ft30
Shop16.16 sq m · 174 sq ft10
Shop17.11 sq m · 184 sq ft10
Shop23.49 sq m · 253 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 124 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardMakwana Associates pancard.pdf · uploaded 18 Oct 2022Source

Legal

  • Declaration Form BFORM B.pdf · uploaded 18 Oct 2022Source
  • Legal Title reporttitle report final upload.pdf · uploaded 25 Nov 2022Source
  • Other – LegalCONVEYANCE-114 A-1,A-2,A115-1.pdf · uploaded 15 Jun 2024Source
  • Other – LegalCONVEYANCE-121-19C.pdf · uploaded 15 Jun 2024Source

Migrated

  • 1 PAN CardMakwana Associates pancard.pdf · uploaded 18 Oct 2022Source
  • 1 a Details of encumbrances concerned to FinanceEncumbrance upload.pdf · uploaded 18 Oct 2022Source
Show all 125 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalEncumbrance upload.pdf · uploaded 18 Oct 2022Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 18 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentGR AND TYPICAL.pdf · uploaded 18 Oct 2022Source
  • 2 Building Plan Approval / NA Order for plotted development8 AND 14.pdf · uploaded 18 Oct 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 18 Oct 2022Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 18 Oct 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 18 Oct 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 18 Oct 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaraion about Seprate Bank AC.pdf · uploaded 18 Oct 2022Source
  • 1 Other – TechnicalMCHI Certificate.pdf · uploaded 18 Oct 2022Source
  • 2 a Details of encumbrances concerned to FinanceEncumrance Upload.pdf · uploaded 17 Nov 2022Source
  • 2 b Details of encumbrances concerned to LegalEncumrance Upload.pdf · uploaded 17 Nov 2022Source
  • 1 Declaration about Commencement CertificateDeclaration About CC.pdf · uploaded 17 Nov 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Final Form 3.pdf · uploaded 17 Nov 2022Source
  • 1 Proforma of Allotment letterFORM OF ALLOTMENT LETTER - Final upload.pdf · uploaded 17 Nov 2022Source
  • 1 Deviation Report with respect to Allotment letterMakwana Associates_Deviation of Allotment Letter.pdf · uploaded 17 Nov 2022Source
  • 1 Copy of the legal title reporttitle report final upload.pdf · uploaded 25 Nov 2022Source
  • 1 CERSAI detailsCERSAI Report new.pdf · uploaded 25 Nov 2022Source
  • 2 CERSAI detailsDeclaration for CERSAI.pdf · uploaded 25 Nov 2022Source
  • 1 Proforma of Agreement for saleDraft Agreement Upload.pdf · uploaded 25 Nov 2022Source
  • 1 Deviation Report with respect to model copy of AgreementNew Dated Deviation.pdf · uploaded 25 Nov 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 Form 1 Qtr4.pdf · uploaded 11 May 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 Form 2 Qtr 4.pdf · uploaded 11 May 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 Final Form 3 Q4.pdf · uploaded 11 May 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Q2 23-24.pdf · uploaded 22 Dec 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 Form 2 23-24 Qtr 2.pdf · uploaded 22 Dec 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 Final Form 3 Q2 23-24.pdf · uploaded 22 Dec 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)22-23.pdf · uploaded 7 Feb 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 Form 1 Qtr4 FY 23-24.pdf · uploaded 15 Jun 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 Form 2 23-24 Qtr 4.pdf · uploaded 15 Jun 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)4 Final Form 3 Q4 23-24.pdf · uploaded 15 Jun 2024Source
  • 1 Other – LegalCONVEYANCE-114 A-1,A-2,A115-1.pdf · uploaded 15 Jun 2024Source
  • 2 Other – LegalCONVEYANCE-121-19C.pdf · uploaded 15 Jun 2024Source
  • 2 Proforma of Agreement for saleCarbon Rera New draft 20-7-2024 final.pdf · uploaded 20 Jul 2024Source
  • 2 Deviation Report with respect to model copy of AgreementDraft Agreement new Deviation - final 20-7-2024.pdf · uploaded 20 Jul 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)6 Form 1 Qtr2 FY 24-25.pdf · uploaded 9 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)7 Form 1 Qtr3 FY 24-25.pdf · uploaded 9 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)5 Final Form 3 Q2 24-25.pdf · uploaded 9 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)6 Final Form 3 Q3 24-25.pdf · uploaded 9 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 Form 2 24-25 Qtr 2.pdf · uploaded 9 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)2023-2024.pdf · uploaded 9 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 Form 2 24-25 Qtr 3.pdf · uploaded 13 Feb 2025Source
  • Form 2A (FY 2022-2023)22-23-1-1.pdf · uploaded 5 Oct 2025Source
  • Form 2A (FY 2023-2024)23-24-1-1.pdf · uploaded 5 Oct 2025Source
  • Form 2A (FY 2024-2025)24-25-1-1.pdf · uploaded 5 Oct 2025Source
  • Form 5 (FY 2022-2023)22-23.pdf · uploaded 5 Oct 2025Source
  • Form 5 (FY 2023-2024)2023-2024.pdf · uploaded 5 Oct 2025Source
  • Form 5 (FY 2024-2025)24-25.pdf · uploaded 5 Oct 2025Source
  • Disclosure of Sold and Booked Inventory22-23 Q3.pdf · uploaded 6 Oct 2025Source
  • Form 11 Form 1 at the time of registration.pdf · uploaded 6 Oct 2025Source
  • Form 21 Form 2.pdf · uploaded 6 Oct 2025Source
  • Form 31 Final Form 3.pdf · uploaded 6 Oct 2025Source
  • Disclosure of Sold and Booked Inventory22-23 Q4.pdf · uploaded 6 Oct 2025Source
  • Form 12 Form 1 Qtr4.pdf · uploaded 6 Oct 2025Source
  • Form 22 Form 2 Qtr 4.pdf · uploaded 6 Oct 2025Source
  • Form 32 Final Form 3 Q4.pdf · uploaded 6 Oct 2025Source
  • Form 18 Form 1 Qtr2 FY 24-25.pdf · uploaded 26 Nov 2025Source
  • Form 28 Form 2 24-25 Qtr 2.pdf · uploaded 26 Nov 2025Source
  • Form 35 Final Form 3 Q2 24-25.pdf · uploaded 26 Nov 2025Source
  • Disclosure of Sold and Booked Inventory24-25 Q2.pdf · uploaded 26 Nov 2025Source
  • Form 19 Form 1 Qtr3 FY 24-25.pdf · uploaded 26 Nov 2025Source
  • Form 29 Form 2 24-25 Qtr 3.pdf · uploaded 26 Nov 2025Source
  • Form 36 Final Form 3 Q3 24-25.pdf · uploaded 26 Nov 2025Source
  • Disclosure of Sold and Booked Inventory24-25 Q3.pdf · uploaded 26 Nov 2025Source
  • Form 110 Form 1 Qtr4 FY 24-25.pdf · uploaded 26 Nov 2025Source
  • Form 210 Form 2 24-25 Qtr 4.pdf · uploaded 26 Nov 2025Source
  • Form 37 Final Form 3 Q4 24-25.pdf · uploaded 26 Nov 2025Source
  • Disclosure of Sold and Booked Inventory24-25 Q4.pdf · uploaded 26 Nov 2025Source
  • Form 14 Form 1 Qtr2 FY 23-24.pdf · uploaded 26 Nov 2025Source
  • Form 24 Form 2 23-24 Qtr 2.pdf · uploaded 26 Nov 2025Source
  • Form 33 Final Form 3 Q2 23-24.pdf · uploaded 26 Nov 2025Source
  • Disclosure of Sold and Booked Inventory23-24 Q2.pdf · uploaded 26 Nov 2025Source
  • Form 16 Form 1 Qtr4 FY 23-24.pdf · uploaded 26 Nov 2025Source
  • Form 26 Form 2 23-24 Qtr 4.pdf · uploaded 26 Nov 2025Source
  • Form 34 Final Form 3 Q4 23-24.pdf · uploaded 26 Nov 2025Source
  • Disclosure of Sold and Booked Inventory23-24 Q4.pdf · uploaded 26 Nov 2025Source
  • Form 13 Form 1 Qtr1 FY 23-24.pdf · uploaded 18 Dec 2025Source
  • Form 23 Form 2 23-24 Qtr 1.pdf · uploaded 18 Dec 2025Source
  • Form 33 Final Form 3 Q1 23-24.pdf · uploaded 18 Dec 2025Source
  • Disclosure of Sold and Booked Inventory23-24 Q1.pdf · uploaded 18 Dec 2025Source
  • Form 15 Form 1 Qtr 3 FY 23-24.pdf · uploaded 18 Dec 2025Source
  • Form 25 Form 2 23-24 Qtr 3.pdf · uploaded 18 Dec 2025Source
  • Form 35 Final Form 3 Q3 23-24.pdf · uploaded 18 Dec 2025Source
  • Disclosure of Sold and Booked Inventory23-24 Q3.pdf · uploaded 18 Dec 2025Source
  • Form 17 Form 1 Qtr1 FY 24-25.pdf · uploaded 18 Dec 2025Source
  • Form 27 Form 2 24-25 Qtr 1.pdf · uploaded 18 Dec 2025Source
  • Form 37 Final Form 3 Q1 24-25.pdf · uploaded 18 Dec 2025Source
  • Disclosure of Sold and Booked Inventory24-25 Q1.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 111 Form 1 Qtr1 FY 25-26.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 112 Form 1 Qtr2 FY 25-26.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 211 Form 2 25-26 Qtr 1.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 212 Form 2 25-26 Qtr 2.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 310 Final Form 3 Q1 - 2025-26.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 311 Final Form 3 Q2 - 2025-26.pdf · uploaded 18 Dec 2025Source
  • Withdrawal Update Form 113 Form 1 Qtr3 FY 25-26.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 213 Form 2 25-26 Qtr 3.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 312 Final Form 3 Q3 - 2025-26.pdf · uploaded 4 Feb 2026Source
  • Withdrawal Update Form 114 Form 1 Qtr4 FY 25-26.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 114 Form 1 Qtr4 FY 25-26.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 214 Form 2 25-26 Qtr 4.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 214 Form 2 25-26 Qtr 4.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 313 Final Form 3 Q4- 2025-26.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 313 Final Form 3 Q4- 2025-26.pdf · uploaded 21 May 2026Source
  • Withdrawal Update Form 115 Form 1 Qtr1 FY 26-27.pdf · uploaded 18 Aug 2026Source
  • Withdrawal Update Form 215 Form 2 26-27 Qtr 1.pdf · uploaded 18 Aug 2026Source
  • Withdrawal Update Form 314 Final Form 3 Q1 - 2026-27.pdf · uploaded 18 Aug 2026Source

Technical

  • DocumentLAYOUT.pdf · uploaded 18 Oct 2022Source
  • DocumentGR AND TYPICAL.pdf · uploaded 18 Oct 2022Source
  • Document8 AND 14.pdf · uploaded 18 Oct 2022Source
  • Other – TechnicalMCHI Certificate.pdf · uploaded 18 Oct 2022Source
  • DocumentCC DTD 03-01-2022.pdf · uploaded 18 Dec 2025Source

Technical (Architect)

  • Document6 Form 1 Qtr2 FY 24-25.pdf · uploaded 9 Feb 2025Source
  • Document7 Form 1 Qtr3 FY 24-25.pdf · uploaded 9 Feb 2025Source
  • Document15 Form 1 Qtr1 FY 26-27.pdf · uploaded 18 Aug 2026Source

Technical (Engineer)

  • Document6 Form 2 24-25 Qtr 2.pdf · uploaded 9 Feb 2025Source
  • Document7 Form 2 24-25 Qtr 3.pdf · uploaded 13 Feb 2025Source
  • Document15 Form 2 26-27 Qtr 1.pdf · uploaded 18 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Kopri, Vasai taluka

Survey, CTS, gat or plot numbers

19/C20/120/3214A2H NO. A/1S. NO.114S NO 115 H NO 1S NO 118 H NO 3S NO 121 H NO19/B

Boundaries

North
Chandansar Road
South
Mountains
East
Sai Hill Nagar Co-Operative Housing Society
West
Mseb Office

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSanat Mehta—
Chartered accountantDolly Milan Ashar—
Chartered accountantMazhar H Khambaty—
Chartered accountantRakhi Chandak—
Chartered accountantShailendra Kumar Mishra—
EngineerAbhishek Lengare—
EngineerKarnav Makwana—

Source: MahaRERA project page. Contact details are not shown.